13. Contract Practise Flashcards
What if your client tell you the LADs (Liquidated and are to be £100,000 per week?
Firstly I would check the Liquidated and ascertained damages figure is based on a genuine pre-estimate of financial loss and explain in the event of LAD’s are to be applied, they would need to substantiate this figure
What are extensions of time?
Extensions of time adjust the completion date and relieves the contractor’s liability to pay liquidated damages
What are liquidated damages?
A genuine pre-estimate of the likely loss incurred by the employer should the completion date not be met
What must be in place before LDs can be deducted?
Employer must issue non completion certificate and a withholding notice
What if the employer suffered no loss or damage? (Liquidated damages)
It doesn’t matter the damages can still be deducted
What are the benefits of being able to grant an extension of time?
Advantage to the contractor is that is relieves the contractor’s liability damages for a delay they did not cause
It sets a new completion date with maintain’s the employers ability to deduct LDs if another delay occurs
What happens when ‘time is at large’
There is no contractual completion date.
The contractor only has the obligation to complete the works within a reasonable time
LDs cannot be claimed as there is no set date
What are the main elements you would include within an interim valuation?
Preliminaires
Measured work
Variations
Materials on and off site
Loss and expense
Retention
What needs to be in place for you to include payments for materials on site?
The materials should be for the works, they should be protected, delivered to programme and in reasonable quantity
What needs to be in place for you to include payments for materials off site?
Proof that ownership will transfer to the employer upon payment (vesting certificate)
Insurance until materials arrive at site
Materials are clearly labelled s for the sitr and set apart from other materials
A materials off site bond has been provided if required
What is a retention of title clause?
Where a subcontractor or supplier retains ownership of materials until they are paid for them by the contractor. This is why a vesting certificate is needed as the employer may subsequently pay for materials that are not owned by the contractor
How do you evaluate interim valuations?
This will depend on payment mechanism used however for example if lump sum is used, you will go to site and inspect thr works to form a view on the percentage of the works undertaken
You check for materials on site and off site
Value time related and fixed preliminaries items undertaken
Value any agreed variations
This then gets presented a gross valuation less previous payments made and retention then I would make my recommendation to the CA for them to prepare the certificate
How do stage payments work?
Each stage of the project and value assigned will be set out in the contract. When a stage is complete for example completion of concept design, the value assigned to that will be paid out.
What is retention?
It is a percentage of each interim certificate deducted and retained by the employer from each interim payment to the contractor
What is purpose of retention?
It provides an incentive for the contractor to rectify any defects within the contract defects liability period
When is the retention released to the contractor?
Half of the retention is released in the interim certificate after Practical completion
The remaining retention is released in the final certificate after the certificate of making good defects is issued
What is a retention bond?
This is a bond provided by the contractor instead of taking retention from interim payments. It should be equal to the same value as the retention deducted.
The requirement for the bond should be stated in the contract particulars
What happens if the contractor does not maintain the retention bond?
The employer can deduct retention from interim payments
Why might a retention bond be used?
If market conditions are difficult, this can be used to aid the contractor’s cashflow
What are the disadvantages of a retention bond?
It may reduce the incentive for the contractor’s incentive to complete making good defects.
It reduces the employer’s cashflow.
The employer would not get the interest accruing on the amount of retention bond
What is acceleration?
Acceleration is reducing the project timeline and therefore completion of work would be carried out in a shorter timeframe than anticipated or this is also used to carry out programme recovery as a result of delay
What options may be considered to achieve acceleration?
Resequencing works
Increasing the working time by using working longer hours
Increasing resources employed by using larger gangs
Changing the working methods
Increasing the incentives for example offering bonus payments
Which are the most and least efficient? (Resequencing works)
Resequencing the works can be the most cost effective and efficient
The least efficient would be increasinfg working time and resources employed which usually results in lower productivity
What is a fixed price contract?
Where the contract sums are limited to changes. It is an agreed price anything missed off by the contractor will be at their risk
What is a fluctuating price contract?
Where the contract sum is adjusted for changes in the costs of materials, labour
What is the date for completion?
The date stated in the contract for which the project will be finished by
How does this differ from completion date?
Completion date is when the project is finished wheres date for completion is the projected date that also considers the EOT
What does it mean when ‘time is at large’
No fixed completion date
The contractor must complete the works in a reasonable time
What is practical completion?
When the works are substantially complete with minor defects only
The employer is able to gain beneficial occupancy of the development
Half retention is released
The employer surrenders the right to apply liquidated damages
What is sectional completion
The completion and handover of the works to the employer in agreed stages
What is partial possession?
Where the employer requests and the contractor consents to the employer taking possession of the works
What is the difference between partial and sectional completion?
Sectional completion is a contractual obligation to hand over the section at the stated date, partial possession relies on the contractor’s consent
What does the architect have to do at partial possession?
Issue to a written statement to the contractor showing the relevant part and stating the relevant date
What is the rectification period?
This is the time period where the contractor has a contractual obligation to make good any defects
How long is the rectification period?
It will depend on the form of contract but typically 52 weeks
What is a non-completion certificate?
This is issued the employer to certify that the works or work section have not been completed by the relevant completion date
What are the consequences of a non-completion certificate?
Employer may apply LDs
What are the three ways that benefits can be transferred over under JCT contracts?
Collateral Warranties
Third party rights
Assignment