Contract Admin Flashcards
After valuation and certificate are issued, the client advised that they don’t have sufficient funding to make the payment. What would you do?
Once the certificate has been issued to the contractor they are contractually obliged to honour payment of the certificate and I therefore could not withhold the payment
What items do you include for on a valuation?
Prelims
Measured works
Materials on and off site
Variations
Claims
Retention
Previous payments
If an instruction was issued during the contract which involved the fabrication of a substantial amount of materials off site would you pay for them as off site materials within the valuation?
There is no obligation on the client to pay for materials off site if this is not identified in the contract document
How do you deal with the urgent Verbal Instructions?
If the instruction affects the critical path i would ensure it is reviewed with the contract admin. If the instruction is valid under the contract I would as soon as possible follow it up with writing
Could an email constitute a contract document?
NEC can be used within the building and civil engineering projects whereas JCT is specifically for building projects
NEC can be adopted to a number of bespoke contract strategies due to the various options available whereas JCT has a standard set of clauses
What is the defects liability period?
The defects liability period is the duration at the end of the contract, usually 52 weeks after the
Substantial Completion Certificate has been issued whereby the contractor undertakes to rectify any defects that arise within the structure at the contractors expense, providing they were due to materials & workmanship not being in accordance with the contract
The retention money retained may be used to cover the costs of making good.
What is a provisional sum?
A sum of money included in the contract for work that cannot be fully designed and costed at the time of tender or contract sum
What types of provisional sum are there?
Defined and undefined
Where are provisional sums defined?
New Rules of Measurement
What is a defined provisional sum?
A sum included in the contract for work that has not been completely designed at the time of contract sum agreement but for which certain information can be given about the extent of works
What is the contractor deemed to have allowed on the inclusion of a defined provisional sum?
They are deemed to have made proper allowances to carring out the work in their programme and preliminaries
This means that they are not entitled to an extension of time or extra prelims for carrying out the work
What if the actual work does not closely resemble the provisional sum?
This will be treated as a variation
This will entitle the contractor to an extension of time and extra preliminaries if appropriate
What is an undefined provisional sum?
A sum included for work for which there is minimal or no information at the time of contract sum agreements.
What is the contractor deemed to have allowed?
They are not deemed to have allowed for anything
Expenditure of the undefined provisional sum may carry addtional costs for programme or prelims
How are provisional sums dealt with in the final account?
The provisional sums included in the contract are deducted and the actual amount substituted
What are the risks associated with provisional sums?
The actual cost and time exceeds that allowed for in the provisional sum because the nature of the item changes between tender and instruction
What are the main suites of construction contracts?
JCT
NEC 4
ECC
ICE
FIDIC
What does ‘JCT’ stand for?
Joint Contract Tribunal
What does NEC stand for?
New Engineering Contract
What does ECC stand for?
Engineering and Construction contract
What does FIDIC stand for?
Federation internationale des ingenieurs civils
What does ICE stand for?
Institution of Civil Engineers
What is a bespoke contract?
Contract conditions that are drafted specifically for a particular project.
What the advantages of standard forms over bespoke contracts?
- They are written by legal experts.
- Rights and obligations of each party are clearly set out to the required level of detail.
- The time and expense of preparing a fresh document for each occasion is avoided.
What the disadvantages of standard forms over bespoke contracts?
They may not be appropriate to the needs of a particular project or client.
Using an inappropriate standard form for the project will cancel out any advantages.
When would use a bespoke contract rather than a standard form?
When specialist advisors can undertake the amendments as this requires great skill and knowledge.
Can you have an EOT without an L&E claim?
Yes an EOT does not automatically mean entitlement to L&E.