Project Finance Flashcards

1
Q

What is the purpose of cost reporting?

A

To inform the client in a construction project of the likely outturn cost of the construction project. The forecast of outturn costs may be expressed as a variance against a budget amount, or expressed in absolute terms

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the 3 cost reporting methods?

A
  1. Construction cost report
  2. Project cost report
  3. Detailed cost reports
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What factors can affect the outturn in construction costs?

A
  • Provisional Sums (defined/undefined)
  • Provisional quantities
  • Prime cost sums
  • Daywork allowances
  • Variations
  • Anticipated variations
  • Loss and expense
  • Fluctuations
  • Risk allowances
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

How frequent would you issue a cost report?

A

Cost reports must be regularly updated to inform the client of likely outturn costs. UK construction industry practice is to value work on a monthly basis. It is therefore recommended that cost reports are also updated and published on a monthly basis. There may be specific project or client requirements to report costs on a different frequency, e.g. quarterly, but this should be at the specific request of the client

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Who should the cost report be distributed to?

A

QS must take instruction from the client as to who the report should be issued to. This is due to the report containing confidential information

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is Loss & Expense?

A

Term often used to describe the additional costs incurred by a contractor as a result of disturbance to the regular progress of the works caused by matters either within the employer’s control or by breaches of contract by the employer.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is an example of an event which would lead to loss and expense?

A

Delay to the works caused by the employer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

How would you assess a claim for loss and expense?

A
  1. Prolongation costs (overheads & loss of profit)
  2. Finance charges
  3. Disruption
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are the two types of Cashflow Forecasting?

A
  • The cash flow forecast of a company (i.e., a contractor or consultant) – otherwise known as organisational cash flow.
  • The cash flow forecast of a particular construction contract or project – otherwise known as project cash flow
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is the purpose of cashflow forecasting?

A
  • Organisational cashflow - The cash flow forecast of a company will review and analyse the predicted incoming and outgoing cash for a set period of time (usually a year) and is often used for business and resource planning and for analysing the financial health of companies.
  • Project cashflow - deals specifically with the payments due under a particular construction contract. The construction contract cash flow will often inform a company’s overall cash flow as they are intrinsically linked.
  • In simple terms the purpose of a cash flow forecast is to ensure that the employer has an accurate assessment of what needs to be paid to the contractor and at what periods, therefore the employer’s bank or funder needs to be aware of drawdowns to manage the movement of funds to meet the contractual timescales of payment.
  • Monitor contractors progress on site
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What methods are used to forecast cashflow?

A
  • Dictated by the type of payment. I.e., Stage Payments, Milestone Payments, Payment against an activity schedule & valuation of works done to date on site
  • S Curve is typically used early in the design process to give employers a guide to the predicted cashflow.
  • Advanced cashflow forecasting - Once the project has been tendered or a contract has been entered into with the contractor then the cash flow forecasting can become more accurate. If the contract is for stage payments of milestone payments then it becomes relatively simple to plot this information and create an accurate cash flow forecast. For third party certification contracts the contractors programme and pricing document (Whether builders’ quantities or a bill of quantities) can be used to provide a more accurate cash flow forecast
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

How do you present your cashflow?

A

Typically, via excel, which is also presented in the form of a graph

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

The Construction Act 1996 and 2009

A
  • Providing the right to interim, periodic or stage payments.
  • Requiring that contracts should provide a
    mechanism to determine what payments
    become due and when, and a final date for
    payment.
    *Requiring that the payer gives the payee early
    communication of the amount he has paid or
    proposes to pay.
    *Providing that the payer may not withhold
    money from the sum due unless he has given
    an effective withholding notice to the payee.
  • Providing that the payee may suspend
    performance where a sum due is not paid in full
    by the final date for payment.
    *Prohibiting pay when paid clauses that link
    payment to payments received by the payer
    under a separate contract.
    *Providing a statutory right to refer disputes
    to adjudication. The adjudicator’s decision
    is binding until finally determined by legal
    proceedings or arbitration at the end of the
    contract.”
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Claims for loss and expense from
contractor

A

As soon as it becomes apparent that a claim may be made by the contractor, the employer should be made aware that the accuracy of the cash flow forecast may be compromised

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Why did you include artwork within your cost report on KN?

A

My client requested I include artwork within the report to be tracked as a cost as the scope of artwork was being developed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What was the value of the artwork?

A

I was advised by the artwork specialist to include a £50k budget within the report. This was managed and firmed up as the scope developed. Artwork was rented; therefore the cost was for installation and fees only

17
Q

What is a change management / control procedure?

A

Change control procedures are usually included in contracts between an employer and contractor or subcontractor. These procedures may describe the processes that should be followed when something detailed in the scope of works is replaced; this change can concern labour, materials or plant, or the location of the work, and could also be an amendment that affects the programme. The contract will typically contain a definition of what constitutes a change, and a mechanism for controlling it

18
Q

How did you implement this on Cubico

A
  • D&B 2016 - Introduced change control forms, which included a description of change, effects of the change from cost and programme perspective, and reason/benefit of the change
  • Any variation over £10k would require approval at board level
19
Q

What are the benefits of good change control procedure?

A

Ensures the client retains control of the budget and can make informed decisions on future variations with budget in mind

20
Q

What RICS guidance note would be applied to this?

A

Change control and management - GUIDANCE NOTE UK 1st edition, January 2021

21
Q

When making such a change, the person responsible should:

A
  • identify the reason or reasons for change
  • investigate the impact of items such as costs, timescales, and locations
  • strive to mitigate risks and maximise opportunities in relation to the overall objectives of the project
  • review and accept or reject the change
22
Q

How does the JCT deal with change?

A

Called Variations.