Case Study Flashcards
Why did you use the JCT SBC Without Quantities?
Design was not detailed enough for a quantified contract
Provides a lump sum Contract
What are the negatives of using a JCT without quantities
Not as much detail to value variations as there would be with a quantified Contract
What are the benefits of a concrete frame structure?
Fire resistant
Low maintenance costs
Flexible
What issues did you face as a result of the works being nearby to a occupied residential units and what did you do to mitigate?
Complaints from local neighbours due to noisy working
Noisy works between Monday to Friday 8am to 6pm. Saturdays 8am to 1pm
Why did you advise your client to use the traditional single stage procurement method?
- Sufficient time in the programme to enable this option
- Cost certainty
- Client retained control of the design
- Competitive Pricing
Why did you include Contractor Design Portion?
External Terrace Works + Co-ordination of services
Design was not in enough detail to tender these works at tender stage, therefore put the design element of these works onto the Contractor to manage
What is Contractors Design Portion?
- Where items of work are designed by the Contractor (usually on traditional contracts)
- Contractor assumes design responsibility for those works
How do we ascertain the CPD has been carried out correctly?
Performance specification is provided at tender stage, which the contractor provides proposals in response to this.
Proposals will be reviewed by the design team and either accepted, commented or rejected.
What is a Cat-B Fit-Out?
A Cat B fit out is the term used to describe a fully operational workplace that has been designed to a client’s unique specifications to make it their own.
* Partitions and doors
* Floor finishes
* Specialist lighting and facilities
* Cafés, tea points and kitchen areas
* Furniture
* Branded material and décor
Where can I find the definition of a Cat-B Fit-Out
- British Council for Offices - Guide to fit-out
- Most fit-out contractors websites
What did you have to do to negotiate landlord contributions?
- Agree contribution for carpet and floor boxes - £150k
- Value works associated with removing works from basebuild scope and including works within fit-out scope = £400k
There was a significant increase from CSA to FA. How did you deal with that?
Project Contingency = £500k
Landlord Contribution = £550k
Total = £1,050,000.00
Increase in from CSA to FA = £950k
I monitored the cost increase by producing monthly cost reports and presenting to my client. I also implemented a change control procedure to monitor each variation
What works were omitted from the basebuild works and included within the fit-out?
- Fit-out of the toilets, cycle storage and showers
- MEP works
What were some of the key variations, which increased the costs of the works?
- Construction Issue Drawings - £100k
- Desk + Room Booking System - £30k
- Additional Pattressing Requirements - £30k
What is a Steering Committee?
The Steering Committee’s role is to provide advice, ensure delivery of the project outputs and the achievement of project outcomes
What is a contingency?
Allowance for the unknown risks associated with a project
Why was 5% chosen?
During the early stages it was 10%, however as the design developed the contingency was reduced to 5%
Key Issue 1 (sensor taps/auto doors - tell me one thing that you did your review on?
I liaised with the Contractor and sub-contractors to understand the cost impact + programme impact of the changes
What is value engineering?
An exercise that involves most of the project team as the project develops. It is about taking a wider view and looking at the selection of materials and processes to see if a more cost-effective solution exists, that achieve the same design intent.
How does VE differ from VM?
a. VM is a method of highlighting possible opportunities to create value within a project and subsequently managing those solutions to ensure value is continuously delivered.
Whereas VE is a method used to eliminate any unnecessary costs, in order to achieve value for money on a project. VE methods and techniques can be used throughout the life cycle of a project, from strategic definition (very early design) to handover and close out.
How does partial possession work?
Handing over part of the site before official completion. NOT PRE AGREED
What is float in relation to programme?
The amount of time a task can be delayed without impacting the overall programme
What is deferment of possession?
Entitle the client to defer giving the contractor possession of the site for a period of up to six weeks unless a shorter period was stipulated in the contract particulars (it is probably unwise to reduce the period). This provision enables the client to defer possession without being in breach of contract.
Deferment of possession - what did the contractor have to do?
Notice of Delay - The Contractor shall notify the Employer as soon as the likely effect of a Relevant Matter on regular progress or the likely nature and extent of any loss and/or expense arising from a deferment of possession becomes (or should have become) reasonably apparent to him
Was the contractor entitled to any money & how was that calculated?
Loss & Expense – calculated by using rates from their prelims
– Prolongation Costs
– Finance Charges
– Disruption
– Cost of compiling claim
What is impediment by employer?
Relevant Event/Matter - Whereby the employer impedes the Contract Works
Name three Relevant Events?
- Architect/Contract Administrator’s instructions
- Fore Majeure
- Any impediment, prevention or default, whether by act or omission, by the Employer
Name three Relevant Matters?
- Architect/Contract Administrator’s instructions
- Any impediment, prevention or default, whether by act or omission, by the Employer
- Variations
How can Overheads + Profit be calculated?
- Hudson Formula - (Head Office overheads + profit) ÷ 100 x contract sum ÷ period in weeks x delay in weeks
- Emden Formula - (Overheads & profit / 100) x (contract sum x period of delay / contract period)
What do you understand by client care?
Continuous process or concept of understanding the clients requirements, suggestions, complaints etc. and analysing to find a solution.
- Defining the client brief
- Quality assurance procedures
- Client feedback meetings
Why is client care important?
- To retain existing clients
- Reduce likelihood of conflict
- Maintain strong reputation within the industry
How do you conduct yourself with a new client?
- Well mannered
- Well presented
- Respectful
- Friendly and enthusiastic
What is your company’s procedure for receiving client feedback?
My company has a Exception Experience Questionnaire which the client completes to provide feedback on the project