Mock 1 Flashcards
What is a contingency?
Allowance for the unknown risks associated with a project
How much was the contingency on this project?
£500k (approx. 5%)
Why was 5% contingency chosen?
During the early design stages it was 10%, however as the design developed the contingency was reduced to 5%
Why was a traditional procurement method used here?
- Sufficient time in the programme to allow this option
- Cost certainty
- Competitive pricing
Why was it a JCT without quantities?
- Project not complex enough to require BoQ
- Price was a lump sum
What impact could using a JCT without quantities have on the contractors tender?
Contractor may factor in more risk allowance to facilitate errors with quantities
Key Issue one (sensor taps/auto doors) – tell me one thing that you did your review on?
I liaised with contractor and sub-contractors to understand the cost impact of the changes
Other than costs, did you take any other factors into account?
Lead in time of materials & lifespan of the products
What is life cycle costing?
Process of economic decision analysis, which helps taking decisions on investments in new construction - Considers the overall cost of a product over its life cycle
Simple English, what is value engineering?
An exercise that involves most of the project team as the project develops. It is about taking a wider view and looking at the selection of materials, plant, equipment, and processes to see if a more cost-effective solution exists that will achieve the same project objectives
How does VE differ from VM?
VM is a method of highlighting possible opportunities to create value within a project and subsequently managing those solutions to ensure value is continuously delivered.
Whereas VE is a method used to eliminate any unnecessary costs, in order to achieve value for money on a project. VE methods and techniques can be used throughout the life cycle of a project, from strategic definition (very early design) to handover and close out
With regards to JCT without quants, this was for the fit out works. – what about the basebuild, was you part of the basebuild contract?
I was appointed for the fit-out works only. My only involvement on the basebuild was agreeing landlord contributions for works which were moved into the fit-out works
What input/access did you have to the basebuild project (you mentioned about monitoring the basebuild works/progress)?
Landlord contribution only
What would you do differently next time?
Ensure the project manager + designers have sufficient scope within their fee to closely monitor the progress of basebuild works
How does partial possession work?
Handing over part of the site before official completion. NOT PRE AGREED
What is “Float” in relation to programme?
The amount of time a task can be delayed without impacting the overall programme
What are some of the disadvantages of D&B from a client’s point of view?
- Client has to commit to concept design early in project
- Variations from brief may be difficult to agree
- Difficult to compare tenders
- Low quality
Single stage tendering – What are the advantages?
- Early cost certainty
- Competitive price
ASOS – Did you adjust the previous phase rates (negotiated tender)
No. The contractor agreed to maintain the previous phase rates
If you did make an allowance for inflation, how could you do that?
Take advice from the BCIS and apply and % to the rates
What advice did you give your client on KN within your tender report?
i. selection process
ii. documentation issued
iii. Tender Q&A / changes along the way
iv. Tender Analysis / detailed comparison
v. advice on the winner
vi. recommendation for contract
Tell me some methods of natural ventilation?
Openable windows
KN – you mention you made an allowance for acoustic products. Can you tell me what one of those was?
Acoustic ceiling baffles
Acoustic ceiling rafts – tell me what they are and how the work (what is the build-up?)
Sound absorbing/insulated core, wrapped in an acoustic felt – suspended from the ceiling
What is an acoustic ceiling raft’s purpose?
Designed to reduce reverberation and reflection of sound within rooms. By absorbing sound energy, they stop this energy from continuing to bounce around the room helping to reduce reverberation
Brunel House – Asbestos Survey – What was your role on advising the client of this asbestos problem?
I advised my client to instruct a specialist asbestos removal company to remove the identified asbestos to provide a safe environment for the contractor and future tenants
Feasibility Estimating – what is that?
Produced up to stage 1 - Feasibility estimates are used to give clients a rough order of magnitude of the cost of the project. These estimates are intended to be a tool to help a customer decide to proceed on the articulated quote or scale the project up or down keeping in mind several feasibilities may be required before moving to the conceptual phase
Why do we have the RIBA Plan of Works?
The RIBA Plan of Work organises the process of briefing, designing, constructing, and operating building projects into eight stages and explains the stage outcomes, core tasks and information exchanges required at each stage
Give me a take-off list under NRM1 for those partitions
- Walls + Partitions (stating thickness) measured = m2
- E/O internal walls for forming openings = Nr
Tell me how you went about it?
- I would review the architects drawings and identify the different types of partitions and then measure using Bluebeam measurement software
- Marked-up plans to reflect the take-off
- Review with the designer to ensure allowances and assumptions are correct
Tell me how you updated your cost plans on KN as the design moved through the RIBA stages?
i. Following receipt of the developed design information, I would carry out a take-off of the new information
ii. I would then update the cost plan to reflect these adjusting rates where necessary
iii. Finally, I would review the cost plan with the designers to ensure allowance are in line with their expectations
How did you deal with any unknowns or any queries
Q&A - Raise with relevant member of the design team
KN – you mentioned you reviewed the design with the design team and advised the client with some options/considerations, which include specialist lighting – What was your advice in relation to these specialist light fittings
My involvement was advising of the impact from a commercial perspective (i.e. costs + lead in time)