Project Finance Flashcards
What do you include in pre-construction cashflow?
- Design team fees
- HR fees
- Legal
- Surveys
Project Finance Periods.
- Pre- contract
- Tendering and contractor bid analysis
- Post-contract
Steps to issue/write a variation.
- Characterise the nature of your entitlement. …
- Check the contract. …
- Notify the client. …
- Wait for a direction to proceed before instructing. …
- Perform the work and claim payment (and an EOT if needed)
What is a variation order?
Ordinarily this would be in the form of an instruction, usually in writing, from the person named as administering the contract terms. So a “Variation Order” may also be referred to as an architect’s (or engineer’s) instruction, or “Change Instruction
How do you manage risk allowances?
Regularly review the element of risk, assess if there are mitigation measures to reduce cost/impact.
Example. Potential ground contamination was identified at ground investigations.
What is a risk allowance?
‘risk allowance’ refers to:
‘…the amount added to the base cost estimate for items that cannot be precisely predicted to arrive at the cost limit.’
What is contingency?
downside risk estimates that make allowance for the unknown risks associated with a project. Typically, contingencies refer to costs, and are amounts that are held in reserve to deal with unforeseen circumstances.
Standard 5%
How do you present the information (variation) to the client?
I :
- collate all the information
- organise
- refer to which element of the works it refers and any implications to other elements of the project
- arrange with the client to discuss the information
Sub-consultants appointment. What did you do?
Due diligence checks.
- Capability
- Check that the company exists
- Financial status. Credit check, involving accounts filed at Companies House
- Past work examples and references.
- Sign the client terms of payment. that were 60 days.
- Check their PI cover levels
How do you draft a subcontractor agreement?
I managed the appointments not drafted the agreement.
I provided the:
- Needs of the project and scope of works. I checked with the relevant parties before issuing.
- Clarified the terms of payment
- Ensure that they returned the documents signed and that the client signed them
- I agreed the time scales for the surveys under their appointment.
- I also reviewed the PI levels
-
How did you review the invoices issued to you?
The invoices were sent to our finance team with the PO for that specific survey. On recipe the Finance team will contact be asking for legitimacy, once confirmed it was issued to the client for payment.
Following the confirmation I log the invoice and review the cash flow.
Boston £1m.
How did you managed the variations? Example
Drainage design.
assess against the contract if the contractor was entitled to the variation.
I requested revised design, and associated costs. Review them with the QS.
Arrange meting with the client to present the information.
Boston. Time scales to review the variation?
Boston was JCT contract. I ensured the variations were dealt with diligence to avoid any potential delay in the project.
Toilet refurb. Unforeseen existing conditions. Can you name one?
A structural bracing was found when stripping out the existing toilet.
The drainage connection point wasn’t in the specified location and a re-design was required.
What is the difference between funding and financing?
Funding
• A funding source provides money that will be used to as capital for a project without any
repayment being required
• Common sources of funding include government grants and private donations.
Financing
• Financing refers to arrangements that make capital available in return for future repayments.
• Financial capital often comes in the form of debt such as a mortgage loan or a development
loan from a bank
• The repayments are normally made over an agreed period of time plus interest
What is meant by the term SPV?
• An SPV or Special Purpose Vehicle is created as a separate company with its own balance sheet.
• The SPV creates a commercial entity that is separate from a parent company
• SPV’s are normally utilised to undertake higher risk projects whilst minimising the negative
financial affects the project may have on the parent company in the event they become loss making.
What is the difference between corporate financing and project financing?
Corporate Finance
• Corporate finance is where the borrower, developer or sponsor company look to leverage their
organisations financial strength to borrow working capital for the project under consideration
• The corporate entity requests capital from private lenders based on the demonstration of its
financial strength
• If the organisation can demonstrate that is has sufficient assets to serve as collateral to
cover the loan amount, a good credit rating and stable revenue projections it should be approved by
the respective lender in their application
Project Finance
• Project Finance works on the basis of an SPV (Special Purpose vehicle) seeking to borrow
finance from a private lender
• Instead of looking to use an existing companies’ assets as collateral against the borrowed
amount, only the assets of the project company are used
• SPV’s are commonly used by project sponsors to ensure the project is built, financed and
operated
• Because the SPV does not possess a credit rating, private lenders will focus on the
sustainability of the project and its business model prior to approving the loan amount
How would you create a cashflow forecast?
• Establish the construction programme and contract value
• The costs from the contract sum would be allocated to each of the activities shown on the
programme
• Fee draw down schedules could also be used to plot expenditure on the cash flow
• Alternatively historic project cashflows or computer programmes could be utilised to undertake
a high level cashflow forecast typically based on an S-curve graph
What are the benefits of compiling a cashflow forecast?
• This allows the employer to gain an understanding of financial requirements over the duration
of the project
• It can also serve as a benchmark to check valuations against
• Lag of expenditure can be an indication of financial difficulties
• The cashflow can also be compared against the valuations to determine if the contractor is
behind or ahead of programme
What would you include in a financial report?
- a) Contract sum
- b) Instructed variations
- c) Potential future variations as advanced warnings
- d) Claims
- e) Anticipated final account total
- f) Total of certified payments
What is the purpose of a financial report?
- To report against budgeted values and act as a working cost check on the project budget
- To give the Client an understanding of any savings or additional monies required
- To report on contract progress against pre-contract predictions.
RICS Practice Standards - Valuing Change 2010
Includes JCT and NEC
JCT What 3 methods are there of obtaining a cost for variations?
- On project X under the JCT form adopted:
- Agreement between the employer and contractor
- A schedule 2 quotation
- Valuation by the QS under the valuation rules
What costs does the quotation contain?
- a) Value of the work
- b) Any adjustment of time
- c) Money in lieu of direct loss and expense
- d) The fair and reasonable cost of preparing the quotation
What costs is the contractor entitled to if the quote is rejected?
• The fair and reasonable cost of preparing the quote, as long as the quote itself was fair
What are the valuation rules?
• There are three rules for measurable work:
• a) If it is of a similar character, quantity and in the same conditions as existing work, then
the bill rates should be used
• b) If it is of a similar character, but different quantity or conditions, the bill rates
should be used as a basis but a fair allowance should be made to take account of the difference
• c) If it is not of a similar character, fair rates and prices should be used
What about non-measurable work?
• Should be valued by dayworks
What is dayworks?
• The prime (actual) cost of all the materials, labour and plant used in carrying out the work,
along with the % additions to each category as set out in the contract
What document should the prime cost be calculated in accordance with?
• Should be calculated in accordance with the ‘Definition of the Prime Cost of daywork carried out under Building Contracts’ published by the RICS
What is quantum meruit?
Translates as ‘what he deserves’ i.e. fair and reasonable
What is loss and/or expense?
• Reimburses the contractor for direct loss and/or expense incurred in carrying out additional work or from an employer’s breach of contract