Programming and Planning Flashcards
Define the key elements on a programme
Critical paths
Float
Milestones
Interdependencies
Braintree development. 3 interratled projects. How did you create the master programme?
I included the project duration for each project and assess the best sequence of taks, critical ones.
L3. Bingham. What advise did you give the client in regards the programme and the cabinet days?
I reviewed the programme jointly with the client, and as the cabinet days were fixed I assessed which dates will align better with the programme. Then I present them to the client.
L3 Bingham. Time scales for Stakeholders inputs.
I reviewed with he client the different stakeholders and which areas they will be providing their input. Then I discuss it in shape of workshop with the design team, and provide a schedule to the client of when the inputs will be required.
L3 Bingham. Why did you advise to progress with the tender despite the design change?
It was key to achieve December cabinet date. The programme was tight to review and analyse the tender returns, any delays in issuing the tender with impact the time for the revision.
L3 Toilet Refurb.£1.8m. Why there were consecutive programme delays?
This were caused by Venesta ( cubicle panels) deliveries not being met.
L3 Toilet refurb. What advise did you give to the client to overcome the delays?
Re- sequence of the works to prioritise the critical items.
L3 Boston £1m. What advise did you give the client in regards S278. Road closure and drainage connection.2.
Re-design of the drainage connection to avoid the road closure and the associate programme delays.
What is concurrent delay?
• Where one or more events occur at the same time that are caused by different parties involved
in a project
• These events will typically occur independently of each other
• Both events have an affect on the completion date of the project
• In the case of City Inn vs Shepherd Construction, there was no dominant cause of delay – The
Scottish Appeal Court decided that apportioning delay was appropriate and concluded that:
- If a dominant cause can be identified this must be considered as the relevant event resulting
in the impact on the completion date
- If no dominant cause can be identified an apportionment should be made in a fair and
reasonable way
What is the critical path on a construction programme?
• The critical path is the longest sequence of activities that must be completed to successfully
conclude a project
• It is essentially the route which represents the bottleneck of the project
• A reduction of the duration of the project is only possible if the critical path activities
can be shortened
• Activities on the critical path are known as critical activities because if they are delayed
the whole project will be delayed
What are the benefits of the critical path method?
- Reduction in delays
- Visualise dependencies
- Improve organisation
- Optimise efficiency
- Float calculation
How would you compile a programme for a new project?
• I would first understand the purpose and the level of detail required
• Identify All activities including project deliverables, key milestones and contractual requirements
• The durations associated with each activity would be assigned
• If required the activities would be allocated into each of the RIBA work stages
• I would also identify the relationship between activities and link these accordingly paying
particular attention to critical path items
• Any float & programme contingency and critical path items would be identified
• Finally I would issue the programme to the team for comment and update as required
What are project milestones?
• A project milestone is a task of zero duration that shows an important achievement in a
project
• For example successful completion of the substructure, achieving a water proof building
envelope or topping out may be considered as significant milestones in the project
Q) What information does a programme typically show?
- Construction activities and sequence
- The durations of each activity
- Inter dependencies of each activity
- Key Project Milestones
- Critical Path
- Float (Programme Contingency)
- Overall Project Start and End Date
What is meant by the term programme float?
• Programme float is the amount of time an activity can be delayed without impacting on the
project’s critical path
• This can also be referred to as programme contingency