Project Documents & Process Where Created Flashcards
match the document description and what process it ties back to
Activity attributes
Detailed information about each individual activity ;
Define activities
Activity list
List of all the activities on the project;
Define Activities
Assumption log
List of all project assumptions and constraints. ;
Develop Project Charter
Basis of Estimates
Describes how schedule, cost, and resource estimates were developed. Also includes their confidence level and ranges;
Estimate activity duration, estimate costs, estimate activity resources
Change log
Lists and describes the status of the change requests that is being processed or have been processed
through the perform integrated change control process;
Perform Integrated Change Control
Cost Estimates
Cost of each individual activity;
Estimate Costs
Cost Forecasts
A prediction of how much the project will cost when
it completes based on the current work. ;
Control costs
Duration estimates
Amount of time needed to complete each activity on the project. ;
Estimate activity durations
Issue log
List of all issues on the project. Could include history type, description, priority, status, and resolution ;
Direct & Manage Project Work
Lessons Learned Register
List of all lessons learned throughout the project ;
Manage Project Knowledge
Milestone List
Description of milestones on a project. ;
Define Activities
Physical resource assignments
Assignments of the physical resources to the activities or work packages ; Acquire Resources
Project Calendars
A calendar view of what takes place on a day-to-day basis on the project.;
Develop Schedule
Project communications
Communicate in on the project by following the communications management plan ;
Manage Communications
Project Schedule
A detailed breakdown of the work that needs to be done in order to complete the project. Will include a bar chart, milestone chart, and the project schedule network diagram. ;
Develop Schedule