Misc Flashcards

1
Q

What method does PMIS use to build schedule?

A

Precedence Diagramminng

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What kind of costs can be scaled down and reduced?

A

Direct, Variable

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What tool is used to validate scope?

A

Inspection

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What can a critical path have? (possible, not necessary)

A

Zero, Posititive, or Negative Float

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What process is a fishbone diagram used for?

A

Identify Risk

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

REAM

A

Resource Assignment Matrix. shows what work is assigned to who

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

SEAM

A

Stakeholder Engagement Assessment Matrix, assess how to engage each stakeholder

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Project team assignments are an output of what excuting process?

A

Acquire Resources

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What close is not associated with a project close?

A

Procurement Close (often done with control procurements)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are the 3 most common sources of conflict?

A

Schedule, Priorities, Resources

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Unplanned Training

A

Training executed through conversation, observation, & project performance appraisals

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Cost Plus Percentage of Cost (contract)

A

Buyers pay all & costs are not limited. Highest risk

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Who is accountable for enforcing the team charter?

A

The team, they created it

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is the best process for adding requirements/features in an agile project?

A

ensure sufficient detail on user stories and add to Sprint Backlog

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Getting insurance for a storm is an example of what type of risk

A

Transfer - risk is now in the hands of insurance company

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Quality Audits

A

structured, independent process to determine if activities comply with an organization’s policies & procedures.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Transformational Leadership

A

Empowers, encourages, and inspires.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Transactional Leadership

A

Performance-focused. Goal and objective-oriented

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Laissez-faire Leadership

A

Allows the team to make their own decisions.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Interactional Leadership

A

Combines transactional, transformational, and charismatic qualities to suit the group dynamics.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

Charismatic Leadership

A

Energetic, inspiring, and passionate about convictions but may be motivated by personal goals.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

What is the last thing that should be done in the Close Project process?

A

Release project resources

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

When is the PM assigned?

A

Project manager is assigned during project initiating & project charter creation, not after it.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

What are outputs of Define Scope?

A

-Project Scope Statement
-Updates to project docs including: stakeholder register, requirements docs, and the requirements traceability matrix

25
Q

Resource Leveling

A

schedule network analysis technique. It is applied to a schedule that has already been analyzed by the critical path method.
-necessary when resources are over allocated
-keeps resource usage at a constant level

26
Q

6 Steps of Change Request

A

1.Document the change and analyze it for feasibility
2.Determine the costs and benefits of the change
3.Submit a change request
4.Perform the Integrated Change Control Process
5.Update the project management plan and project documents
6.Communicate the status of the change to relevant stakeholders

27
Q

What is 90% of the PMs time spent doing?

A

Communications

28
Q

Where are all delays tracked?

A

Issue Log

delays in overall schedule may warrant change request

29
Q

Who can add to the Product Backlog?

A

PM, Product Manager, Project Team, Customer

30
Q

When a change request is approved, what process is used to implement the change?

A

Direct & Manage Project Work

31
Q

Where are exclusions to scope noted?

A

Scope Statement

32
Q

Resolving conflict is done through which process?

A

Manage Team

33
Q

Crashing

A

scheduled compression method where you add more resources to complete a project sooner

34
Q

Fast Tracking

A

Running activities in parallel to complete a project sooner

35
Q

Is CPI is overbudget and SPI is ahead of schedule, what is taking place?

A

Crashing

36
Q

Cost Aggregation

A

Tool used in Determine Budget

Done after costs are assigned (Estimate Costs is completed)

37
Q

Which process applications do not increase cost?

A

Fast Tracking
Resource Leveling

38
Q

Where is positive risk accounted for?

A

Risk Register

NOT included in Risk Management plan

39
Q

Attribute Sample

A

measurement that is pass/fail or good/bad

40
Q

Statistical Independence

A

outcome of 2 events cannot affect eachother

41
Q

Mutually Exclusive

A

2 events that cannot happen at the same time

42
Q

Project Team Assisgnments

A

Recording of the team members and their roles and responsibilities for the project.

Documented in PM directory, Project Org chart and/or schedule

43
Q

What best describes the role of a sponsor in a project?

A

Helping to avoid unnecessary changes to the project objectives

44
Q

Whose job is to prioritize project changes?

A

Project Manager

45
Q

The most important thing to focus on in contract negotiations is:

A

To negotiate a deal that both parties are comfortable with.

46
Q

In an agile project, who owns quality?

A

Cross Functional Team

47
Q

Single-Source Seller

A

means there is only one seller the company wants to do business with.

48
Q

What is the preferred method for settlement of all claims and disputes in a contract?

A

Negotiation

49
Q

Acceptance (Risk)

A

choosing to deal with it when and if it occur

ex) sandbags for flooding from a storm

50
Q

which is the document that will list all possible threats and opportunities that could occur during the project?

A

Risk Register

51
Q

what is NOT included in the cost baseline?

A

Management Reserves (but they are included in budget)

52
Q

What is true of the schedule management plan?

A

Can be formal or informal, highly detailed or broad in nature depending on the project. Is a key input to “Define Activities”

53
Q

Who assists the PM in managing difficult stakeholders as needed?

A

Project Sponsor

54
Q

Risk Owner

A

-Responsible for planning a response plan,
ensuring the plan is implemented when needed, and taking any corrective actions needed to handle the risk during the implementation of the plan.

55
Q

What mindset contains 4 paired values + 12 principles?

A

Agile Manifesto

56
Q

Velocity

A

average number of story points an Agile team is completing in their sprints

57
Q

When conducting an Agile Suitability Assessment, What three areas are you looking at?

A

Culture, project itself, & the team

58
Q

Monte Carlo Simulation.

A

A method of identifying the potential impacts of risk and uncertainty using
multiple iterations of a computer model to develop a probability distribution of a range of outcomes that could result from a decision or course of action

59
Q

Net Promoter Score

A

An index that measures the willingness of customers to recommend
an organization’s products or services to others.