Formulas Flashcards
Budget at Completion (BAC)
Original budget of the project. (no formula)
Planned Value (PV)
PV= Planned % Complete x BAC
Amount of money worth of work we that should have been done on the project.
Earned Value (EV)
EV= Actual % Complete x BAC
Amount of money worth of work you actually did on the project.
Actual Cost (AC)
Amount of money you already spent on the project (no formula)
Cost Variance (CV)
CV = EV - AC
-The difference between the work done and money spent.
-This value should be positive for under
budget. Negative values indicate over budget
Cost Performance Index (CPI)
CPI = EV / AC
-The rate of how we are spending to actually earning on the project.
-This value should be 1 and over for projects under budget.
Schedule Variance (SV)
SV = EV - PV
-The difference between the amount of work we should have done vs. the amount actually done.
-Positive = ahead of schedule. Negative = behind schedule
Schedule Performance Index (SPI)
SPI = EV / PV
-The rate of how we are meeting the project
schedule.
-This value should be 1 and over for a project to be ahead of the schedule.
Estimate at Completion (EAC)
EAC = BAC / CPI
-Forecasting the total cost of the project at the end based on the current spending rate of the project.
Estimate to Completion (ETC)
ETC = EAC - AC
Forecasting the amount that will be needed to complete the current project based on the current performance.
Variance at Completion (VAC)
VAC = BAC - EAC
-The difference between the original budget and new forecasted budget.
-This value should be positive for projects that may end at or under budget
To-Complete Performance Index
(TCPI)
TCPI = (BAC – EV) / (BAC – AC)
The performance that needs to be met to finish the project within the budget.
Early Finish (EF)
ES + Duration - 1
part of critical path method
Late Start (LS)
LF - Duration + 1
part of critical path method
Total Float
LS - ES
LF - EF
subtracts shortest from longest time on the critical path. also called slack. if an activity has float/slack it is NOT on the critical path