Formulas Flashcards

1
Q

Budget at Completion (BAC)

A

Original budget of the project. (no formula)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Planned Value (PV)

A

PV= Planned % Complete x BAC

Amount of money worth of work we that should have been done on the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Earned Value (EV)

A

EV= Actual % Complete x BAC

Amount of money worth of work you actually did on the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Actual Cost (AC)

A

Amount of money you already spent on the project (no formula)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Cost Variance (CV)

A

CV = EV - AC

-The difference between the work done and money spent.
-This value should be positive for under
budget. Negative values indicate over budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Cost Performance Index (CPI)

A

CPI = EV / AC

-The rate of how we are spending to actually earning on the project.
-This value should be 1 and over for projects under budget.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Schedule Variance (SV)

A

SV = EV - PV

-The difference between the amount of work we should have done vs. the amount actually done.
-Positive = ahead of schedule. Negative = behind schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Schedule Performance Index (SPI)

A

SPI = EV / PV

-The rate of how we are meeting the project
schedule.
-This value should be 1 and over for a project to be ahead of the schedule.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Estimate at Completion (EAC)

A

EAC = BAC / CPI
-Forecasting the total cost of the project at the end based on the current spending rate of the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Estimate to Completion (ETC)

A

ETC = EAC - AC

Forecasting the amount that will be needed to complete the current project based on the current performance.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Variance at Completion (VAC)

A

VAC = BAC - EAC

-The difference between the original budget and new forecasted budget.
-This value should be positive for projects that may end at or under budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

To-Complete Performance Index
(TCPI)

A

TCPI = (BAC – EV) / (BAC – AC)

The performance that needs to be met to finish the project within the budget.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Early Finish (EF)

A

ES + Duration - 1

part of critical path method

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Late Start (LS)

A

LF - Duration + 1

part of critical path method

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Total Float

A

LS - ES
LF - EF

subtracts shortest from longest time on the critical path. also called slack. if an activity has float/slack it is NOT on the critical path

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Standard Deviation of an Activity (SD)

A

(P-O)/6

gives range of an estimate

17
Q

Activity Variance

A

SD^2

18
Q

Triangular Expected Activity Duration/Cost

A

(O + M + P) / 3

non weighted avg

19
Q

PERT/Beta Expected Activity Duration/Cost

A

(O + 4M + P) / 6

weighted avg formula to predict length of activities and the project
O=optimistic
R/M=realistic, most likely
P= pessimistic

20
Q

Present Value

A

FV / (1 + i)^n

21
Q

Critical Path Method

A

-Longest path = critical path
-Contains no float or slack
-Any delays on critical path will delay the whole project

22
Q

Free Float

A

FF= ES of Next Activity - EF of current Activity - 1

the amount you can delay an activity, without delaying the project

23
Q

Communication Channels Formula

A

N(N - 1) / 2

n= # of stakeholders

24
Q
A