Project Cost Management Flashcards
What are the 8 parameters normally established by the cost management plan?
- Units of measure
- Level of precision
- Level of accuracy
- Organizational procedure links
- Control thresholds
- Rules of performance measurements
- Reporting formats
- Process description
What is the 3-point estimate name PERT?
A technique for estimating that applies a weighted average of optimistic, pessimistic, and most likely estimates when there is uncertainty with the individual activity estimates.
What are the 4 EVM status measures?
- SV - schedule variance
- CV - cost variance
- SPI - schedule performance index
- CPI - cost performance index
What are some resources for which cost estimates should be developed on a project?
Labor Materials Equipment Services Facilities Inflation allowance Contingency Cost of financing
What are the 2 main categories of cost in cost of quality?
Conformance
Nonconformance
What are the 5 tools and techniques for the Determine Budget process?
- Cost aggregation
- Reserve analysis
- Expert judgement
- Historical relationships
- Funding limit reconciliation
What are the 6 tools and techniques for the Control Costs process?
- Earned value management
- Forecasting
- To-complete performance index (TCPI)
- Performance reviews
- Project management software
- Reserve analysis
What is the Estimate Costs process?
The process of developing an approximation of the monetary resources needed to complete project activities.
What is analogous estimating?
A technique for estimating the duration or cost of an activity or a project using historical data from a similar activity or project.
What are the 3 PERT estimates?
- Most likely (Cm)
- Optimistic (Co)
- Pessimistic (Cp)
What are the 4 of the different ways to determine Earned Value (EV)?
- Fixed formula rate
- Weighted milestone
- Apportioned effort
- Percent complete
In the Initiation phase, what is the cost estimate called? What is its range?
ROM (rough order of magnitude)
Range = -25% to +75%
What are the 7 inputs to the Estimate Costs process?
- Cost management plan
- Human resouce management plan
- Scope baseline
- Project schedule
- Risk register
- Enterprise enviornmental factors
- Organizational process assets
What are the 3 outputs of the Determine Budget process?
- Cost baseline
- Project funding requirements
- Project document updates
What are the 10 tools and techniques for Estimate Costs?
- Expert judgement
- Analogous estimating
- Parametric estimating
- Bottom-up estimating
- Three-point estimating
- Reserve analysis
- Cost of quality
- Project management software
- Vendor bid analysis
- Group decision-making techniques
What is PV (planned value)?
The authorized budget assigned to scheduled work.
What does the term ETC mean?
Estimate to complete
What are the formulas for SV (scheduled variance) and CV (cost variance)?
SV = EV-PV CV = EV-AC
What is the general form of the EAC formula?
EAC = AC + ETC