Formulas Flashcards
Actual Cost (AC) or Actual Cost of Work Performed (ACWP)
Actual costs incurred by the project at a certain point in time.
“How much have we spent on the project today?”
Budget At Completion (BAC)
How much you estimate the project will cost at its completion.
Estimated and determined at the start of the project.
Planned Value (PV)
= Planned % Completed x BAC
Estimated value of the work to be completed by your project within a specific time period. Also used to calculate schedule variance (SV).
AKA: Budgeted Cost of Work Scheduled (BCWS)
Earned Value (EV)
= % completed x BAC
Estimated value of work completed by your project as of TODAY.
AKA: Budgeted Cost of Work Performed (BCWP)
Cost Variance (CV)
= Earned Value(EV) - Actual Cost (AC)
Are there any variations in the cost of the project. Is the project over or under budget.
Negative number over budget
Positive number under budget
0 is within budget
Schedule Variance (SV)
= Earned Value (EV) - Planned Value (PV)
less than zero - behind schedule
greater than zero - ahead of schedule
Are there any variations in the scheduling of the project.
Is the project behind or ahead of schedule.