Formulas Flashcards

1
Q

Actual Cost (AC) or Actual Cost of Work Performed (ACWP)

A

Actual costs incurred by the project at a certain point in time.
“How much have we spent on the project today?”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Budget At Completion (BAC)

A

How much you estimate the project will cost at its completion.

Estimated and determined at the start of the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Planned Value (PV)

A

= Planned % Completed x BAC

Estimated value of the work to be completed by your project within a specific time period. Also used to calculate schedule variance (SV).

AKA: Budgeted Cost of Work Scheduled (BCWS)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Earned Value (EV)

A

= % completed x BAC

Estimated value of work completed by your project as of TODAY.

AKA: Budgeted Cost of Work Performed (BCWP)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Cost Variance (CV)

A

= Earned Value(EV) - Actual Cost (AC)

Are there any variations in the cost of the project. Is the project over or under budget.

Negative number over budget
Positive number under budget

0 is within budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Schedule Variance (SV)

A

= Earned Value (EV) - Planned Value (PV)

less than zero - behind schedule
greater than zero - ahead of schedule

Are there any variations in the scheduling of the project.

Is the project behind or ahead of schedule.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly