Project+ 4 Flashcards
1
Q
Work Package
A
Lowest level of WBS
2
Q
Scope Management Plan
A
Describes :
- How scope changes will be handled
- The procedures for preparing the scope statement
- The procedures for preparing the WBS
3
Q
Ishikawa Diagram
A
Depicts every potential cause of a problem and the effect that each proposed solution will have on the problem
4
Q
Run Chart
A
Displays data observed or collected over time as plots on a line
5
Q
Scatter Diagram
A
Plots two numerical variables on a chart to determine whether there is a correlation between them
6
Q
Process Diagram
A
Shows step-by-step how a process works, where approvals or decisions need to be made and so on
7
Q
Scope Baseline
A
Includes
Scope Statement
WBS
WBS Dictionary
8
Q
Elements in the WBS dictionary
A
- Code of accounts identifier
- Description of the work of the component
- The organization responsible for completing the component
- Resources
- Cost estimates
- Criteria for acceptance
9
Q
Influence
A
- Influences can impact, change, or create a new constraint
- Scope creep is an example of an influence
- Change request is an influence
- Interaction between constraints is an example of an influence