Progress Flashcards

1
Q

What is an exception?

A

A situation where a deviation beyond agreed tolerance levels can be forecast.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What tolerances is the project manager responsible for dealing with?

A

Only those within the work package tolerances.

The team manager must raise work package tolerances and work package progress/issues to the PM.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

If there is going to be an issue or exceeded tolerance on a stage, who does the PM escalate to?

A

The project board

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

If the project board have exceptions or progress issues for the project that exceeds project tolerances, who do they escalate to?

A

CPC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Who produces a checkpoint report?

A

Typically produced by team manager for the PM with details of progress against work package.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Who produces a highlight report?

A

PM for the project board. Details progress for the whole project or management stage.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Who produces the end stage report?

A

PM for project board with details of progress towards each management stage (except last stage as this is an end stage report). Provides sufficient detail to ask for a project board decision on what to do next.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Who provides project tolerances and documents them in the project mandate?

A

CPC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Who provides the tolerances?

A

CPC for project tolerances
Executive for management stage tolerances
PM for work package tolerances

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

When a supplier is updating someone on a decision, which report is needed?

A

No report - just a work package

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

If something happens which causes a delay but it is still within time tolerance - what report should be used to record this?

A

Checkpoint report as it is still within tolerance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

If there were problems throughout a stage and there are recommendations for future projects, what report is used to record this?

A

End stage report as this has the lessons log.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Are checkpoint reports time driven or event driven?

A

They are time driven not event driven. They are predetermined

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Can checkpoint reports be oral?

A

Yes and checkpoint reports can change in format and frequency at any time if agreed by relevant authority

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Is the issue register created in the starting up a project process?

A

No - the daily log is used to record issues until the register becomes available

How well did you know this?
1
Not at all
2
3
4
5
Perfectly