Procurement and Tendering Flashcards
What is the difference between single stage and two stage forms of procurement?
Traditionally, tendering involves just one stage, in which a tenderer is selected and appointed to carry out all of the works required. In Two-stage tendering, the tenderer is initially appointed only to carry out some of the works required. They are generally then appointed to carry out the rest of the works in a second stage.
What are the different types of procurement?
Traditional
D&B
Management contracting
Construction management
For the ECFRS floor refurbishment, what did the tender documents include?
ITT, form of tender, schedule of works and appendices, PCI and appendices
For the ECFRS Floor refurbishment, how do you decide how many contractors to invite to tender?
Four contractors to ensure competitive price achieved without flooding the tender process with too many contractors which could end with an unachievable price being obtained.
With regards to the ECFRS floor refurbishment, what was the tender route you took for this project?
Selective single stage tendering to four contractors.
Allows competition, simpler analysis of tenders, contractors that are trusted, less chance of misjudged tenders, fixed price achieved, design fully completed before tender
For the ECFRS floor refurbishment, why was the tender non-compliant?
It was not in accordance with the invitation to tender, a priced schedule of works was not provided.
With regards to the ECFRS floor refurbishment, how do you analyse the tenders using the matrix?
As set out in invitation to tender, 60% cost competitiveness and 40% quality, i scored each tender accordingly.
For the ECFRS floor refurbishment, what document would you review if you required guidance for tendering?
JCT Tendering Practice Note 2017
RICS Tendering Strategies Guidance Note
RICS E-Tendering Guidance Note
How do you determine a genuine error? Give an example?
An error in the tender deemed to be made sincerely.
Example is a single arithmetical error in adding, compared to a not genuine error of not pricing numerous items as could then have time to find out other tender sum.
For Appleford Court, how did you deal with any tender clarifications that arose?
-Queried whether contractors had clarifications
- Compiled all queries into one list and removed contractor details
- Liaised with consultants
- Provided answers and issued list to each contractor so they are tendering off the same basis
With regards to Appleford Court, what was included in your tender report?
Introduction
Tender returns
Tender analysis
Consideration of tenders
Comparison with budget and PTE
Recommendation
What areas to the tender matrix consider?
Cost - cheapest and arithmetical errors.
Quality - H&S, quality control, previous experience, company structure.
On your fire service floor refurbishment project, why did you end up recommending the contractor in your tender report?
Scored highest on scoring matrix.
Highest in terms of cost effectiveness, also scored relatively well for qualitative questions.
Provided reassurance for during tender queries that their overheads and profit were included within their costs.
What is the difference between single stage and two stage tender?
The main aim of the single-stage approach is to generate a firm price at the outset through a competitive tendering process, where-as the two-stage approach embraces a collaborative open book approach throughout the project.
What are the latest OJEU figures?
€5.3 million for central government and other contracting authorities works contracts.
€1 million for small lots works contract
What are the latest GPA figure thresholds?
For construction services the value is circa £5,000,000
For goods and services the value is £130,000, £200,000 or £400,000 depending on whether its a government entity.
What is the GPA? When is the OJEU still applicable?
Government Procurement Agreement. Advertising tenders publicly if over a certain threshold.
Applicable to new contracts post 1 january 2021.
How were the four contractors selected for the ECFRS floor refurbishment project?
- Tender Enquiry Letter to client’s preferred list
- Four contractors responded
- Alternatively could have issued pre qualification questionnaire
For the fire service floor refurbishment project, were the quality responses scored in any particular way?
Yes 40% scoring for quality and split up so percentages for each quality question.
Scores were provided for each quality question, based on detail and context as per chart included in ITT.
In regards to the Appleford Court project, what is the purpose of issuing tender query lists?
To ensure the tender is accurate and errors are identified so disputes at a later date can be minimised.
In regards to the Appleford Court project, what is the purpose of issuing a tender clarifications list?
To clarify anything which isnt clear prior to the return of tenders and ensures an accurate and reflective price is obtained from each contractor.
What is the difference between a tender query list and a tender clarifications list?
A tender clarifications list is issued during tender stage to clarify any works specified, whereas a tender query list is issued once the tenders have been returned and analysed to clarify any potential errors.
On the fire service floor refurbishment project, why did you have to exclude a contractor from the process?
- Did not submit priced SoW
- Only submitted a rate for a portion of the works
- In accordance with ITT excluded as non-compliant tender
What was the scoring criteria for the tenders for the fire service floor refurbishment project?
Cost: competitiveness and arithmatical errors
Quality: company structure, quality control, H&S and previous experience
For the Appleford Court project, why did you end up recommending the contractor in the tender report? What factors were considered?
They were the highest as per the scoring matrix criteria.
Scored well on cost and qualitative questions and had previous experience working with client.
What is the difference between procurement and tendering?
Procurement - The overall processes that take place prior to construction of a building. Involves design, tender and appointment.
Tendering - Specifically the process of selecting a contractor
Identify the different types of procurement?
Traditional, D&B, Management Contracting, Construction Management.
Identify the different types of tender?
Open, selective, PFI, negotiated, single stage, two stage
What are the main differences between traditional and design and build procurement?
Traditional: The Contractor is required to build what has been specified and holds responsibility for workmanship, but all design liability lies with the Architect/design team.
D&B: The Contractor retains overall control of your project and is legally responsible for both the design and the workmanship of your build.
When are the different procurement options normally suitable?
- Traditional:
The traditional procurement route involves separating design from construction. The client first appoints consultants to design the project in detail (and often to ensure cost control and inspect the construction works as they proceed), and a contractor is then appointed for the construction of the project on a single-stage competitive basis. - Design and Build:
Used when there is a need to make an early start on site – as design and construction can overlap. Used when the client wishes to minimise their risk – as they have no responsibility for design. It’s for technically complex projects which can benefit from the contractor’s expertise in the design stage. Used when the employer does not want to retain full control over the design development. Used when the client wishes to have a single point of responsibility. - Management Contracting and Construction Management:
Construction management is a procurement route in which the works are constructed by a number of different trade contractors. Construction management differs from management contracting, in that management contractors place contracts with works contractors (equivalent to trade contractors in construction management) direct, whereas construction managers only manage the trade contracts, the contracts are placed by the client. They might be used on large, complex projects where the advantages of CM / MC can be put to use e.g. upfront buildability knowledge, programme advice, specialist input from trade contractors. It is used where early start on site is key, flexibility in design is required and where price certainty before commencement is not key.
What are guidance notes for tendering?
JCT Tendering Practise Note 2017
RICS Tendering Strategies Guidance Note
RICS E-Tendering Guidance Note
What are the pros and cons of open tendering?
Pros:
- Increased competition
- Providing opportunity to smaller contractors to tender
- Ensuring the lowest price is obtained
- Can quickly advertise and issue on an online portal
Cons:
- Contractors can tender that you have no experience of working with
- Lowest price is often inaccurately priced
- Likely to receive more invalid tender submissions
- Have to have an online system or way of advertising to all
- Tender analysis is lengthier