Health and Safety Flashcards
What RICS guidance should you familiarise yourself with before an inspection? What does it include?
Rics Surveying Safely Guidance Note 2018 2nd Ed
What are the CDM Regulations?
management of health and safety during construction projects
What are the requirements of the CDM Regulations?
Requires a Principal Designer and Principal Contractor, F10, dutyholders, PCI, CPP, H&S file, sufficiently skilled/trained/experienced operatives.
What governs health and safety in the workplace? What is it?
Health and Safety at Work Act 1974. Legislation confirming duties employers have to employees regarding H&S, protecting non employees and controlling explosive or flammable substances.
What is HSE? Give an example of HSE guidance
Britain’s national regulator for workplace H&S.
HSE guidance include home working, first aid in work, appoint a competent person, reporting accidents or incidents.
What risk assessments should be undertaken before visiting a site?
Lone working
Working at height
Visiting a construction site
Visiting a derelict property
Confined space
What is the purpose of a Construction Phase Plan? What is included in a CPP?
Description
Existing site risks
Risks from undertaking the works
Other H&S measures, e.g. inductions/toolbox talks/A&E
RAMS
Give an example of how you ensured H&S standards were being met on a project?
I included a section on H&S and whether items were being met for Acorn House.
What is included in a PCI? What is our role in relation to PCI production?
- Introduction
- Client requirements, site set up, etc
- Existing site risks
- Risks that could arise from the works
- Other H&S considerations, e.g. nearest A&E
- Existing information, e.g. fire risk assessment, asbestos management plan, etc
What is RIDDOR? When should you report an incident?
Reporting of Injuries, Diseases and Dangerous Occurrences Regulations 2013. Any accidents notifiable under RIDDOR should be made within 15 days of the incident, near miss or disease.
What does the latest CLC guidance state?
CLC guidance no longer current and withdrawn but 9 versions are available for reference
What are the main elements of the Control of Asbestos Regulations 2012? Who does it apply to?
Applies to employers, employees and those managing a property. The dutyholder is the person that has clear responsibility for the maintenance or repair of non-domestic premises.
Ensures management of asbestos for non-domestic properties, asbestos management plan and survey, R&D survey if construction works, some removal may not be licensable but still notifiable.
What is the Regulatory Reform Fire Safety Order 2005?
Applies to all buildings other than individual private homes and ensures employees have fire safety training, FRAs are undertaken and those with control reduce fire risk.
What is the difference between the Regulatory Reform Fire Safety Order 2005 and the Fire Safety Act 2021?
Fire Safety Bill 2021 amended clarifying Responsible Persons should reduce fire risk to external walls, e.g. windows/balconies and all doors to common parts.
When are CDM regulations applicable?
CDM 2015 applies to all construction work including domestic projects.
What needs to be in place to control asbestos in an existing building?
An asbestos management plan and an asbestos management survey
Provide an example of when you raised an urgent health and safety issue on site? How did you ensure it was rectified?
I raised an urgent issue when operatives were not were PPE on scaffolding for the ext decs project. I advised them to urgently put on PPE and afterwards informed the site manager and PD.
You are going to a new site for an inspection, what is the process?
- Research the site and any info
- Have PPE and equipment prepared
- Put myself in diary and inform line manager
- Review relevant risk assessments
- Attend site and sign in, undertake induction, etc as required
On your Acorn House project, tell me about how you reported your H&S observations?
- H&S section included within my report.
- Any urgent actions I requested whilst on site and also addressed them in the report.
- Principal Designer was cc’d into reports issued.
Do you have an obligation to report H&S issues?
Yes as per the safe person concept to protect myself and others and I have a duty of care
Give examples of different risk assessments?
Lone working, Office risk assessment, risk assessment for empty buildings, risk assessment for construction sites.
What are the requirements of the Control of Asbestos Regulations 2012? What should the client have available?
Client should have an asbestos management plan and asbestos management survey.
Dutyholder should have a clear record of the asbestos in a building. This should be given to anyone undertaking work. Any asbestos to be removed should be undertaken under controlled conditions with air tests and it should be checked whether the work is licensable and notifiable.
Describe the sections within the RICS Surveying Safely guidance note. What year and edition is it?
RICS Surveying Safely 2nd Ed 2018
Assessing hazards and risks, place of work, occupational hygiene and health, visiting sites, fire safety, management of contractors
Give examples of HSE guidance you have read?
home working, first aid in work, appoint a competent person, reporting accidents or incidents.
Talk me through how you ensure H&S before, during and after a survey?
- Review risk assessments
- Bring correct PPE and equipment
- Review site information
- Put myself into calendar and inform line manager
- Adhere to company policy
- Undertake induction and sign in
- Adhere to site rules
- After update any risk assessments or discuss with the PD and site manager as necessary
What is a safe person concept?
Each individual has responsibility for their own and others safety whilst at work.