Procurement And Tendering Flashcards
What is procurement? What is tendering?
Procurement is the overall act for obtaining goods and services
Tendering is the process by which those goods and services are procured
What procurement routes are you familiar with?
- Traditional
- Design and Build
- Management Contracting
- Construction Management
What are the main factors which typically inform what procurement route you would recommend?
- Time
- Cost
- Quality
- Risk allocation
When might you recommend a traditional procurement route?
- If Client wishes to control design / quality
- If Client requires cost certainty
- If the Client does not have any reason to expedite programme
What are the advantages and disadvantages of Traditional Procurement route?
Advantages:
- Client retains design control
- Client getting what they want from the scheme
- All tenderers tender on the same basis
- Client can obtain cost certainty
- Should result in minimum risk premium
Disadvantages:
- programme may be longer
- No buildability input from contractor
- Client retains design risk
When might you recommend a Design and Build procurement route?
- Where client requires an early start on site / shorter programme
- Where Client wishes to minimise their risk profile
- To benefit from contractor buildability
What are the advantages and disadvantages of a Design and Build procurement route?
Advantages:
- Single point of responsibility
- Client transfers design risk
- Provides buildability input from contractor
- Can provide cost certainty
Disadvantages:
- Client cannot control quality
- Can be difficult to compare tender returns
- Employer changes will be more expensive
- Tenderers will build in risk premium into prices
What is a construction management procurement route?
- The Client directly employs the subcontractors to carry out the works
- The construction manager would deal with programme & coordination of subcontractors to carry out works, but has no contractual link
When might you recommend a construction management procurement route?
- When you have a more experienced client
- Where the Client does not require cost certainty
- Employer wants flexibility to make minor design changes
- Wants to achieve an early start on site
- When the project is more complex and requires specialist subcontractor design
What are the advantages and disadvantages of a construction management procurement route?
Advantages:
- Early start on site / programme benefits if construction & design overlapped
- Client has some flexibility with design
- Prices may be lower due to direct contracts
Disadvantages:
- Client has direct contractual link with subcontractors, and construction manager does not have the contractual relationship, barring them from professional negligence
- Cost certainty not obtained until last package is agreed
What is management contracting?
- Essentially a main contractor
- Client employs a “management contractor” to manage trade contractors, for a fee %
When might you recommend management contracting procurement route?
- Cost certainty not a priority
- Wants to achieve early start on site
- Employer wants flexibility to make minor changes to design
- Where buildability input is required
What are the advantages and disadvantages of management contracting?
Advantages:
- Single point of responsibility
- Management contractor can provide buildability input
- Programme benefits from overlapping design and construction
- Flexibility with design
Disadvantages:
- Price certainty not achieved until last package is tendered and agreed
- Requires an informed, experienced employer
Which is the least risky procurement route for Clients?
- D&B
- Transfers risk of design and construction to contractor
What is the riskiest procurement route for Clients?
- Construction management
- Clients takes out numerous contracts with trade contractors & construction manager carries no contractual link, therefore barring them from professional negligence
What is a framework?
- A collation of contractors, subcontractors and suppliers that have agreed to use an established set of governing terms to be procured for schemes
When might you recommend a framework?
- If client wishes to reduce time associated with procurement
- Financial benefits, eg maximum OH&P
- Efficiency benefits, eg procurement team on hand to advise
- Public sector clients would generally use frameworks for procurement
Why do public sector clients use frameworks for procurement?
- Compliance with UK Public Contracts Regulation 2015
- Ensures public sector clients provide opportunity, equality and non discrimination
How long are frameworks typically in place?
- Usually around 4 years
- Can be between 2 and 10 years
What are the advantages and disadvantages of framework agreements?
Advantages:
- Encourages long term collaboration between parties
- Saves time through procurement process
- Opportunity for repeat work
- Rates and prices usually agreed up front
- Capped OH&P
Disadvantages:
- Contractors can become complacent
- Bidders could invest time and money to get onto the framework, then not receive any work
What is a PQQ?
- Pre Qualification Questionnaire
- Sends out a set of questions to potential tenderers to understand their experience, financial standing and capacity
What is the aim of a PQQ?
- Remove any tenderers that are not suitable to carry out the works
- Reduces the number of tenderers down to a group that are genuinely fitted to the project
What might the PQQ ask for, from tenderers?
- Financial information
- Health and safety policies & records
- Insurance details
- Company details
- Relevant experience
- Technical & professional abilities
Usually you would carry out a credit check as part of the PQQ process. Where would you obtain a credit check from?
- Procure a Dunn & Bradsheet report
- Use a credit check agency, such as Experian
What would you look for on a Dunn & Bradsheet report?
- Overall financial health of the company
- Maximum recommended contract value
What is tendering?
- Where Clients invite contractors to bid for works
- Enables the Client to obtain a price for the works
What is single stage tendering?
Single stage tendering involves one stage where contractors are invited to provide a price for the works. It is utilised to secure a price for the works, from the offset.
Time period may be longer as tenderers will need to digest and analyse information. Perhaps 10-16 weeks for large projects, depending on level of information & procurement route.
What are the advantages and disadvantages of single stage tendering?
Advantages:
- Client gets lump sum for the works
- Gains the most competitive price (contractors put their best foot forward)
Disadvantages:
- May not be much appetite in good economic climate
- May lead to increased risk allowances / premium