Conflict Avoidance And Dispute Resolution Flashcards

1
Q

How can conflicts be avoided between parties?

A
  • clear contract documentation
  • Unambiguous tender documentation
  • Communication and listening skills
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

If a conflict occurred, how would you deal with it?

A
  • politely, professionally and respectfully
  • request a face-to-face meeting to begin negotiations in order to resolve
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

In your opinion, what is the cause of most disputes?

A
  • commercial aspects and disagreements
  • Unclear or conflicting specifications and drawing within scope of contract
  • Teams being under pressure, leading to poor or rushed decisions
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is dispute resolution?

A

Dispute resolution is a method of resolving a conflict, dispute or claim

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What does ADR stand for?

A
  • Alternative Dispute Resolution
  • refers to the processes and alternatives to the traditional methods of dispute resolution, such as litigation or arbitration
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are the main forms of ADR available?

A
  • Negotiation
  • Mediation
  • Adjudication
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

If a dispute were to occur, what court would the dispute be referred to?

A
  • The Technology and Construction Court
  • The TCC would not normally handle cases with the value of less than £250k
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What would indicate the success of a final account negotiation?

A

All parties come away happy, within the clients budget, and the negotiation is resolved in a timely manner

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is mediation?

A

Parties agree on an independent, third-party neutral person to facilitate discussions between them in an attempt to reach a settlement

The power of his settlement remains of the parties and the process is non-binding

The mediator does not award a winner

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Can you explain what a negotiation is?

A

Negotiation is a process where parties work out between them how to resolve the issue that has arisen

The process requires cooperation of both parties and is a non-binding process

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is conciliation?

A

Conciliation is similar to mediation, being a non-binding process, where a third-party facilitates conversations in an attempt to agree

The conciliator prepares a recommendation to resolve the dispute

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is an expert witness?

A

A person who has extensive experience and knowledge in a field, who can make their expertise available to court or other bodies

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is expert determination?

A

Where parties to a contract can refer their disagreement to an impartial third-party expert

This process is more simple and cheaper than arbitration or litigation

The process is binding

Process has been essentially made redundant due to the introduction of Adjudication

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What are the advantages and disadvantages of expert determination?

A

Advantages:
- Confidential procedure
- Reduces cost and time
- Less adversial than formal dispute resolution

Disadvantages:
- Less suited for factual disputes
- limited grounds of appeal

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is adjudication?

A

Adjudication was developed to allow construction contract disputes to be resolved more quickly and cost effectively than formal dispute resolution procedures

The aim of adjudication is so parties can come to a solution so they can resume and continue the work efficiently

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Can you explain how the adjudication process works in terms of time frames?

A
  • Conserve a notice to the other party for their intention to refer to adjudication
  • With seven days of the notice of adjudication, the referring party must serve their statement of case (the referral - the why)
  • The referral must contain detailed explanation of the referring parties claim, along with any supporting documentation
  • Within these seven days, the referring party must also secure the appointment of an adjudicator
  • From day seven, the adjudicator will be appointed, and will set out a timetable for information to be gathered for analysis
  • The adjudicator must make his decision within 28 days of the referral
17
Q

What is the maximum period for adjudication? Can this be extended?

A

Maximum period is 28 days

Can be extended up to 42 days by mutual agreement of both parties

18
Q

Is there an appeal process with adjudication?

A

There is no appeal process

However, parties can refer the same dispute to litigation or arbitration

19
Q

What if the building contract does not contain provisions for adjudication?

A

Adjudication is legal right under construction contract due to the construction act addendum 2009

20
Q

Who pays for adjudication?

A

Both parties are jointly liable to pay the adjudicator fees, however, the adjudicator can decide who pays the fees

21
Q

Is the adjudication process binding?

A

Yes

However, the decision may not be binding if the adjudicator acted outside their jurisdiction or was biased towards one party

22
Q

What is arbitration?

A

Arbitration is essentially a lawsuit without court involvement.

Parties agreed to submit their dispute to arbitration rather than to pursue a lawsuit in court

The process is legally binding

Arbitration can only be referred to if there is an arbitration clause in the contract

23
Q

What are the advantages and disadvantages of arbitration?

A

Advantages:
- Process is private
- Quicker in comparison to litigation
- Parties can agree on an arbitrator with relevant expertise in the matter

Disadvantages:
- Parties must bear the costs of both the arbitrator and venue
- Limited appeal rights
- could be considered uneconomical for smaller claims

24
Q

What is litigation?

A

Litigation involves claims in civil court

The nature, complexity, and value of the dispute will determine which court will hear a particular dispute

25
Q

What are the advantages and disadvantages of litigation?

A

Advantages:
- Judges can compel parties to comply with time frames
- judges have the power to make interim relief to protect the parties decision pending final judgement
- There are defined rights of appeal in cases where errors of fact or law are made

Disadvantages:
- Costly
- Public process
- Longer period to obtain judgement
- Judgement will be subject to appeal

26
Q

Are you aware of any guidance and conflict avoidance published by the RICS?

A

I am aware of the RICS guidance on conflict avoidance and dispute resolution

27
Q

What if negotiation finished and you could not reach an agreement with the contractor?

A
  • I will consult the client to present the issue and see what their thoughts are
  • I would potentially make an assessment of the cost under NEC
  • I would not display the contractor from proceeding to ADR
  • The client may also wish to proceed to ADR
28
Q

How is NEC implemented to avoid conflict?

A
  • language in the contract is to promote collaboration and cooperation between parties
  • Timescales are implemented to ensure issues are dealt with swiftly
  • The contract executes an early warning system to have a collaborative approach to risk
29
Q

How can JCT be used to avoid conflict?

A

The GCT constructing excellence contract uses partnering to promote collaboration and integrated working

30
Q

What are the available conflict avoidance options under NEC and JCT?

A
  • NEC = Adjudication or Arbitration. NEC4 also allows contractor & client to nominate senior representatives to try and negotiate before formal proceedings are undertaken.
  • JCT allows for Adjudication and Arbitration.
31
Q
A