Case Study Flashcards

1
Q

Why are you so adverse to recommending a Letter of Intent for a client?

A
  • lack of robustness
  • relevant case law, eg Turner&Townsend vs Abbey Trust
  • potential ambiguities

All lead to LOI’s being in advisable

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Why do you believe additional professional fees would need to be required for the works if another contract was issued? It’s the same amount of works?

A
  • programme was longer due to additional scope introduced
  • execution & administration of another contract
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Is a letter of intent a contractual agreement?

A
  • it’s a letter
  • unless signed by both parties, or terminology suggests it is a legally binding contract
  • I would also recommend my clients seek legal advice regarding LOI’s
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What challenges were presented for the refurbishment of 200BPR?

A

-

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What was the cost £m2 of the asbestos removal?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Is there a cost limit on the NEC short form?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What could you have done if the design was not complete? How could the contractor have priced the works?

A
  • I am aware they could have implemented Prov Sums, but generally NEC does not allow for Prov Sums under unamended versions
  • Could have continued design through construction, but client required cost certainty before entering into main contract
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is the GIA of 200BPR?

A

5,000 m2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

How does location affect cost?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

How would site logistics impact costs, and how would you factor this in?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

How do you price main contractor and subcontractor preliminaries in your cost plans?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

When would you use NRM 3?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

How much more information would you expect to receive at Stage 4?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is the Stage 4 design wasn’t complete on a scheme? How would you price for unknown elements?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

How would you approach pricing bespoke works?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What RIBA stage was Gosford hill when you were cost planning?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Talk me through the process of cost planning you followed for Gosford Hill?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

What are some of your exclusions from cost plans?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

What is DATOS? How does it work?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Did you have any other considerations when you omitted the roof lights on Oak House?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

What levels of inflation did you use for inflating the Endoscopy Hospital LCC?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

How did you address maintenance and operational costs in your LCC report?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

You mentioned BCIS wasn’t reflecting current market conditions. Do you share your tender returns with BCIS?

A
  • Ensure confidentiality is adhered to
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

What is the difference between construction management and management contracting?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

What information might you request in the first stage of a two stage tender process?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

How can you maintain competition in the second stage? How can you ensure Value for Money?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

What would provide the client better value for money. Single stage or two stage?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

On the Kingsway scheme, what weighting was applied to price? Did the lowest tenderer win the project?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

How would you deal with an abnormally low tender? What would be your considerations?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

On the PAN projects, if the Client had not wanted to negotiate, what would your recommended strategy have been and why?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q

What is an Order of Cost Estimate?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
32
Q

What information would you use for an Order of Cost Estimate?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
33
Q

What is the purpose of an Order of Cost Estimate?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
34
Q

What sources of information might you use for an Order of Cost estimate?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
35
Q

How much would you include for design development risk?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
36
Q

How much design development risk would you include in your FCP 3 / RIBA 4?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
37
Q

Does the type of project affect Design Development risk?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
38
Q

What about construction contingency? Would the type of project affect the level of construction contingency that would be included?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
39
Q

How much design development contingency would you allow in a stage 3 cost plan?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
40
Q

Talk me through the last cost plan you did

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
41
Q

What is value engineering?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
42
Q

Can you give me an example of some recent value engineering from one of your projects

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
43
Q

What is the difference between a defined and undefined provisional sum?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
44
Q

What is a prime cost sum? When might you use a PC sum?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
45
Q

What are fluctuations? When might you recommend using a fluctuations clause?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
46
Q

How do you calculate tender inflation?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
47
Q

How do you calculate construction inflation?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
48
Q

What level is tender inflation currently running at right now?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
49
Q

Is BCIS part of the RICS?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
50
Q

What is a good wall to floor ratio?

A

0.3-0.5

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
51
Q

What clarifications did you include in your last cost plan?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
52
Q

What do preliminaries cover?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
53
Q

What is the average weekly run rate for your current projects?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
54
Q

What is the purpose of NRM?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
55
Q

What is IPMS?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
56
Q

What does the GEA include?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
57
Q

What does the GEA exclude?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
58
Q

What different types of pricing documents are there and when might you use them?

A

BOQ
CSA
Activity Schedule
Preliminaries
CEQ

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
59
Q

How would you assess a final account?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
60
Q

What are the different ways of valuing change?

A

Quotations
Rates
Dayworks?

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
61
Q

How do you assess loss & expense?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
62
Q

What is a complaint?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
63
Q

What are the RICS rules in relation to Complaints?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
64
Q

How do you deal with a complaint?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
65
Q

What do you need from a Client to prepare a fee?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
66
Q

What would you exclude from a fee proposal?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
67
Q

How do you communicate with your team?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
68
Q

What is ADR?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
69
Q

What should you consider when looking at ADR?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
70
Q

What are the drawbacks of ADR?

A
  • can waste time and money if ADR does not work
  • may not be suitable for overly complex claims due to time contraints
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
71
Q

What affects the price of internal walls?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
72
Q

How would you go about quantifying & pricing an internal wall?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
73
Q

What is stretcher bond?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
74
Q

What do you need to consider when pricing the excavation and construction of a basement?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
75
Q

What is CLT?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
76
Q

Tell me about the Building Safety Act

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
77
Q

What is the purpose of a base date?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
78
Q

are you aware of any products that shouldnt be used in construction?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
79
Q

What is the difference between end bearing and friction piles?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
80
Q

When might friction piles be more suitable?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
81
Q

What is the best frame for a residential building?

A
82
Q

What is the best frame solution for a commercial building?

A
83
Q

What are the O&M manuals?

A
84
Q

What are the requirements for practical completion?

A
85
Q

What is Value for Money?

A
86
Q

What were the fire protection requirements on the Oak House data centre?

A
  • Fire suppression system in data rooms
  • Wouldn’t use sprinkler system due to amount of electrical equipment
87
Q

What tender strategy would offer best value for money - single or two stage?

A
88
Q

For 200BPR, were you involved in the tender stage?

A
89
Q

What information was requested from the contractor in their tender submission, for 200BPR?

A
90
Q

What is happening at 200BPR at the moment?

A
91
Q

What were the issues that were holding up signing the main contract? Could these have been foreseen at tender stage?

A
92
Q

How would viability have been impacted had the £5m expenditure not been achieved? What would your advice have been to the Client?

A
93
Q

How would you advise a client that a letter of intent should be drafted?

A
94
Q

What is the short form NEC contract best used for?

A
95
Q

Would executing the short form contract mean two contracts are running in parallel, or would all of the early works be completed ahead of the main contract starting?

A
96
Q

You mentioned that you cannot enter into the ECC with Stage 3 design due to the inability to provide cost certainty. Did you consider asking the contractor to include a sum for design development and transferring the risk of design to the contractor?

A
97
Q

For your second key issue, why was the end user assuming that they could make changes to the design with no additional cost to themselves?

A
98
Q

Can you give me an example of one of the changes that was proposed by the end user? Who ended up paying for that change?

A
99
Q

How easily was the change control process implemented into the scheme?

A
100
Q

On Oak House, you mention that market volatility was driving a long lead in for the ballistic board. What impact would this have had on the critical path for the programme?

A
  • not direct impact on critical path as other activities could be undertaken, but would have reached a point where packages could not complete ie M&E and finishes
101
Q

What was the cost impact of changing from a ballistic board to a blockwork wall?

A
102
Q

On CiNER Glass, you recommended a review of the frame. Why was concrete specified by the structural engineer?

A
103
Q

When you requested the frame to be reviewed on CiNER Glass, what action did the team take following your advice? What was the outcome?

A
104
Q

What additional constraints should be considered when working on a live airfield

A
  • Airside insurance
  • Security clearances
  • Limited suppliers for specialist works, eg hangar doors, bouncy castle specialist seal
105
Q

On the bottle manufacturing facility you recommended omitting glazing in lieu of cladding. Were there any knock on effects on the design?

A
  • Additional lighting internally
106
Q

For contract practice on the PAN projects, which risks did the contractor propose to transfer to the Client?

A
107
Q

Following your advice, which risks did the contractor retain on the PAN projects PSC?

A
  • Lead in
  • Logistics
  • Client budget (ensuring design suits client budget)
108
Q

On The Kingsway, how did you address any variances in your assessment of the valuation?

A
109
Q

What would be your advice if the contractor submits an updated activity schedule with their application for payment?

A
110
Q

On 31 Borough High Street, was there a limit on how long you could withhold monies for non provision of warranties?

A
  • Mention 25% withhold only until collateral warranties are issued for specific packages where CW requires
111
Q

You not that you provide a quarterly update on market conditions. can you summarise your latest update?

A
  • Building safety act
  • AI implementation in construction
  • Market conditions
  • London construction events
  • Retrofitting buildings to improve sustainability
112
Q

On Gosford Hill School, how much longer would the programme have been for remodelling on the existing footprint?

A
113
Q

Which option was more economical from a construction perspective, option 1 or 2 (Gosford Hill)?

A
114
Q

What did you advise your client what the impact would be of decanting the school into temporary accommodation?

A
115
Q

You have completed both cost plans and estimates - what is the difference?

A
116
Q

What is the last cost plan that you prepared? What design stage was this?

A
117
Q

What exclusions did you make in your last cost plan and why?

A
118
Q

Is it better to exclude asbestos or take a guess?

A
119
Q

On Oak House, what was the cost per square meter for the bullet proof lights?

A
120
Q

Why did the endoscopy hospital need a Life Cycle Cost? Did they not understand how much it costs to run?

A
121
Q

On 71/72 The Kingsway, how were the scores weighted?

A
122
Q

How was the score weightings communicated to tenderers, for The Kingsway?

A
123
Q

On The Kingsway, how did you ensure that a contractor didn’t submit a low price to “outweigh” a poor quality score?

A
124
Q

On CiNEER Glass, how did you manage the responses to tender queries?

A
  • Queries compiled and issued to professional team
  • Responses collated and issued to all tenderers
  • No reference to who has submitted queries, all anonymous
125
Q

On CiNER Glass, how long did requesting revised preliminaries and programmes add to the tender analysis process? How was this delay communicated to the Client?

A
125
Q

On CiNER Glass, how did you communicate to the contractors the need to resubmit their price based on the tender information?

A
125
Q

On the PAN Project, did you manage to obtain three or more quotations for all packages?

A
126
Q

On 71/72 The Kingsway, at what stage did you identify that contingency needed to be expended?

A
126
Q

On 71/72 The Kingsway, was Value Engineering realistic at this stage of the project, or has items already been ordered for the works?

A
127
Q

You mention that you produce cost estimates, plans and reports in accordance with NRM1. Why would you prepare a cost report in line with NRM 1?

A
128
Q

On CiNER Glass, what additional information did you obtain between the Stage 2 and 3 cost plans?

A
129
Q

On Oak House, did you carry out a pre-tender estimate?

A
130
Q

On 71/72 The Kingsway, how would you have proceeded the following month if the the contractor had included the CE £2.38m?

A
131
Q

What are the payment provisions for the Kingsway project?

A
132
Q

How do you agree a compensation event?

A
  • In line with the time scales, outlined in contract
  • Actual defined cost of work done
  • Forecast defined cost of work not done
  • Fee %
  • Would include elements outlined in SSCC
133
Q

On 200BPR, what risks were identified and how did you assess the cost impact of these risks?

A
134
Q

How can you earn BREEAM credits, besides LCC reports?

A
135
Q

Why is it important that our working environment is inclusive?

A
136
Q

Can you name three groups protected by the equality act?

A
137
Q

What is unconscious bias?

A
138
Q

As a QS, what data do you collect?

A
139
Q

On 71/72 The Kingsway, how did you maintain a positive working relationship with the contractor after reducing their valuation by £2.38m for an unagreed CE?

A
140
Q

Why is it important to have a business plan?

A
141
Q

What is the difference between a profit and loss and a balance sheet?

A
142
Q

What do you do to prepare for a site visit?

A
143
Q

What if you see an area of the site that is unsafe during your site visit? For example, an area being excavated but not protected by barriers?

A
144
Q

When should you not give advice?

A
145
Q

What would you do if you were approached by your neighbour, who asks you to price the extension on their house?

A
146
Q

Say you arrive in the office on Monday morning and there is a letter on your desk with a complaint from a client saying you have over certified on the last valuation. What should your next step be?

A
147
Q

Post qualification, how much of your CPD must be formal?

A
148
Q

How should you record your CPD when chartered?

A
149
Q

When might you need a locum?

A
150
Q

How long should run off cover last?

A
151
Q

What is meant by “act with integrity”?

A
152
Q

What is the RICS Inclusive Employer’s Quality Mark?

A
153
Q

You weren’t involved for long before you got involved with the 200BPR project. How did you get up to speed?

A
  • Streamlined due to transferring from another office
154
Q

What were some of the first tasks you undertook when coming onboard on 200BPR?

A
155
Q

Have you agreed the contract sum for 200BPR?

A
156
Q

How did you ensure competitiveness was maintained through the two-stage tendering process?

A
  • Open book
  • 3nr quotations minimum
157
Q

Why was there a delay in agreeing legal amendments if the project is being procured through a framework? Surely the amendments to the contract should be pre agreed on the framework

A
158
Q

What were the risks associated with the early works contract?

A
159
Q

What are the risks associated with a letter of intent?

A
160
Q

What was your general advice to the client around Letters of Intent?

A
161
Q

Do you have any experience dealing with Letters of Intent?

A
162
Q

Why did you need to liaise with the framework representatives regarding a Letter of Intent? What influence would they have?

A
163
Q

Did you seek contractor buy-in to executing another contract?

A
164
Q

Did the contractor have the resource and capacity to undertake an additional contract?

A
165
Q

Did you consider whether there could have been a risk in agreeing additional legal terms and conditions for the short form contract?

A
166
Q

Was the design produced in a way that would allow the early works to be procured separately from the main works for 200BPR?

A
167
Q

How many weeks did executing an NEC short form contract save on the programme?

A
168
Q

What are the pros and cons of executing the main contract with the stage 3 design information, for 200BPR?

A
169
Q

Could you not have obtained cost certainty through a RIBA 3 design for the clients internal procurement team?

A
170
Q

You confirm you proceeded with Option 2 with the NEC short form contract. Can you summarise why this was the best option from a time, cost and quality perspective?

A
171
Q

What are your takeaways from dealing the scenario encountered on 200BPR?

A
172
Q

What would you do differently on 200BPR next time?

A
  • Scott schedule at tender for proposed amendments
  • Engage legals early in the process
173
Q

On 200BPR, why was the contractor taking instruction from the end user when they have no contractual relationship?

A
174
Q

On 200BPR, you advised that there needed to be provisions in place for change control. Does NEC not already have processes in place for this?

A
175
Q

Did the communication between the end user and contractor stop?

A
176
Q

Why weren’t all communications going through the PM for 200BPR?

A
177
Q

What are some of the risks of not being party to the conversations between the end user and the contractor, on 200BPR?

A
178
Q

On 200BPR, can you explain how the process of the PCR worked from the start to end?

A
179
Q

Did you need to factor in additional time in responding to the quotation provided by the Contractor to obtain internal sign off due to the number of project stakeholders?

A
180
Q

Was allowing communications to continue on 200BPR a viable option?

A
181
Q

Did communications continue or stop on 200BPR for end user changes? If not, is there not a financial risk to the project?

A
182
Q

From 200BPR, what experiences would you take from this project onto new projects?

A
183
Q

Can you give me an example of one of the changes that your PCR was used for on 200BPR?

A
184
Q

On Oak House, what did you try and do to reduce the cost of the 30% steel increase?

A
185
Q

On the Kingsway, for the £2.38m compensation event they submitted with their valuation, did this impact their cash flow?

A
186
Q
A
187
Q
A
188
Q

Why was the contractor undertaking works where a CE had not been implemented?

A
189
Q

How did you ensure value for money for the £2.38m CE?

A
190
Q

What is the purpose of a cost report?

A
191
Q

When would you consider issuing cost reports at different intervals than monthly?

A
192
Q

For CiNER glass, were you not able to level the tenders?

A
193
Q

For the PAN projects, why was the Client keen to negotiate with the contractor?

A
  • Buildability input
  • Worked before, satisfied with work
  • Speed to appoint design works
194
Q

Why do risks need to be managed?

A
195
Q

What considerations do you make when pricing risks?

A
  • stage of cost estimating / planning
  • method to use (management of risk)
  • likelihood / probability
  • impact
196
Q

What would you typically find in a risk register?

A

-Risk title, description, and reference
-Effect
- Likelihood
- Impact = cost, time
- Risk rating
- Recommended action
- Risk owner
- Action owner
- Update date

197
Q

Example of a risk you identified on ciner glass, and how did you control it?

A
198
Q

Example of a risk on 200BPR, and how you controlled it?

A
199
Q
A