Case Study Flashcards
Why are you so adverse to recommending a Letter of Intent for a client?
- lack of robustness
- relevant case law, eg Turner&Townsend vs Abbey Trust
- potential ambiguities
All lead to LOI’s being in advisable
Why do you believe additional professional fees would need to be required for the works if another contract was issued? It’s the same amount of works?
- programme was longer due to additional scope introduced
- execution & administration of another contract
Is a letter of intent a contractual agreement?
- it’s a letter
- unless signed by both parties, or terminology suggests it is a legally binding contract
- I would also recommend my clients seek legal advice regarding LOI’s
What challenges were presented for the refurbishment of 200BPR?
-
What was the cost £m2 of the asbestos removal?
Is there a cost limit on the NEC short form?
What could you have done if the design was not complete? How could the contractor have priced the works?
- I am aware they could have implemented Prov Sums, but generally NEC does not allow for Prov Sums under unamended versions
- Could have continued design through construction, but client required cost certainty before entering into main contract
What is the GIA of 200BPR?
5,000 m2
How does location affect cost?
How would site logistics impact costs, and how would you factor this in?
How do you price main contractor and subcontractor preliminaries in your cost plans?
When would you use NRM 3?
How much more information would you expect to receive at Stage 4?
What is the Stage 4 design wasn’t complete on a scheme? How would you price for unknown elements?
How would you approach pricing bespoke works?
What RIBA stage was Gosford hill when you were cost planning?
Talk me through the process of cost planning you followed for Gosford Hill?
What are some of your exclusions from cost plans?
What is DATOS? How does it work?
Did you have any other considerations when you omitted the roof lights on Oak House?
What levels of inflation did you use for inflating the Endoscopy Hospital LCC?
How did you address maintenance and operational costs in your LCC report?
You mentioned BCIS wasn’t reflecting current market conditions. Do you share your tender returns with BCIS?
- Ensure confidentiality is adhered to
What is the difference between construction management and management contracting?
What information might you request in the first stage of a two stage tender process?
How can you maintain competition in the second stage? How can you ensure Value for Money?
What would provide the client better value for money. Single stage or two stage?
On the Kingsway scheme, what weighting was applied to price? Did the lowest tenderer win the project?
How would you deal with an abnormally low tender? What would be your considerations?
On the PAN projects, if the Client had not wanted to negotiate, what would your recommended strategy have been and why?
What is an Order of Cost Estimate?
What information would you use for an Order of Cost Estimate?
What is the purpose of an Order of Cost Estimate?
What sources of information might you use for an Order of Cost estimate?
How much would you include for design development risk?
How much design development risk would you include in your FCP 3 / RIBA 4?
Does the type of project affect Design Development risk?
What about construction contingency? Would the type of project affect the level of construction contingency that would be included?
How much design development contingency would you allow in a stage 3 cost plan?
Talk me through the last cost plan you did
What is value engineering?
Can you give me an example of some recent value engineering from one of your projects
What is the difference between a defined and undefined provisional sum?
What is a prime cost sum? When might you use a PC sum?
What are fluctuations? When might you recommend using a fluctuations clause?
How do you calculate tender inflation?
How do you calculate construction inflation?
What level is tender inflation currently running at right now?
Is BCIS part of the RICS?
What is a good wall to floor ratio?
0.3-0.5
What clarifications did you include in your last cost plan?
What do preliminaries cover?
What is the average weekly run rate for your current projects?
What is the purpose of NRM?
What is IPMS?
What does the GEA include?
What does the GEA exclude?
What different types of pricing documents are there and when might you use them?
BOQ
CSA
Activity Schedule
Preliminaries
CEQ
How would you assess a final account?
What are the different ways of valuing change?
Quotations
Rates
Dayworks?
How do you assess loss & expense?
What is a complaint?
What are the RICS rules in relation to Complaints?
How do you deal with a complaint?
What do you need from a Client to prepare a fee?
What would you exclude from a fee proposal?
How do you communicate with your team?
What is ADR?
What should you consider when looking at ADR?
What are the drawbacks of ADR?
- can waste time and money if ADR does not work
- may not be suitable for overly complex claims due to time contraints
What affects the price of internal walls?
How would you go about quantifying & pricing an internal wall?
What is stretcher bond?
What do you need to consider when pricing the excavation and construction of a basement?
What is CLT?
Tell me about the Building Safety Act
What is the purpose of a base date?
are you aware of any products that shouldnt be used in construction?
What is the difference between end bearing and friction piles?
When might friction piles be more suitable?