Procurement and Tendering Flashcards
1
Q
Difference between procurement and tendering?
A
2
Q
What is a traditional route?
A
3
Q
What is design & build?
A
4
Q
What is management contracting?
A
4
Q
What is construction management?
A
5
Q
What are the reasons for robust tendering strategies?
A
5
Q
What is a single stage tender?
A
6
Q
What is a two-stage tender?
A
7
Q
What is a negotiated tender?
A
8
Q
What is open tendering?
A
9
Q
- What is selective tendering?
A
10
Q
- What is single contractor selection?
A
11
Q
- What is a PQQ?
A
12
Q
- Why was the consultant framework advertised openly?
A
13
Q
- What is the effect of FTS tendering rules on tendering?
A
14
Q
- What are the public procurement thresholds?
A
15
Q
- What is the documentation that forms a tender?
A
16
Q
- What is a tender process?
A
17
Q
- Benefits of e-tendering (online tender systems
A
18
Q
- Disadvantages of e-tendering (online tender systems)?
A
19
Q
- How do you review a tender?
A
20
Q
- How do you deal with errors in a tender?
A
21
Q
- Errors in tenders public procurement?
A
22
Q
- What do you do about late tender returns?
A
23
26. What is a pre-qualification process?
24
27. What is included in a tender report?
25
28. Risks of different procurement routes?
26
29. What is partnering? Collaborative procurement approach
27
30. What is the purpose of a Bill of Quantities?
28
31. Bill of quantities v activity schedule
29
32. Behavior of a contractor in traditional and design and build?
30
33. MEAT vs MAT
31
34. What did you advise your client were the risks of a negotiated tender?
32
36. How would you advise your client to apply BCIS indices?
33
38. Are you aware of any changes to the Most Economically Advantageous Tender ‘MEAT’?
34
40. How do you commercially assess tender submissions?
35
41. What are the benefits of e-tendering? What may be seen as a negative?
36
42. In what scenario may it be inappropriate to advise of a traditional procurement route?
37
43. How would you approach normalizing a tender?
38
45. What would you do if you received a late tender submission?
39
46. Talk me through the public procurement rules and how they’ve applied to your projects?
40
47. Explain an ITT you have issued, what are the headline contents?
41
48. What advice and analysis do you give in a tender report, name 5 items?
42
49. What procurement advice would you give a client on a £10m new build project, with a lot of complex M&E installations?
43
50. How do you currently calculate inflation and what advice would you give to a client in respect of tendering a project in the current market condition?
44
51. What advice would you give to a client, after you have advised on the most appropriate tenderer to appoint in a cost focused tender, choses to appoint the most expensive tender?
45
52. How do you handle tender queries?
46
53. What would you do if a client wanted to alter part of an ITT during the tender period?
47
46. Talk me through the public procurement rules and how they’ve applied to your projects?
48
47. How might the process for dealing with errors differ from tenders governed by public procurement regs to non-public procurement?
49
48. What other methods allow your client to retain control on design?
50
49. Rockfall Protection - How did you ensure Value for Money using the negotiated route?
51
50. Rockfall Protection - Could you have called off from a framework?
52
51. Rockfall Protection - Was the H&S risk a result of their works from last year? Were they liable?
53
52. PQQ - How did you come up with suitable prequal questions? Where could you look for them / is there any guidance on what to ask?