Conflict Avoidance Flashcards

1
Q

What are the minimum levels of service?

A
  • Seek clarity in any documents produced for the purpose of procuring works
  • Identify risks which should be brought to the clients attention
  • Manage professionally, objectively and consensually in day-to-day work
  • Recognise escalation of disputes and keep client informed
  • Understand the range of ADR processes
  • Recognise when more specialist assistance is required (rule 2)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the cause of disputes?

A

Lack of communication and misunderstandings, complaints, breaches of contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

How can you avoid conflict?

A

Good communication, clear contract documentation and good contract management, following procedures, good record keeping and audit trails

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

How to deal with conflict initially?

A

Speak to the other party verbally to understand the conflict, before following up formally and proceeding with appropriate formal method

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What ADR processes are you are of?

A

Mediation, conciliation, negotiation, adjudication, arbitration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is Negotiation?

A
  • Parties come together to discuss, problem solve and agree (negotiate) on an outcome to the issue
  • No 3rd party involvement
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is Mediation?

A
  • Third party impartial mediator who helps to find solution
  • Mediator does not pass opinion or judgement – simply facilitates so that both parties can find a solution
  • Useful if negotiation is fraught and poor communication - there to ease tensions and improve communication – encouraging parties to explore potential solutions.
  • Decision/outcome is not binding
  • Lower cost/time then other ADR’s such as Adjudication and Arbitration (and potentially Conciliation)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is Conciliation?

A
  • Third party impartial conciliator who reviews situation, meets with both parties and then makes a recommendation of a solution
  • Useful if negotiation is fraught and poor communication - Conciliator (like Mediator) is there to ease tensions and improve communication – encouraging parties to explore potential solutions.
  • Decision/outcome is not binding
  • Lower cost time then other ADR’s such as Adjudication and Arbitration
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is Adjudication?

A
  • Dispute is referred to an adjudicator by one party
  • Adjudicator makes a binding decision on dispute
  • Entitlement to adjudication is a provision under the HGCRA 1996 and the timescales are outlined in the scheme for construction contracts 1998
  • Timescales
    - Notice of Adjudication is issued
    - The referral notice must be served within 7 of service of the
    Notice
    - The adjudicator’s decision must be made within 28 days of
    service of the referral notice
    - This period can be extended by a further 14 days if the
    referring party agrees, or can be further extended if both
    parties agree
  • NEC4 W2 – Clause W2.2(1) states that a Party may refer a dispute to the Adjudicator at any time, whether or not the dispute has been referred to the Senior Representatives. In line with HGCRA.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is Arbitration?

A
  • Dispute referred to a tribunal
  • Decision is final and binding but not public like litigation
  • Expensive process but good if discretion is required
  • Arbitration Act 1996 regulates proceedings and powers that arbitrators have – outlines must be fair, impartial, autonomous and accessible
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is Litigation?

A
  • Legal proceeding that is settled in court
  • The technology and construction court deals with disputes in construction and engineering
  • Decision is final and binding
  • Very expensive and public decision
  • Wolfe Report - Must have attempted other forms of ADR before going to court
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is Expert Determination?

A
  • Contract outlines that parties agree to refer a dispute to an expert third party who will decide on issue/dispute
  • Expert will determine value/final account
  • Generally eclipsed by adjudication – but still used where HGCRA doesn’t apply such as international contracts
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What are RICS three pillars of ADR?

A
  • Negotiation – problem solving of parties themselves
  • Mediation (Conciliation) – third party involvement not binding
  • Adjudication – binding decision by third party
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What are the Dispute Resolution procedures on one of your contracts? NR12

A
  • Employers representative decision - Employer’s Representative shall decide any dispute between the Contractor and the Employer, decision is binding, both parties can dispute the decision
  • Optional Conciliation or Mediation
  • Adjudication
  • Litigation
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What RICS guidance/assistance is there on Dispute Resolution?

A
  • Conflict avoidance and dispute resolution in construction guidance note
  • RICS dispute resolution service
  • RICS conflict avoidance toolkit
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What are the Dispute Resolution procedures on one of your contracts? NEC

A

Clause W2 – dispute resolution procedure used when the HGCRA applied – adjudication
If, after the Adjudicator notifies his decision a Party is dissatisfied, the matter may be referred to tribunal (stated in CDP1).

17
Q

What are dispute boards?

A
  • Contractual form of dispute resolution procedure
  • Adoption of dispute boards varies from jurisdiction to jurisdiction and project to project.
  • Typically consists of one or three members, whose powers to resolve disputes are set out in the contract
  • Dispute avoidance board - W3 NEC4 (ECC only) – to avoid rather than resolve, not appropriate for UK due to HGCRA
18
Q

Example of conflict?

A

Disagreement about value of change

19
Q

As a QS how would you avoid conflict on a project?

A

Good communication, collaborative approach, following the contract, good record keeping and audit trail

20
Q

What is the difference between arbitration and litigation?

A

Both are expensive processes with final and binding decisions but arbitration is private with disputes referred to a tribunal and litigation is public with legal proceedings in court.