Case Study Flashcards
Did we know the clients budget?
No but we have a longstanding good relationship with the client so we understood their budget concerns although not the actual number
How did I produce the estimate for termination at will?
Undertook an assessment of the works completed to date, subcontractor and Atkins prelims, any materials ordered which included the DNO. Also factored in cost for making good and demobilising from site.
Project end of control period - Due to this, there was no option for the client to gain additional funding if the project exceeded the budget – can they usually get more budget?
Potentially yes and especially if this at the beginning of the control period. Projects at the end are always the ones more impacted, If they over overspend at beginning, more likelihood of uses spare budget
Possessions that had been secured for commissioning – were these E&P possessions?
They can just book new possessions.
Terminating under the target?
Works were only 50% complete, would not get full gain share, could be dealt with as proportional OR works are not completed to gain share not used.
What did the costs for demoblisation include?
Cost to remove excavator, telehandler and welfare units from the site and the cost to transport them back to site again after the demob period.
What industry news stories did I read about inflation increases and materials shortages?
- Communicated within business.
- The impact of the war in Ukraine resulted in significant energy price increases which had an impact on the cost of production of materials
- This conflict also led to materials shortages, with key electrical components
- Ukraine war intensifies already turbulent market previously effected by covid and Brexit.
- High inflation.
How did I instruct the subcontractor?
Delegated authority, to provide a quote in line with a proposed instruction.
How did I assess the delay for the DNO cubicle?
Additional prelims for both the contractor and subcontractor, in line with the programme extension.
The delay meant that the contract completion date was extended by four weeks. What types of float are there?
Terminal float which is owned by the contractor. Client risk and therefore this change could not use it.
How was the ongoing management for the reduced prelims captured to the client?
Why did I present the options before proceeding
Authority to sign off in line the companys governance procedures
Client care – keeping the client informed at each stage? Did I inform them weekly of the additional cost increase while demoblised? How was I tracking the costs?
How were my effective contract management and commercial skillset were crucial in delivering successful outcomes?
Working on behalf of the contractor, my commercial skills ensured that the contractor maintained profitability.
Would you say the project had a successful outcome?
No, I meant from a commercial management perspective to the contractor.
How did I maximise contractual opportunities under the contractual entitlement and ensured that the contractor maintained profitability throughout the review of each key issue option.
How did I consider the risk expose would be managed for termination options?
Understanding of termination? Pros and cons?
How is termination dealt with under NEC
Section 9 of the contract, there is a termination table which details the reasons (22), procedure (1-4) and amount due (1-4) for each terminating party.
What would undertaking a Quantitative Cost Risk Analysis with the client achieve?
Was the relationship with the subcontractor bad if I wanted to improve relationships?
Did we have a risk budget?
Yes 20k contingency but all risks were pass through.
Why were works not suspended?
Process of termination under NR12?
- I would follow the contract, different types
- In this instance I was considering termination at will, where the employer with 30 days’ notice to the contractor can terminate the employment of the Contractor
- Can terminate for contractor or employer default, 7 days notice must be given to terminate employment
- The contract outlines rights, how the works will be valued and payment after termination
- E.g., the employer may complete the works himself or employ another contractor to do so
How did you ask the subcontractor for a quote?
Request for quotation in similar format to a proposed instruction under NEC.
Am I advising the internal team about termination or the client?
Internal only, worst case scenario to demonstrate costs but not to propose as an option to client.
Key issue 1 - Price the 3 options
Key issue 2 – Price the 3 options
What clause did they instruct demob?