Contract Practice Flashcards
What are the fundamentals of contract law such as the requirements of a legally binding contract?
Offer, Acceptance, Consideration (something that the party is not currently entitled e.g., money), Intent (Both parties have an intention to be legally bound by the agreement), Capacity (The parties are legal entities recognised by law, such as companies, limited liability partnerships and individuals of at least 18 years of age)
What constitutes a construction contract under the Construction Act? Are consultant appointments covered?
The carrying out of construction operations, the carrying out of construction operations by others whether under sub contract to him or otherwise and providing his own labour, or the labour of others for the carrying out of construction operations. Includes agreement for surveying work.
Operations not considered as construction?
Drilling for oil and gas, nuclear processing and power generation
What does the HGCRA (1996) cover?
s107 Construction Contract to be in writing
s108 Right to Adjudicate
s109 Entitlement to stage payments
s110 Payment notices
s111 Withholding
s112 Right to suspend works for non-payment s113 ‘Pay when Paid’ became ineffective
What is the payment scheme process in HGCRA?
- End of relevant period
- 7 days until due date
- 5 days from due date to issue interim certificate
- 7 days before final date for payment to issue pay less notice
- entire cycle 24 days
How did the Local Democracy, Economic Development and Construction Act 2009 (LDEDCA) amend the HGCRA?
- Contracts will no longer required to be evidenced in writing
- Adjudicator’s power to correct decision (clerical error)
- Bans tolent clauses
- Payment notice - If after 5 days no Notice of Payment is issued, Payee may issue a Notice in Default stating what is due. If an application has been made in accordance with the Contract, the application is considered the Payee’s ‘Notice in Default’ (rather than them issuing a separate notice of payment) -> The amount contained in the Notice in Default may be considered as the amount DUE
- Withholding payment – provides clarity – requirement to pay the ‘notified sum’. Payer may amend ‘notified sum’ via a ‘notice of intention to pay less’.
What documentation makes up an NEC3 contract?
Form of Agreement, Works Information, Site Information, Pricing document, Contract Data Part 1, Contract Data Part 2, Programme
Documentation that makes up a NR contract?
The contract agreement (form of agreement), schedule of post tender amendments, Appendix Part 1 (same as CDP1 & 2), the conditions of contact with NR amendments, technical workscope, HSEA, preliminaries, Appendix parts 2-4, pricing document.
What’s included in the works information?
Description of works, constraints e.g. access to site, working hours, contractors design e.g. design submission procedures and approvals, completion e.g. completion definition, training, final clean requirements, programme requirements additional to clause 31.2
What is the structure of a NEC contract?
- Core clauses
- Dispute resolution (W2 – adjudication)
- Secondary option clauses
- S(S)CC
- CDP1 & CDP2
What are the main differences between NEC and JCT?
Collaboration, NEC has EWN process, time baring in NEC, NEC - CE is time and cost, JCT changes are relevant time and relevant matters, programme is contractual document in NEC
What are the roles and responsibilities of the named parties in NEC3?
Employer
Project Manager – the key person involved in the management of the contract, duties are summarised in clauses of the contract e.g. issuing a project managers instruction
Supervisor - His main function is to check that work is carried out in compliance with the Works Information. He is also concerned with identifying and correcting Defects.
Adjudicator
Contractor – Responsible for undertaking the works
What are the roles and responsibilities of the named parties in NR contracts?
Employer
Employer’s Representative – nominated by the Employer to act for such purposes of the contract such as instructing variations
Contractor – Responsible for undertaking the works
What are the roles and responsibilities of the named parties in JCT contracts?
Adjudicator, Architect/Contract Administrator, Quantity Surveyor, Contractor, Employer
Employer’s Representative, Site Manager (appointed to act as the Contractor’s representative)
What are liquidated damages and benefits?
Pre-determined damages written into the contract for non-completion or missing a sectional completion date. Genuine pre-estimate of loss.
Who calculates delay damages?
Client
What is an unliquidated damage?
Haven’t pre-determined the damages.
What do you do if your contract has a liquidated damage stated as zero?
Nothing – stays zero.
Delay damages blank?
Up for negotiation
How to enforce delay damages?
Through pay less notice, should always be having conversations with contractor counterpart, issue EWNs, need to consider the relationship, often last resort
What is consequential loss?
What are collateral warranties and benefits?
A collateral warranty is an agreement with a third party that is not named in the contract. Creates a contractual agreement where there wasn’t one, this party can benefit from privity of contract. Protection mechanism e.g., could use to complete the works if the contractor goes insolvent. Third Party Rights Act 1999 can be used instead.
Example of where collateral warranties can be used?
In a D&B contract between the designer and the employer?
What is a net contribution clause?
Limits the party in the collateral warranty to only be liable for the works they have undertaken.
What are third party rights?
The Contracts (Rights of Third Parties) Act 1999 allows a third party to a contract, i.e. not the Employer or the Contractor, to enforce a term of that contract in certain circumstances.
This Option (Y(UK)3) will ensure that only those terms that are clearly set out in Part one of the Contract Data can be enforced by those persons, or class of persons, that are named. This will ensure that third party rights cannot be implied from any of the other terms of the contract or Works Information
What do you do if a contractor goes insolvent?
Check contract, is there a PCG to call upon to finish works? Could you enter into contract with a sub-contractor to finish works? Could re-tender (more time consuming and costly).
What are the secondary option clauses NEC?
Adapt contract to suit nature of project and requirements of the client e.g. X7.
What are delay damages (X7)?
Delay damages are liquidated damages paid by the Contractor if he fails to complete the works by the Completion Date. The rate is defined in CDP1 (should not exceed a genuine pre-estimate of the damage which the Employer will suffer as a result of the Contractor’s breach).
Opinion on delay damages?
Suitable mechanism for a genuine requirement and based on a genuine pre-estimate of loss for the client but should not be used a punishment tool to punish the contractor
What is retention (X16)?
The purpose of retention is to enable the Employer to retain a proportion of the Price for Work Done to Date as security and as an additional motivation for the Contractor to complete the works. Usually 3 to 5%. Half of the retention being held is released at Completion of the works and the remaining half is released at the end of the defects period. Can have a retention free amount stated in CDP1. Not collaborative, impacts contractors cash flow.
What is an alternative to retention?
Retention bond.
What is a retention bond?