Procurement Flashcards

1
Q

What does Procurement mean

A

The process used to produce goods and services

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Name the types of Procurement

A

Traditional (Segregated)
Design and Building (Integrated)
Contract Management
Construction Management

New Procurement Strategies
Cost Led Procurement
Integrated Project Insurance Procurement
Two Stage Open Book Procurement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are benefits of Traditional procurement?

A

Familiarity among contractors and consultants.
The client retains responsibility for and control of design team.
There is direct reporting by the design team to the client to ensure that quality control is maintained.
The client has a contract administrator monitoring the project.
There is certainty of price (if the work is fully designed in advance).
Priced Bills of Quantities provide a basis for variations to be priced at tendered rates.
All prices are based on the same information.

As all prices are based on the same information;
It is easier to analyse the prices.
The lowest price is usually the best value for money.
Where elements of the building are not fully designed. provisional sums may be used to allow for the later. design of those elements.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is a Bespoke Contract?

A

A contract which has been tailored to suit the two parties and also the implied laws of foreign countries.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the 4 factors which can decide upon a Procurement strategy?

A

Quality
Time
Cost
Management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Why is procurement different in the Construction industry in regards to other industries?

A

You cannot purchase a project fully made. It has to be tailored by the client.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are the 3 types of Procurement?

A

Traditional
D&B
Management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are the 2 types of sub-contractors? Who do the sub-contractors have a contract with?

A

Domestic and Nominated

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are the benefits of Design and Build?

A

Speed of delivery

Single point responsibility of Contractor

Acceptance of design (the contractor has to buy in to the design)

Novation of design

Cost effective and cost certainty as the contractor can

Apply best margin, goods and services prices to the design.

Lower management costs - less client management

The law implies a duty of fitness for purposes on a design and build contractor (more care and skill than a design consultant)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are the 5 types of procurement systems

A

price in advance (fixed price / lump sum)
design and build
management
cost reimbursement
partnering / alliancing / framework agreements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What are the cons of Traditional Procurement?

A

To be effective, it requires the scheme to be more or less fully designed before invitation to tender.

Adversarial blame culture.

Potential for over-design and/or over-engineering.

The contractor is not involved in the design process and therefore is not required to feel responsible for the design.

The client retains responsibility for the design team performance

A fixed lump sum price is rarely actually achievable
The use of provisional sums and the power of the A/CA to issue instructions for additional or varied works can lead to price escalation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What are the cons of Design and Build?

A

Higher price due to higher risk premium

The client has less control and influence over design matters

Inflexibility. There is a limited scope for the client to
make changes

There is the potential of dual loyalties of a novated
architect

The quality achieved can be an issue because of the lack of control that the client has over the architect

The lack of independence of the architect.

D&B is not the appropriate route to use where a high quality design is required, unless a robust specification is included within the client’s requirements;

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is Contract Management?

A

100% sub-contracting from Main Contractor

Where the management contractor undertakes and carrying out work through work contractors, and those works contractors are contractually accountable to the management contractor.

The overall design is the responsibility of the client’s
consultants, but the management contractor is responsible for defining packages (tasks) of work and then for managing and carrying out of those work packages (tasks) through separate trades or works contractors

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What are the benefits of Management Contracting?

A

particularly beneficial for fast-track complex projects where minimal design information is available at the start of the project

allows for early ‘buildability’ and programming input from the management contractor acting as a consultant

There is a single point contractual and payment arrangement for the client with the management contractor

the preliminaries and management fee can be fixed, therefore allowing for a degree of certainty on price

the quality can be controlled by the design team

greater scope for client changes.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What are the disadvantages of Management Contracting?

A

this procurement approach is a low risk strategy for the
management contractor as he/she has little responsibility for package contractor defaults, bankruptcy, etc.

although guaranteed maximum price can be achieved,
the process is still fundamentally prime cost in its nature

cost increases can be substantial, and there is often a
tendency for the initial cost plan to be adjusted upwards

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is Construction Management?

A

The Construction Manager manages and carries out the work through trade contractors.

The Client contractually holds the risk for the trade contractors eventhough they are arranged and administered by the Construction Manager/

As part of his/her duty, the construction manager is required to co-ordinate the trade contractors.

The construction management procurement approach is a method where overall design is the responsibility of the client’s consultant

17
Q

Do NEC have Contract Types? If so, what page?

A

Yes, Page 4 for Options and Traditional Approaches are available

18
Q

What is Cost Led Procurement

A

Client sets a challenging cost ceiling

Appoints one or more supply chain teams in a framework agreement

Team’s selection based on ability to work collaboratively to deliver below cost ceiling for first project

Where cost ceiling cannot be matched by teams in the framework, project must be offered to others outside framework.

Where scheme price cannot be met, project should not proceed at all

19
Q

Integrated Project Insurance

A

Client appoint members of integrated project team

Team works together to present preferred solution with cost savings against existing costs benchmarks

Proposed solution goes through rigorous third party verification process

A single insurance covering all insurance policies put in in place

The Single Insurance Policy also covers any COST OVERRUNS (Only 2.5% of combined costs)

20
Q

What is Two-Stage Open Book Procurement?

A

Stage 1- Client invites contractor-consultant teams on
a framework agreement to bid for project on basis of
outline brief and costs benchmark

Stage 2 - Winning team produces proposal on basis of
open book cost that meets client’s requirements and
costs benchmark

Independent expert are employed as
Stage- Gate reviewers

21
Q

What are the Procurement Project Objectives?

A

Quality, Time, Cost

22
Q

How are Procurement Methods Categorised?

A

Risk
Level of information available at that time
How the Contractor is reimbursed
Interaction between the Design team and Construction team

23
Q

What is the best procurement strategy for Cost and why?

A

Cost Led Procurement as the whole strategy is based upon meeting the Cost of the project.

Between Traditional,D&B and Contract Management- Traditional would the cheapest as there is less of a risk premium however prices can rise from variations

24
Q

What is the best procurement strategy for Time and why?

A

It depends on how much information is available:

For little information- Contract Management
For large amount of information- D&B

D&B runs through the Contractor who is usually experienced

25
Q

What is the best procurement strategy for Quality and why?

A

Traditional procurement as the client has more of a say in the design

the scope is less rigid to be changed

easier to make variations

26
Q

What is the best procurement strategy for someone who wants little risk and why?

A

D&B - Payment Goes Through Contractor

Only one line from Client to Contractor

27
Q

Whats the difference between Management Contracting and Construction Management?

A

Client is contractually responsible for all duties in Construction Management whereas in Management Contracting, the Contractor deals with the Sub-Contracting

28
Q

What are the similarities between each Procurement?

A

They all involve the same roles however the duties vary.

With D&B and Management Contracting, the client holds a lower risk

29
Q

What are the disadvantages of Procurement?

A

Bulky
Expensive
Lengthy supply chain
Commerical backlog of payment

30
Q

What is PFI/PPP

Give an example of PPP

A

PPP = Public Private Partnership

A PPP is a long-term contract between the public sector (a Public Sector Client) and a private company or consortium of companies (a Private Entity) covering the design, construction, maintenance, and financing of an infrastructure asset

Example: A hospital where the private entity cover the maintenance and housekeeping whilst the public client (Local District Health Board.) cover the medical services.

31
Q

What is the Construction Management procurement called in NEC?

A

Prime Contracting