Managing Time in JCT and NEC Flashcards
What are the main stages of JCT?
Date of Possession
Regularly and Diligently carry out the Works
Completion Date
What are the main stages of NEC?
Access Date (Starting Date)
Plan programme of work to measure progress
Completion Date
What does time is at large mean?
What does time is of the essence mean?
Time is at large
When the Contractor can finish the Works with no deadline attached, ASLONG as it is within a reasonable time.
Time is of the essence
When the Client needs the project the finish at it’s original completion date. Variations and/or an acceleration programme is suggested to achieve the original Completion date.
What are the 4 possible completion stages in JCT?
Practical Completion
Sectional Completion
Partial Possession
Completion of Making Good
What does practical completion mean?
Completion for all practical purposes based upon the clients requirements.
What are the effect of practical completion?
- Rectification Period begins
- The client is responsible for the insurance
- 6 months defect liability period occurs
- End of contractor’s liability to Liquidated
Damages; - Start of the 6 month period for preparation of
final accounts - Half the Retention money is released;
What does sectional completion mean?
Part of the Works have been complete and the Client gains possession of the Works.
What is partial possession in JCT?
Allows the client, to take possession of part(s) of
the works WITH consent of the contractor
What is the Rectification period?
Period within which contractor is liable to make good
any defects
What is a snagging list?
A list the A/CA (JCT) or PM/Supervisor/Supervisors Assistant* (NEC) issues to provide a list of the defects found
What is a key date?
A date by which work is to meet the condition stated in the contract data.
What are time risk allowances?
Time risk allowances are a required part of an ECC project programme (clause 31.2).
If a contractor identifies an activity float in the programme as a “time risk allowance”, that is protected in the same way as the terminal float.
In other words, “the contractor owns the time risk allowances”.
What does Takeover mean in NEC?
Take over is about who is using the building (works) But, once completion is certified, the employer has to take them over within 2 weeks (unless the contract data says differently) whether they are actually using them or not.
The project manager certifies the date of the take over.
What is the effect of Completion in NEC?
Completion Date is a fixed milestone and is the trigger point for which delay damages would be applicable
What is Planned Completion and what is the effect of it?
When the contractor “plans” to finish and in simple terms is linked to the contractor’s last planned site
activity (activities required to meet the Completion).
The planned completion date can be adjusted however it has no effect on the Completion Date
What is the early warning clause?
An early warning is an event or potential risk which may effect the project in regards to:
Cost
Money
Quality
Explain the following JCT terms:
Adjustment of time
Delay in completion
Rectification period
Delay Damages (NEC)
What are these terms called in NEC?
- Adjustment of time
Amending the completion date due to relevant events.
2.Delay in completion
If in the opinion of the Architect the works have not reached practical completion at the completion dates
3.Rectification period - Defect Correction Period
Amending/Completing any minor works
4.Delay Damages (NEC) - Liquidated Damages (JCT)
Compensation to the client due to potentially loss profits which could have been made.
When is Sectional Completion provided?
Applied if the intention of the client is to complete project in phases or sections
What impact does the Sectional Completion have on the Contract in comparison to Practical Completion.
There is separate timetable for each section of the works
Such intermediate dates and relevant sections are stated in the contract particulars
Sectional Completion Certificate have same effects as Practical Completion
Can the client gain possession of part of the works even if there are no provisions in the contract?
If no provisions are made for Sectional Completion then contractor has right to occupy whole site until Practical Completion
What effect does Partial Possession have?
Same as Practical Completion
Is a certificate issued in possession?
No issue of certificate by Architect
A written statement prepared by Architect to
identify part of works being possessed ( this statement is called relevant part)
What is the effect of Delay in Damages?
An non-completion certificate is issued.
Enables the Liquidated Damages term and conditions to be used.
What must the client serve to get liquidated damages?
Notice of Liquidated Damages
Withholding Notice