Managing Time in JCT and NEC Flashcards
What are the main stages of JCT?
Date of Possession
Regularly and Diligently carry out the Works
Completion Date
What are the main stages of NEC?
Access Date (Starting Date)
Plan programme of work to measure progress
Completion Date
What does time is at large mean?
What does time is of the essence mean?
Time is at large
When the Contractor can finish the Works with no deadline attached, ASLONG as it is within a reasonable time.
Time is of the essence
When the Client needs the project the finish at it’s original completion date. Variations and/or an acceleration programme is suggested to achieve the original Completion date.
What are the 4 possible completion stages in JCT?
Practical Completion
Sectional Completion
Partial Possession
Completion of Making Good
What does practical completion mean?
Completion for all practical purposes based upon the clients requirements.
What are the effect of practical completion?
- Rectification Period begins
- The client is responsible for the insurance
- 6 months defect liability period occurs
- End of contractor’s liability to Liquidated
Damages; - Start of the 6 month period for preparation of
final accounts - Half the Retention money is released;
What does sectional completion mean?
Part of the Works have been complete and the Client gains possession of the Works.
What is partial possession in JCT?
Allows the client, to take possession of part(s) of
the works WITH consent of the contractor
What is the Rectification period?
Period within which contractor is liable to make good
any defects
What is a snagging list?
A list the A/CA (JCT) or PM/Supervisor/Supervisors Assistant* (NEC) issues to provide a list of the defects found
What is a key date?
A date by which work is to meet the condition stated in the contract data.
What are time risk allowances?
Time risk allowances are a required part of an ECC project programme (clause 31.2).
If a contractor identifies an activity float in the programme as a “time risk allowance”, that is protected in the same way as the terminal float.
In other words, “the contractor owns the time risk allowances”.
What does Takeover mean in NEC?
Take over is about who is using the building (works) But, once completion is certified, the employer has to take them over within 2 weeks (unless the contract data says differently) whether they are actually using them or not.
The project manager certifies the date of the take over.
What is the effect of Completion in NEC?
Completion Date is a fixed milestone and is the trigger point for which delay damages would be applicable
What is Planned Completion and what is the effect of it?
When the contractor “plans” to finish and in simple terms is linked to the contractor’s last planned site
activity (activities required to meet the Completion).
The planned completion date can be adjusted however it has no effect on the Completion Date