Payment Flashcards
What are the 3 payment types? explain the 3 types
Advance payment; not allowed in uk
Interim payment;
Final payment
What is an interim valuation?
An interim valuation is when the total cost of that period is valued and a financial sum is provided to the contractor from the client.
An interim valuation gives the Contractor an opportunity to view how that period was valued in the PM’s point of view
What is a bond?
A bond allows the client/contractor (in this scenario the client) to directly gain a financial amount back when the other party becomes insolvent. The bondsmen must provide the financial amount back to those who receive the bond.
When is a Contractor entitled to periodic payments?
Contractors are entitle to periodic payments unless projects has duration of less than 45 days
What if no amount or interval has been agreed?
Part II of The Scheme determines the amount and interval
What is an interim certificate?
Interim certificates provide a mechanism for the client to make payments to the contractor before the works are complete.
State the key dates in order to provide a interim payment certificate and interim payment.
Also how many days before the interim payment is a witholding notice required?
- Contractor/QS calculates payment 7 days before the interim certificate
- 5 days payment notice by CA after the due interim certificate
- 14 days to make the payment for the interim payment
- 5 days before the interim payment to provide a withholding notice.
- An interim certificate period is 1 month long
What is included in the Interim Valuation Payment ?
1) Measured works;
2) Preliminaries;
3) Value of variations;
4) Materials on site Cl.4.16.2;
5) Off-site materials and goods – Cl.4.17;
6) Fluctuations – Cl.4.21;
7) Retention – Cl.4.18;
8) Claims – Cl.23.
Name the different types of Certificates in JCT and NEC
JCT Interim Certificate Final Certificate Practical Completion Non-Completion Completion of making good
NEC
Completion Certificate
Defect Certificate
Payment Certificates
How is the payment calculated in NEC?
The PM assess the amount on each assessment date and provides an interim payment certificate within 1 week of the assessment date.
When are the assessment dates in NEC?
The first assessment interval is decided by PM
The assessment dates occur at the end of each assessment interval until 4 weeks after the Superverisor issues the Defects Certificate and on the Completion date.
What is the payment procedure in NEC?
7 days before the certificate is the PM assessment
21 days to provide payment for the PM certificates
How do the main option clauses affect the amount of payment?
The rules for calculating amounts due for both interim and final payments vary according to the main options used
What is the payments for in Option C of NEC?
- Interim amounts – defined cost plus fee
2. Final amount – tendered price as the activity schedule plus or minus the contractor’s share
Does the Contract need to submit a payment application?
NEC
No, the PM must calculate the payment even if the Contractor does not provide a payment application
JCT
Contractor must provide a payment application 7 days before the interim certification date.