Defects and Testing of Defects Flashcards
What is a defect in Contract Management?
Works’ which carry different characteristics compared to the works’ described in the WI. An example of this would be cracking or if the Works have not been carried out as it should have.
When is the PM/CA able to issue an instruction regarding the testing of defects
Whenever he is suspicious of a defect, usually during the Supervisors/supervisors assistants inspection
What is a latent defect? What is a patent defect?
Latent defect - defects which are not discover-able by a mere inspection
Patent Defect- defects which are discover-able by an inspection
When is a defect test is viable?
When the PM or Supervisors assistants gains suspicion of a defect during the Works’ or during the inspection
Is there a difference between the JCT and NEC regarding defects?
JCT
The A/CA must provide an instruction of a schedule of defects NOT later than 14 days after the expiry of that Rectification Period.
NEC
Until the defect date, the Supervisor can instruct the Contractor to look for defects, with a reason.
Until the defect date, the Supervisor notifies the Contractor of each defect as soon as he finds it. The supervisor notifies the Contractor when he finds,
What are the roles and responsibilities of the Supervisor?
The Supervisor is the custodian of quality HOWEVER the PM has the extensive powers.
the Supervisor exercises control over:
- investigation
- notification
- certification.
- notify the Contractor of any Defects they may
discover
5.Control reverts to the Project Manager for acceptance of uncorrected Defects
What are the roles and responsibilities of the Contractor?
- Defects are the Contractors liability
2.Notify the Supervisor of any Defects they may
discover - Search for defects if instructed to do so
- correct a Defect, whether notified of it or not;
5.correct notified Defects within the defects correction period.
What are the roles and responsibilities of the Supervisor?
- Quality checker
- Ability to exercise control over investigation, notification and certification
3.
What is the process for defect testing?
The Supervisor and Contractor notify each other
before their respective tests start and, when the
tests has been completed, they notify each other
of the results
What are the consequences for not spotting or amending defects?
The Employer has the ability to hire a third party to amend the defects and surcharge the Contractor
What are the roles and responsibilities of the Client?
The employer must provide access
The employer can inform the Contractor of defects.
HOWEVER the Contractor may not be liable for them if:
- the defect liability period (X18.5/X18) has expired or;
- the Contractors responsibility for latent defects has expired.
What is provided after amending the defects?
Certificate of Making Good (JCT) Defects Certificate (NEC)
Who is liable if collateral damage occurs during defect testing?
Depends on whether there was a defect or not??
Is a defect a compensation event?
No. Changing the Works Information in order to accept a Defect is one of the exceptions listed in Clause 60.1.
What are the options for amending a defect?
Amend the defect
Not amend the defect
Have a third party amend the defect