Procurement Flashcards

1
Q

Cost plus fixed fee/ cost plus percentage of costs

A

Costs plus fixed fee (CPFF) or Cost Plus Percentage of Costs (CPPC) means buyer will pay the seller back for the costs involved in doing the project work, plus an agreed amount (or fixed fee) that buyer will pay on top of that.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Fixed Price Contracts

A

A contract where the price is predetermined and fixed, regardless of the actual costs incurred during the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Fixed price with economic price adjustment contracts (FP - EPA)

A

With this particular contract, both buyer and seller agree on pre-defined criteria for the price adjustment. This is possible because of the uncertainties present in the market. It is important to take note that the dynamics in the market changes over time and this is the reason why this particular contract is beneficial for long-term projects or those that span multiple years.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Cost Plus Incentive Fee (CPIF)

A

a cost-reimbursement contract that provides for an initially negotiated fee to be adjusted later by a formula based on the relationship of total allowable costs to total target costs.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Producer Price Index (PPI)

A

measures the average change over time in the selling prices received by domestic producers for their output.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Arbitration Clause

A

Arbitration is a form of dispute resolution in which the parties to a contract agree to have their dispute resolved by a third-party decision-maker, rather than through litigation, and agree that this third party’s ruling will be binding on them.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Force Majeure

A

Contracts frequently include an act of God clause, also written as force majeure clause, to allow for non-performance in the event an act of God makes completing the contract impossible.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Termination Clause

A

provides a pre-set agreement on what will happen when the employee is terminated in terms of how much notice they get and/or what sort of payment they will receive.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

SIPOC

A

(suppliers, inputs, process, outputs, customers) diagram is a visual tool for documenting a business process from beginning to end prior to implementation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Procurement Audit

A

reviewing procurement contracts, processes, and history with vendors to ensure accuracy, compliance with the terms stipulated in your contract, and improve efficiency

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Time and materials contract

A

commonly used in the construction industry. One party agrees to pay a contractor for the costs of all materials needed to finish a job as well as a predetermined hourly wage for the work performed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Cost plus award fee (CPAF)

A

A contract where the contractor recovers actual costs incurred for completed work and is awarded a fee based on performance. Actual costs include general administration, overhead, labor and fringe benefits, other direct costs, and materials, including mark-up.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Seller rating system

A

A method that uses information such as the seller’s past performance, quality ratings, delivery performance and contractual compliance. These rating systems are used in addition to the proposal evaluations screening system to select sellers.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Build or Buy

A

The process of gathering and organizing data about product requirements and analyzing them against available alternatives, including the purchase or internal manufacture of the product.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Alternative dispute resolution

A

refers to the different ways people can resolve disputes without a trial.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Target Cost

A

Estimated cost of the project without profit

17
Q

Target fee

A

Profits for the seller

18
Q

Target price

A

Cost + fee

19
Q

Buyer’s share ratio

A

Ratio of costs buyer payed (80/20)

20
Q

Ceiling price

A

Maximum price buyer pays

21
Q

Point of total assumption

A

The point of total assumption (PTA) is a point on the cost line of the profit-cost curve determined by the contract elements associated with a fixed price plus incentive-Firm Target (FPI) contract above which the seller effectively bears all the costs of a cost overrun.

22
Q

Request for proposal (RFP)

A

request for proposal. An RFP is a formal request sent from a buyer to potential vendors seeking a product, service or solution. The RFP document asks all vendors the same questions. Then, interested vendors submit their answers in a proposal document for consideration.

23
Q

Source selecting criteria

A

describes properties that are crucial for a purchaser when deciding on a supplier. Criteria can be subjective or objective. Individual judgment can be biased, which may require balancing with objective measures.

24
Q

Procurement strategy

A

documents how your organisation runs its procurement function. It provides an overview of your governance framework and a roadmap for the way your organisation conducts its procurement activity.

25
Q

Procurement statement of work

A

A document that describes the work and activities that the seller is required to complete. The activities also include meetings, reports and communications.