Process Inputs Flashcards
1
Q
Acquire Resources
A
- Project Management Plan
- Project Documents
- Enterprise Environmental Factors
- Organizational Process Assets
2
Q
Close Project or Phase
A
- Project Charter
- Project Management Plan
- Project Documents
- Accepted Deliverables
- Business Documents
- Agreements
- Procurement Documentation
- OPA
3
Q
Collect Requirements
A
- Project Charter
- Project Management Plan
- Project Documents
- Business Documents
- Agreements
- EEF
- OPA
4
Q
Conduct Procurements
A
- Project management plan
- Project documents
- Procurement Documentation
- Seller proposals
- EEF
- Organizational process assets
5
Q
Control Costs
A
- Project management plan
- Project documents
- Project Funding Requirements
- Work performance data
- Organizational process assets
6
Q
Control Procurements
A
- Project management plan
- Project documents
- Agreements
- Procurement Documentation
- Approved Change Requests
- Work performance data
- EEF
- OPA
7
Q
Control Quality
A
- Project Management Plan
- Project Documents
- Approved Change Requests
- Deliverables
- Work Performance Data
- EEF
- OPA
8
Q
Control Resources
A
- Project Management Plan
- Project Documents
- Work Performance Data
- Agreements
- OPA
9
Q
Control Schedule
A
- Project management plan
- Project documents
- Work performance data
- Organizational process assets
10
Q
Control Scope
A
- Project management plan
- Project Documents
- Work performance data
- Organizational process assets
11
Q
Monitor Stakeholder Engagement
A
- Project management plan
- Project Documents
- Work performance data
- EEF
- OPA
12
Q
Create WBS
A
- Project Management Plan
- Project Documents
- Enterprise environmental factors
- Organizational process assets
13
Q
Define Activities
A
- Project management plan
- Enterprise environmental factors
- Organizational process assets
14
Q
Define Scope
A
- Project charter
- Project Management Plan
- Project Documents
- EEF
- Organizational process assets
15
Q
Determine Budget
A
- Project management plan
- Project Documents
- Business Documents
- Agreements
- EEF
- Organizational process assets
16
Q
Develop Project Charter
A
- Business Documents
- Agreements
- Enterprise environmental factors
- Organizational process assets
17
Q
Develop Project Management Plan
A
- Project charter
- Outputs from other processes
- Enterprise environmental factors
- Organizational process assets
18
Q
Develop Schedule
A
- Project Management Plan
- Project Documents
- Agreements
- Enterprise environmental factors
- Organizational process assets
19
Q
Develop Team
A
- Project Management Plan
- Project Documents
- EEF
- OPA
20
Q
Direct and Manage Project Work
A
- Project management plan
- Project Documents
- Approved Change Requests
- Enterprise environmental factors
- Organizational process assets
21
Q
Estimate Activity Durations
A
- Project Management Plan
- Project Documents
- EEF
- OPA
22
Q
Estimate Activity Resources
A
- Project Management Plan
- Project Docuements
- Enterprise environmental factors
- Organizational process assets
23
Q
Estimate Costs
A
- Project Management Plan
- Project Documentr
- Enterprise environmental factors
- Organizational process assets
24
Q
Identify Risks
A
- Project Management Plan
- Project Documents
- Agreements
- Procurement Documentation
- EEF
- OPA
25
Identify Stakeholders
* Project charter
* Business documents
* Project Management Plan
* Project Documents
* Agreements
* Enterprise environmental factors
* Organizational process assets
26
Implement Risk Responses
* Project Management Plan
* Project Documents
* OPA
27
Manage Communications
* Project Management Plan
* Project Documents
* Work Performance Reports
* EEF
* OPA
28
Manage Project Knowledge
* Proejct Management Plan
* Project Documents
* Deliverables
* EEF
* OPA
29
Manage Quality
* Project Management Plan
* Project Documents
* OPA
30
Manage Stakeholder Engagement
* Project Management Plan
* Project Documents
* EEF
* OPA
31
Manage Team
* Project Management Plan
* Project Documents
* Work Performance Reports
* Team Performance Assessments
* EEF
* Organizational process assets
32
Monitor and Control Project Work
* Project management plan
* Project Documents
* Work performance information
* Agreements
* Enterprise environmental factors
* Organizational process assets
33
Monitor Communications
* Project management plan
* Project documents
* Work performance data
* EEF
* Organizational process assets
34
Monitor Risks
* Project management plan
* Project Documents
* Work performance data
* Work performance reports
35
Perform Integrated Change Control
* Project management plan
* Project Documents
* Work performance reports
* Change requests
* Enterprise environmental factors
* Organizational process assets
36
Perform Qualitative Risk Analysis
* Project Management Plan
* Project Documents
* Enterprise environmental factors
* Organizational process assets
37
Perform Quantitative Risk Analysis
* Project Management Plan
* Project Documents
* Enterprise environmental factors
* Organizational process assets
38
Plan Communications Management
* Project management plan
* Project Charter
* Project Documents
* Enterprise environmental factors
* Organizational process assets
39
Plan Cost Management
* Project management plan
* Project charter
* Enterprise environmental factors
* Organizational process assets
40
Plan Resource Management
* Project management plan
* Project Documents
* Enterprise environmental factors
* Organizational process assets
41
Plan Procurement Management
* Project Charter
* Business Documents
* Project Management Plan
* Project Documents
* Activity cost estimates
* Enterprise environmental factors
* Organizational process assets
42
Plan Quality Management
* Project management plan
* Project Charter
* Project documents
* Enterprise environmental factors
* Organizational process assets
43
Plan Risk Management
* Project management plan
* Project charter
* Project Documents
* Enterprise environmental factors
* Organizational process assets
44
Plan Risk Responses
* Project Management Plan
* Project Documents
* EEF
* OPA
45
Plan Schedule Management
* Project management plan
* Project charter
* Enterprise environmental factors
* Organizational process assets
46
Plan Scope Management
* Project Charter
* Project Management Plan
* Enterprise environmental factors
* Organizational process assets
47
Plan Stakeholder Engagement
* Project management plan
* Project Charter
* Project Documents
* Agreements
* Enterprise environmental factors
* Organizational process assets
48
Sequence Activities
* Project management plan
* Project Documents
* Enterprise environmental factors
* Organizational process assets
49
Validate Scope
* Project management plan
* Project Documents
* Verified deliverables
* Work performance data