Process Group and Knowledge Area Matrix Flashcards
PMBOK Guide, Sixth Edition, Table 1-4. Project Management Process Group and Knowledge Area Mapping, p. 25
Identify the five process groups.
- Initiating
- Planning
- Executing
- Monitoring and Controlling
- Closing
Identify the ten knowledge areas.
- Integration
- Scope
- Schedule
- Cost
- Quality
- Resource
- Communications
- Risk
- Procurement
- Stakeholder
Identify the two processes in the Initiating process group.
- 4.1 Develop Project Charter
- 13.1 Identify Stakeholders
Identify the twenty-four processes in the Planning process group.
- 4.2 Develop Project Management Plan
- 5.1 Plan Scope Management
- 5.2 Collect Requirements
- 5.3 Define Scope
- 5.4 Create WBS
- 6.1 Plan Schedule Management
- 6.2 Define Activities
- 6.3 Sequence Activities
- 6.4 Estimate Activity Duration
- 6.5 Develop Schedule
- 7.1 Plan Cost Management
- 7.2 Estimate Costs
- 7.3 Determine Budget
- 8.1 Plan Quality Management
- 9.1 Plan Resource Management
- 9.2 Estimate Activity Resources
- 10.1 Plan Communications Management
- 11.1 Plan Risk Management
- 11.2 Identify Risks
- 11.3 Perform Qualitative Risk Analysis
- 11.4 Perform Quantitative Risk Analysis
- 11.5 Plan Risk Responses
- 12.1 Plan Procurement Management
- 13.2 Plan Stakeholder Engagement
Identify the ten processes in the Executing process group.
- 4.3 Manage and Direct Work
- 4.4 Manage Project Knowledge
- 8.2 Manage Quality
- 9.3 Acquire Resources
- 9.4 Develop Team
- 9.5 Manage Team
- 10.2 Manage Communications
- 11.6 Implement Risk Responses
- 12.2 Conduct Procurements
- 13.3 Manage Stakeholder Engagement
Identify the twelve processes in the Monitoring and Controlling process group.
- 4.5 Monitor and Control Project Work
- 4.6 Perform Integrated Change Control
- 5.5 Validate Scope
- 5.6 Control Scope
- 6.6 Control Schedule
- 7.4 Control Costs
- 8.4 Quality Control
- 9.6 Control Resources
- 10.3 Monitor Communications
- 11.7 Monitor Risks
- 12.3 Control Procurements
- 13.4 Monitor Stakeholder Engagement
Identify the one process in the Closing process group.
- 4.7 Close Project or Phase
Identify the seven processes in the Project Integration Management knowledge area.
Identify the six processes in the Project Scope Management knowledge area.
Identify the six processes in the Project Schedule Management knowledge area.
Identify the four processes in the Project Cost Management knowledge area.
Identify the three processes in the Project Quality Management knowledge area.
Identify the six processes in the Project Resource Management knowledge area.
Identify the three processes in the Project Communications Management knowledge area.
Identify the seven processes in the Project Risk Management knowledge area.
Identify the three processes in the Project Procurement Management knowledge area.
Identify the four processes in the Project Stakeholder Management knowledge area.
4.1
Develop Project Charter
- Initiating PG
- Integration KA
4.2
Develop Project Management Plan
- Planning PG
- Integration KA
4.3
Direct and Manage Project Work
- Executing PG
- Integration KA
4.4
Manage Project Knowledge
- Executing PG
- Integration KA
4.5
Monitor and Control Project Work
- Monitoring and Controlling PG
- Integration KA
4.6
Perform Integrated Change Control
- Monitoring and Controlling PG
- Integration KA
4.7
Close Project or Phase
- Closing PG
- Integration KA
5.1
Plan Scope Management
- Planning PG
- Scope KA
5.2
Collect Requirements
- Planning PG
- Scope KA