5. Project Scope Management Flashcards
Identify the six processes in the Project Scope Management knowledge area.
5.1 Understand the six project management processes in the project scope management knowledge area.
Includes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully.
- 1 Plan Scope Management
- 2 Collect Requirements
- 3 Define Scope
- 4 Create WBS
- 5 Validate Scope
- 6 Control Scope
* PMBOK Guide, Sixth Edition, 5 - Project Scope Management, p. 129*
Plan Scope Management.
5.1 Understand the six project management processes in the project scope management knowledge area.
The process of creating a scope management plan that documents how the project and product scope will be defined, validated, and controlled.
Benefit: guide on how scope is managed
- performed once
- PMBOK Guide, Sixth Edition, 5.1 - Plan Scope Management, p. 134*
Collect Requirements.
5.1 Understand the six project management processes in the project scope management knowledge area.
The process of determining, documenting, and managing stakeholder needs and requirements to meet objectives.
Benefit: basis for defining product/project scope
- performed once
- PMBOK Guide, Sixth Edition, 5.2 - Collect Requirements, p. 138*
Define Scope.
5.1 Understand the six project management processes in the project scope management knowledge area.
(P)- The process of developing a detailed description of the project and product and acceptance criteria
Benefit: describe product boundaries and acceptance criteria
PMBOK Guide, Sixth Edition, 5.3 - Define Scope, p. 150
Create WBS.
5.1 Understand the six project management processes in the project scope management knowledge area.
(P) - The process of subdividing project deliverables and project work into smaller, more manageable components.
Benefit: Provides framework of what has to be delivered
PMBOK Guide, Sixth Edition, 5.4 - Create WBS, p. 156
- 5 Validate Scope.
* 5.1 Understand the six project management processes in the project scope management knowledge area.*
(MC) - formalizing acceptance of the completed project deliverables.
Benefit: brings objectivity to acceptance process. Increase probability of final product acceptance
PMBOK Guide, Sixth Edition, 5.5 - Validate Scope, p. 163
- 6 Control Scope.
* 5.1 Understand the six project management processes in the project scope management knowledge area.*
(MC) - The process of monitoring the status of the project and product scope and managing changes to the scope baseline.
Benefit: Scope baseline maintained throughout project
PMBOK Guide, Sixth Edition, 5.6 - Control Scope, p. 167
Identify the inputs, tools, techniques, and outputs for the following process: Plan Scope Management.
5.2 Identify the inputs, tools, techniques, and outputs defined in the six processes in project scope management.
PMBOK Guide, Sixth Edition, Figure 5-2. Plan Scope Management: Inputs, Tools & Techniques, and Outputs, p. 134
Identify the inputs, tools, techniques, and outputs for the following process: Collect Requirements.
5.2 Identify the inputs, tools, techniques, and outputs defined in the six processes in project scope management.
PMBOK Guide, Sixth Edition, Figure 5-4. Collect Requirements: Inputs, Tools & Techniques, and Outputs, p. 138
Identify the inputs, tools, techniques, and outputs for the following process: Define Scope.
5.2 Identify the inputs, tools, techniques, and outputs defined in the six processes in project scope management.
PMBOK Guide, Sixth Edition, Figure 5-8. Define Scope: Inputs, Tools & Techniques, and Outputs, p. 150
Identify the inputs, tools, techniques, and outputs for the following process: Create WBS.
5.2 Identify the inputs, tools, techniques, and outputs defined in the six processes in project scope management.
PMBOK Guide, Sixth Edition, Figure 5-10. Create WBS: Inputs, Tools & Techniques, and Outputs, p. 156
Identify the inputs, tools, techniques, and outputs for the following process: Validate Scope.
5.2 Identify the inputs, tools, techniques, and outputs defined in the six processes in project scope management.
PMBOK Guide, Sixth Edition, Figure 5-15. Validate Scope: Inputs, Tools & Techniques, and Outputs, p. 163
Identify the inputs, tools, techniques, and outputs for the following process: Control Scope.
5.2 Identify the inputs, tools, techniques, and outputs defined in the six processes in project scope management.
PMBOK Guide, Sixth Edition, Figure 5-17. Control Scope: Inputs, Tools & Techniques, and Outputs, p. 167
What are the key concepts for Project Scope Management?
5.3 Identify key concepts and tailoring considerations for project scope management, and key roles in scope management.
tl;dr
- product v. project
- upfront v. iteratively
- completion comparison
quotes
- [product v. project] Scope can refer to product scope (the features and functions that characterize a product, service, or result), or to project scope (the work performed to deliver a product, service, or result with the specified features and functions).
- [upfront v. iteratively] Project life cycles range along a continuum from predictive to adaptive or agile. In a life cycle that uses a predictive approach, the project deliverables are defined at the beginning of the project and any changes to the scope are progressively managed. In an adaptive or agile approach, the deliverables are developed over multiple iterations where a detailed cope is defined and approved for each iteration when it begins.
- [completion comparison] Completion of the project scope is measured against the project management plan. Completion of the product scope is measured against the product requirements.
PMBOK Guide, Sixth Edition, Appendix X4: X4.2 - Key Concepts for Project Scope Management, p. 674
What tailoring considerations should a project manager have for project scope management?
5.3 Identify key concepts and tailoring considerations for project scope management, and key roles in scope management.
- Knowledge and requirements management. Does the organization have formal or informal knowledge and requirements management systems? What guidelines should the project manager establish for requirements to be reused in the future?
- Validation and control. Does the organization have existing formal or informal validation and control-related policies, procedures, and guidelines?
- Development approach. Does the organization use agile approaches in managing projects? Is the development approach iterative or incremental? Is a predictive approach used? Will a hybrid approach be productive?
- Stability of requirements. Are there areas of the project with unstable requirements? Do unstable requirements necessitate the use of lean, agile, or other adaptive techniques until they are stable and well defined?
- Governance. Does the organization have formal or informal audit and governance policies, procedures, and guidelines?
PMBOK Guide, Sixth Edition, 5.0 - Project Scope Management, p. 133