7. Project Cost Management Flashcards

1
Q

Define the following knowledge area: Project Cost Management.

7.1 Understand the four project management processes in the project cost management knowledge area

A

Includes the processes involved in planning, estimating, budgeting, financing, funding, managing, and controlling costs so that the project can be completed within the approved budget.

financial aspect of a project – development of strategy for how you will estimate and budget costs, obtaining the funds & monitoring & controlling the expenses throughout the project’s life cycle.

Overall goal of this step is to ensure you complete your project within the approved project’s budget

  1. 1 Plan Cost Management
  2. 2 Estimate Costs
  3. 3 Determine Budget
  4. 4 Control Costs
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Define the following process: Plan Cost Management.

7.1 Understand the four project management processes in the project cost management knowledge area

A

(P) - Define how the project costs will be estimated, budgeted, managed, monitored, and controlled.

Benefit: guidance on how costs will be managed

  • performed once
  • PMBOK Guide, Sixth Edition, 7.1 - Plan Cost Management, p. 235*
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Define the following process: Estimate Costs.

7.1 Understand the four project management processes in the project cost management knowledge area

A

(P) - The proccess of developing an approximation of the cost of resources needed to complete project work.

  • Estimate costs of all resource costs

Benefit: Determines monetary resources needed for project

  • Performed periodically
  • PMBOK Guide, Sixth Edition, 7.2 - Estimate Costs, p. 240*
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Define the following process: Determine Budget.

7.1 Understand the four project management processes in the project cost management knowledge area

A

(P) - The proccess of aggregating the estimated costs of individual actvities or work packages to establish an authorized cost baseline.

Benefit: Determines cost baseline → used to monitor and control performance

  • performed once
  • PMBOK Guide, Sixth Edition, 7.3 - Determine Budget, p. 248*
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Define the following process: Control Costs.

7.1 Understand the four project management processes in the project cost management knowledge area

A

(MC) - Monitor the status and cost performance of the project to update the project costs and managing changes to the cost baseline. Monitor how resources are spent

cost performance vs cost baseline

Benefit: Cost baseline is maintained

  • Performed throughout
  • PMBOK Guide, Sixth Edition, 7.4 - Control Costs, p. 257*
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Identify the inputs, tools, techniques, and outputs of the following process: Plan Cost Management.

7.2 Identify the input, tools, techniques, and outputs defined in the six processes in project cost management

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Identify the inputs, tools, techniques, and outputs of the following process: Estimate Costs.

7.2 Identify the input, tools, techniques, and outputs defined in the six processes in project cost management

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Identify the inputs, tools, techniques, and outputs of the following process: Determine Budget.

7.2 Identify the input, tools, techniques, and outputs defined in the six processes in project cost management

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Identify the inputs, tools, techniques, and outputs of the following process: Control Costs.

7.2 Identify the input, tools, techniques, and outputs defined in the six processes in project cost management

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Identify key concepts for Project Cost Management.

7.3 Identify key concepts in project cost management, including tailoring and special considerations for agile/adaptive environments

A

tl;dr

  • ongoing use costs
  • stakeholder expectations
  • outsource performance analysis or nah

quotes

  • [ongoing use costs] This knowledge area should also consider the effect of project decisions on the subsequent recurring cost of using, maintaining, and supporting project deliverables.
  • [stakeholder expectations] Different stakeholders will measure project costs in different ways and at different times. Stakeholder requirements for managing costs should be considered explicitly.
  • [outsource performance analysis or nah] Predicting and analyzing the prospective financial performance of the project’s product may be performed outside the project, or it may be part of Project Cost Management.

PMBOK Guide, Sixth Edition, Appendix X4: X4.4 - Key Concepts for Project Cost Management, p. 674

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Identify the tailoring considerations for Project Cost Management.

7.3 Identify key concepts in project cost management, including tailoring and special considerations for agile/adaptive environments

A
  • Knowledge management. - past project histories, lessons learned
  • Estimating and budgeting. Does the organization have existing formal or informal cost estimating and budgeted-related policies, procedures, and guidelines?
  • Earned value management. Does the organization use earned value management in managing projects?
  • Use of agile approach. Does the organization use agile methodologies in managing projects? How does this impact cost estimating?
  • Governance. Does the organization have formal or informal audit and governance policies, procedures, and guidelines?

PMBOK Guide, Sixth Edition, 7 - Project Cost Management, p. 234

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Identify special consideration for agile/adaptive environments.

7.3 Identify key concepts in project cost management, including tailoring and special considerations for agile/adaptive environments

A
  • Lightweight estimation methods can be used to generate a fast, high-level forecast or project labor csts, which can then be easily adjusted as changes arise.
  • In cases where high-variability projects are also subject to strict budgets, the scope and schedule are more often adjusted to stay within cost constraints.

PMBOK Guide, Sixth Edition, 7 - Project Cost Management, p. 234

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is analogous cost estimating?

7.4 Understand and apply basic forecasting and earned value methods for project cost management

A

Historical data from similar activity to compare current work to previous, similar work. Analogous cost estimating uses values, or attributes, of a previous project that are similar to the current project. Comparison of these project values, or attributes, becomes the basis for estimating the same parameter or measurement for the current project.

  • High level of estimate
  • PMBOK Guide, Sixth Edition, 7.2.2.2 - Analogous Estimating, p. 244*
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is parametric cost estimating?

7.4 Understand and apply basic forecasting and earned value methods for project cost management

A

Parametric estimating uses a statistical relationship between relevant historical data and other variables (e.g. square footage in construction) to calculate a cost estimate for project work.

  • higher level of accuracy (depending on details)
  • PMBOK Guide, Sixth Edition, 7.2.2.3 - Parametric Estimating, p. 244*
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is bottom-up cost estimating?

7.4 Understand and apply basic forecasting and earned value methods for project cost management

A

The cost of individual work packages or activities is estimated to the greatest level of specified detail. The detailed cost is then summarized or “rolled up” to higher levels for subsequent reporting and tracking purposes.

PMBOK Guide, Sixth Edition, 7.2.2.4 - Bottom-Up Estimating, p. 244

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is three-point estimating?

7.4 Understand and apply basic forecasting and earned value methods for project cost management

A

A technique used to estimate cost or duration by applying an average or weighted average of optimistic, pessimistic, and most likely estimates when there is uncertainty with the individual activity estimates.

PMBOK Guide, Sixth Edition, Glossary, p. 724

  • Most likely (tM). The cost of the activity, based on realistic effort assessment for the required work and any predicted expenses.
  • Optimistic (tO). The cost based on analysis of the best-case scenario for the activity.
  • Pessimistic (tP). The cost based on analysis of the worst-case scenario for the activity.
  • Triangular Distribution- insufficient historical data
    • Most accurate est (cE) = (cO + cM + cP)/3
  • Beta Distribution - sufficient historical info
    • cE - (cO + 4cM + cP)/6

PMBOK Guide, Sixth Edition, 7.2.5.5 - Three-Point Estimating, p. 244

17
Q

What is earned value analysis?

7.4 Understand and apply basic forecasting and earned value methods for project cost management

A

Compares the performance measurement baseline to the actual schedule and cost performance. EVM integrates the scope baseline with the cost baseline and schedule baseline to form the performance measurement baseline.

PMBOK Guide, Sixth Edition, 7.4.2.2 - Data Analysis, p. 261

18
Q

What is variance at completion?

7.4 Understand and apply basic forecasting and earned value methods for project cost management

A

A projection of the amount of budget deficit or surplus, expressed as the difference between the budget at completion and the estimate at completion.

PMBOK Guide, Sixth Edition, Table 7-1 - Earned Value Calculations Summary Table, p. 267

19
Q

What is to complete performance index?

7.4 Understand and apply basic forecasting and earned value methods for project cost management

A

A measure of the cost performance that must be achieved with the remaining resources in order to meet a specified management goal, expressed as the ratio of the cost to finish the outstanding work to the budget available.

PMBOK Guide, Sixth Edition, Table 7-1 - Earned Value Calculations Summary Table, p. 267

20
Q

What is schedule variance?

7.4 Understand and apply basic forecasting and earned value methods for project cost management

A

The amount by which the project is ahead or behind the planned delivery date, at a given point in time, expressed as the difference between the earned value and the planned value.

PMBOK Guide, Sixth Edition, Table 7-1 - Earned Value Calculations Summary Table, p. 267

21
Q

What is schedule performance index?

7.4 Understand and apply basic forecasting and earned value methods for project cost management

A

A measure of schedule efficiency expressed as the ratio of earned value to planned value.

PMBOK Guide, Sixth Edition, Table 7-1 - Earned Value Calculations Summary Table, p. 267

22
Q

What is planned value?

7.4 Understand and apply basic forecasting and earned value methods for project cost management

A

The authorized budget assigned to scheduled work.

PMBOK Guide, Sixth Edition, Table 7-1 - Earned Value Calculations Summary Table, p. 267

23
Q

What is estimate to complete?

7.4 Understand and apply basic forecasting and earned value methods for project cost management

A

The expected cost to finish all the remaining project work.

PMBOK Guide, Sixth Edition, Table 7-1 - Earned Value Calculations Summary Table, p. 267

24
Q

What is estimate at completion?

7.4 Understand and apply basic forecasting and earned value methods for project cost management

A

The estimated total cost of completing all work expressed as the sum of the actual cost to date and the estimate to complete.

PMBOK Guide, Sixth Edition, Table 7-1 - Earned Value Calculations Summary Table, p. 267

25
Q

What is earned value?

7.4 Understand and apply basic forecasting and earned value methods for project cost management

A

The measure of work performed expressed in terms of the budget authorized for that work.

PMBOK Guide, Sixth Edition, Table 7-1 - Earned Value Calculations Summary Table, p. 267

26
Q

What is cost variance?

7.4 Understand and apply basic forecasting and earned value methods for project cost management

A

The amount of budget deficit or surplus at the given point in time, expressed as the difference between the earned value and the actual cost.

PMBOK Guide, Sixth Edition, Table 7-1 - Earned Value Calculations Summary Table, p. 267

27
Q

What is cost performance index?

7.4 Understand and apply basic forecasting and earned value methods for project cost management

A

A measure of the cost efficiency of budgeted resources expressed as the ratio of earned value to actual cost.

PMBOK Guide, Sixth Edition, Table 7-1 - Earned Value Calculations Summary Table, p. 267

28
Q

What is budget at completion?

7.4 Understand and apply basic forecasting and earned value methods for project cost management

A

The sum of all budgets established for the work to be performed.

PMBOK Guide, Sixth Edition, Table 7-1 - Earned Value Calculations Summary Table, p. 267

29
Q

What is actual cost?

7.4 Understand and apply basic forecasting and earned value methods for project cost management

A

The realized cost incurred for the work performed on an activity during a specified time period.

PMBOK Guide, Sixth Edition, Table 7-1 - Earned Value Calculations Summary Table, p. 267

30
Q

Cost Baseline

A

Approved version of time-phased project budget,i nclude contengency reserve, excluding management reserves.

  • basis for comparison to actual project results
  • shows how money will be spent
  • broken into phases
    *
31
Q

Trends and Practices

A
  1. Earned Value Management
  • Combines scope, schedule and resource measurements to assess project persformance and progress against baseline
  • best technique for controlling costs
    1. Earned Schedule
    1. Extension to EVM
    2. Replaces schedule variance measures with ES and Actual Time (AT)
    3. Schedule Variance = ES - AT
      1. if ES>0, project is considered ahead of schedule
32
Q

Cost Management Plan

A

covers processes:

  • estimating costs
  • develop time phased budget
  • monitor and control costs
  • level of authority associated with cost/budget
  • funding limitations
  • how/when costs are recorded
  • also:
    • units of measure
    • level of precision (round up or down)
    • control threshold
      • level of accuracy
33
Q

Progressive Elaboration with cost estimates

A

Project progresses, scope becomes clearer, estimates will be more accurate
Rough Order of Magnitude - Estimates of costs for early stages of project when scope and requiremtnets are not fully defined - might involve OPAs

34
Q

Performance Measurement Baseline

A

Used if EVM are applied

35
Q

Funding Limit Reconciliation

A

(T&T) - determines whether or not expenditure of funds exceeds any project funding limit

  • reschedule work to level out rate of expenditutres
    • imposing date constraints
36
Q

Management Reserve

A

budget witheld for managment control purpose. used for unforseen work

  • when used, added to cost baseline (needs approval. change in cost baseline)