PRAC GC 1 Flashcards
Which of the following post-construction services includes evaluation of initial programme versus actual use of the facility?
a. building/ground administration
b. owner’s association organisation
c. building/equipment maintenance
d. post-construction evaluation
d. post-construction evaluation
An architect has done the renovation/addition of a clinic residence in Manila. Project construction cost is three million pesos. Using UAP Standards, how much does the Architect expect to receive as a minimum basic fee from his client?
a. 400,000 pesos
b. 150,000 pesos
c. 300,000 pesos
d. 450,000 pesos
c. 300,000 pesos
What is generally the basis of the architect’s minimum basic fee?
a. owner’s offer
b. type of structure
c. architect’s professional community standing
d. project construction cost
d. project construction cost
In the architect’s post-construction services, under which services does the architect evaluate the initial programme versus the actual use of the facility?
a. building/equipment maintenance
b. design-build services
c. building grounds administration
d. post-construction evaluation
d. post-construction evaluation
Which of the following is NOT included in the Architect’s code “May I Always Build”?
a. humility
b. haste of mind
c. patience
d. artistry
b. haste of mind
In the architect’s design services, under which phase is the preparation of forms for contract-letting, invitation/instruction to bidders, and bidders proposal fall?
a. construction
b. design development
c. schematic design
d. contract documents
Actual answer: Bidding/Negotiation Phase
Under what percentage fee method, what would be the fee of the architect if he acts as a full-time supervisor of a project he designed and which costs 300 million pesos?
a. 500,000 pesos
b. 1.5 million pesos
c. one million pesos
d. three million pesos
d. three million pesos
Which of the following is NOT describe the multiple of direct personal expenses method of the architect’s compensation?
a. based on value of creative design
b. multiplier depends on project complexity
c. application to supervision work
d. applicable to pre-design services
c. application to supervision work
In the architect’s specialised allied services, under which services does the architect check/approve samples of planting materials/landscaping elements?
a. Physical Planning
b. Environmental Planning
c. Landscape Design
d. Interior Design
a. Physical Planning
Which of the following conditions is NOT TRUE in design-build services on guaranteed maximum cost?
a. Architect’s fee is 10% of Project Construction Cost, in addition to Fee for Regular Design Services
b. More than 10% excess of guaranteed maximum cost, paid by Architect
c. Architect’s fee is built-in in guaranteed maximum cost, including fee for regular design services
d. 10% excess of guaranteed maximum cost divided between the architect and the client.
d. 10% excess of guaranteed maximum cost divided between the architect and the client.
Who is responsible for insurance of liabilities on materials, workmanship, labour and property?
a. architect
b. construction manager
c. contractor
d. owner
b. construction manager
Under what condition may owner exercise the right to terminate a contract?
a. After 10 days’ notice
b. Bankruptcy insolvency to contractor
c. after 5 days’ notice
d. provide substitute materials
b. Bankruptcy insolvency to contractor
Which method of compensation for the architect’s services is flexible and any change will not affect owner-architect agreement?
a. Professional Fee plus Expenses
b. Multiple of Direct Personal Expenses
c. Per diem plus Reimbursable Expense
d. Percentage of Construction Cost
d. Percentage of Construction Cost
Under the Architect’s Code of Ethics, which of the following is unethical for the Architect to do?
a. Seeks success through solicited personal publicity
b. Asks fair remuneration for services rendered
c. Confines criticisms/praises within constructive/inspirational limits
d. Hold’s Client’s interest over and above self-interest for financial returns
a. Seeks success through solicited personal publicity
Under the Architect’s Code of Ethics, which of the following is unethical for the Architect to do?
a. Seeks success through solicited personal publicity
b. Asks fair remuneration for services rendered
c. Confines criticisms/praises within constructive/inspirational limits
d. Hold’s Client’s interest over and above self-interest for financial returns
a. Seeks success through solicited personal publicity
In Master Development Plan Formulation, which component is concerned with the movement of people/goods from one place to another?
a. economic
b. sociocultural
c. physical
d. transport
d. transport
In a typical owner-architect agreement, which of the following is chargeable to the owner?
a. structural/electrical/sanitary engineering
b. income taxes on professional fees
c. miniature models
d. five sets of contract documents
c. miniature models