PR S 40002 Flashcards

Temporary bridging

1
Q

When is temporary bridging allowed

A

to minimise disruption to rail traffic or users of level crossings when signalling equipment becomes damaged, disconnected or disarranged

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What must be considered for temporary bridging

A

The protection defeated is provided by an alternative means. Adequate testing is conducted to prove effectiveness of the portion of circuit to remain unbridged.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What contacts can be bridged

A

Generally confined to position indication or detection contacts of trackside equipment.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Trainstop protection

A

A trainstop protecting a series of suppressed trainstop must remain in the stop position

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

what part of the equipment is bridged

A

Bridging is generally applied to the removed or failed portion of equipment.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Where is the ideal location for bridging

A

To be applied as close as possible to the affected equipment. This includes the bridging authority form and accompanying circuit diagram

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What must be done to the opposite part of the circuit that is bridged

A

The opposite of the bridged circuit must be disconnected, for example If the Normal detection is bridged the Reverse detection must be disconnected.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What documentation is required for bridging and any additional documentation for planned works

A

Infrastructure Booking Authority NRF 003, PR S 40002 FM01, Marked up circuit diagram. A package with work instructions is required for planned works

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

How long can bridging be left in

A

16 weeks. Any longer and you need authority from the authorising engineer, the maintenance signal engineer and the Principal engineer signalling integrity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Prior to bridging, what is discussed in the briefing with the signal engineer and the person applying/removing the bridging

A

The bridging arrangements, alternate protection, testing requirements, and notification arrangements.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What needs to happen if the works cannot be completed in time

A

The authorising signal engineer must be contacted and a request for a time extension must be approved.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Can an engineer give verbal approval

A

Yes, they can. However it must be to an independent licensed signalling person who will transcribe the engineers instructions and write the name of the engineer on the form until a signature can be obtained

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

If the bridging is left unattended, what must be left with it.

A

A copy of the temporary bridging form PR S 40002 FM01 and the circuit diagram.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What do you need to do with the paperwork once the bridging is finished

A

You must fill in all required areas on the form, notify the authorising signal engineer and send a copy of the documents to the authorising signal engineer. He will then inspect and sign, then forward a copy to the maintenance signal engineer.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What needs to be on the circuit diagram

A

Temporary bridging for ___ Equipment at ___ Location on Date___ Time___ in accordance with bridging authority____.
Time and date of application and removal, and by who.
The authorising signal engineer signature.
any correlation and function testing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Temporary bridging wire requirements

A

1.5m length minimum, orange or brightly coloured, 1.5mm^2 CSA flexible stranded, 0.6/1kV rating, individually labelled, kept in a locked box by the signal engineer or delegated team leader, signed in and out on a register.

17
Q

What happens in an emergency if there is a need for a temporary bridging wire

A

A temporary bridge can be made with engineers approval, it must be fitted with a label and then destroyed immediately after use.

18
Q

What protection needs to be confirmed with the signaller

A

Protecting signals to be placed at stop, points levers to be in correspondence with position in field. blocking facilities to be applied to signals and points

19
Q

What notes are to be made on the IBA

A

“BRIDGED” to be written in next to equipment that has been bridged. example XYZ points BRIDGED.

20
Q

How do you secure points that are bridged.

A

Points to be booked out and disconnected, points to be clipped and SL locked, any releasing switches, EOL/ESML or half pilot staffs are to be falcon 8 locked

21
Q

How do you secure the Signals protecting the equipment temporarily bridged

A

The signals immediately protecting the equipment temporarily bridged are to be booked out and disconnected.
With engineers approval, some signals may be allowed to be booked in to facilitate train running

22
Q

What conditions are required to book in protecting signals over bridged points.

A

Testing is satisfactory, points are locked and spiked, level crossings have a qualified worker manually operate the crossing , ESML/EOL/half pilot staffs/releasing devices are falcon 8 locked, the signal engineer that makes the determination has suitable experience relative to the complexity of the nature

23
Q

Procedures for temporary bridging

A

Correlate to one clear point of intended temporary bridges, disconnect the portion of circuit leading to the bridges, disconnect the opposite detection circuit/contacts, apply bridges as per bridging authority only, do not bridge out portion of circuit not worked on.

24
Q

Can temporary bridges be shorter than 1.5m in length

A

yes they can be shortened to fit into closed equipment with the authority of the authorising signal engineer. need to be labelled as shorter than regulation.

25
Q

do you remove and replace the bridges inbetween shifts

A

NO

26
Q

Testing required when bridge is applied

A

Strap and function the bridged portion of the circuit with the temporary bridges.
Circuit function the non-bridged equipment contacts for the position in lay, to be verified in the control panel.

27
Q

What do you need to do with bridged points to be left unattended

A

Securing the bridges to ensure they are not tampered with, points to be XL locked and spiked, ESML/EOL to be falcon 8 locked.

28
Q

Testing upon removal of temporary bridging

A

Wire/null count where bridging was applied, circuit function test contacts in detection circuit for position in lay, operate to opposite side and function test circuit again.
correspondence/out of correspondence testing.

29
Q

Do non-vital signalling circuits require a bridging authority.

A

No however the maintenance signal engineer or signal works engineer shall have process in place to manage the application and removal of the bridging.