PMP Study From Coursera - 3 Flashcards
Refers to starting with a final task or milestone and moving backwards through the schedule to determine the shortest path
Backward Pass
The dollar amount used to measure against to find out whether a project is on track or not and to measure the success of the project
Baseline
The act of creating a fixed reference point of spending to measure and compare a project’s progress against
Baseline a Budget
Thinking about all the parts of a project from the beginning to the end–including making a list of anything that comes with an associated cost–and adding all of it together
Bottom-up Approach
The estimated monetary resources needed to achieve the project’s goals and objectives
Budget
A situation where a budget is set before the project begins
Budget Pre-Allocation
The possibility that the costs of a project will increase due to poor planning or expanding the project’s scope
Budget Risk
Extra time added to the end of a task or project to account for unexpected slowdowns or delays in work progress
Buffer
The amount of work that the people or resources assigned to the project can reasonably complete in a set period of time
Capacity
Refers to the act of allocating people and resources to project tasks and determining whether the necessary resources required to complete the work on time have been acquired
Capacity Planning
Capital expenses; refers to expenses which businesses incur to create a benefit in the future
CAPEX
The inflow and outflow of cash on a project
Cash Flow
A visual that shows the possible causes of an event or risk; also known as a fishbone diagram
Cause-and-Effect Diagram
The flow of information; includes everything that’s shared, how it’s shared, and with whom
Communication
A document that organizes the process, types, and expectations of communications for a project
Communication Plan
Money that is included to cover potentially unforeseen events that aren’t accounted for in a cost estimate
Contingency Budget
Money added to the estimated project cost to manage identified risks
Contingency Reserves
Costs that are incurred to prevent issues with products, processes, or tasks
Cost of Quality
The ratio of the percentage complete to the actual costs
Cost Performance Index (CPI)
The difference between the amount of budget expected to be spent on versus what is actually spent for work completed at a point in time
Cost Variance (CV)
The list of project milestones that must be reached in order to meet the project goal on schedule, as well as the mandatory tasks that contribute to the completion of each milestone
Critical Path
A flowchart that helps visualize the wider impact of a decision on the rest of a project
Decision Tree
A relationship between two project tasks, where the start or completion of one depends on the start or completion of the other
Dependency
A visual representing the dependencies in the flow of work during a project
Dependency Graph
Costs that occur directly in a project
Direct Costs
In the critical path method, the earliest possible date on which a task (or the project itself) can begin
Earliest Start Date
In the critical path method, the earliest possible date on which a task (or the project itself) can begin
Earliest Start Date
A technique where a project’s performance or actuals for budget and schedule are regularly monitored against the planned budget and schedule
Earned Value Management (EVM)
A prediction of the amount and difficulty of active work required to complete a task
Effort Estimation
A person’s ability to relate to the thoughts and feelings of others
Empathy
An issue that may cause a person to make unethical choices
Ethical Trap
In this type of dependency relationship, the first task must be completed before the second task can be completed
Finish-to-Finish (FF)
In this type of dependency relationship, the first task must be completed before the second task can start
Finish-to-Start (FS)
FA visual that shows the possible causes of an event or risk; also known as a cause-and-effect diagram
Fishbone Diagram
A contract that is paid for when certain milestones are reached
Fixed Contract
Costs that won’t change over the course of a project
Fixed Costs
The date on which work on a task must start in order to achieve a goal
Fixed Start Date
The amount of time that can be waited to begin a task before it impacts the project schedule and threatens the project outcome
Float
A cost estimate or prediction over a period of time
Forecast
Refers to starting at the beginning of a project task list and moving forward towards the end of the project
Forward Pass
A horizontal bar chart that visually maps out a project schedule and tasks, with clear breakdowns of who’s responsible for the work and when those tasks are due
Gantt Chart