PMP Glossary C Flashcards

1
Q

lead

A

a lead is when you start one task before the previous one is completely finished. It’s a way to speed things up by having some tasks overlap.
Using leads can help you finish a project sooner by having different parts of the project work at the same time.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

lead Example:

A

If you’re building a house, you might start painting the inside while the outside is still being worked on.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Why Lead is Useful

A

Leads help move things along faster, allowing you to get more done in less time.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Lag

A

A lag is the delay or waiting time between two tasks in a project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Lag Example

A

In painting a house, lag happens when, after applying the primer (Task 1), you wait 24 hours before applying the paint (Task 2) to let the primer dry properly.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Analogous Estimating(top-down estimating)

A

This relies on historical information to predict estimates, (i.e. Time, Budget, Difficulty), for current projects.
Often used when there is limited amount of information available. Cost less in Time and Money to uses, but it gives the least accuracy when it comes to estimating.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Analogous Estimating(top-down estimating) example:

A

For example, if a previous video project took 30 days and cost $10,000, you might estimate a similar new project will also take 30 days and cost $10,000. This approach is fast but less detailed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

why is it called top-down estimating?

A

It’s called top-down estimating because you start with a high-level estimate for the whole project, rather than breaking it down into detailed tasks.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Parametric

A

A technique that uses a statistical relationship between historical data and other variables (for example, square footage in construction, lines of code in software development) to calculate an estimate for activity parameters, such as scope,
cost, budget, and duration.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Parametric B

A

Parametric estimating uses statistical relationships between historical data and other variables to calculate estimates. It’s more precise than analogous estimating because it relies on measurable factors.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Example:

A

If laying 1 kilometer of road costs $500,000, and you need to build 3 kilometers, parametric estimating would give you:

3 kilometers × $500,000/kilometer = $1.5 million.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Three Point Estimate

A

Calculates an expected duration using a weighted average of 3 estimated, Optimistic, Pessimistic, Most Likely.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Example:

A

For a mobile app project, you estimate:

Optimistic: 4 weeks
Most Likely: 6 weeks
Pessimistic: 10 weeks

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

PERT (Program Evaluation and Review Technique)

A

is a project management tool used to analyze and represent the tasks involved in completing a project. It focuses on the time required to complete each task and the overall project timeline.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

PERT Key Features 01:

A

Uncertainty Management: PERT is useful for projects with uncertain activity durations, allowing for better risk management.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

PERT Key Features 02:

A

Three-Point Estimation: It typically uses optimistic, pessimistic, and most likely estimates to calculate expected task durations.

17
Q

PERT Key Features 03:

A

Network Diagram: PERT creates a visual representation of project tasks and their interdependencies, helping to identify the critical path and manage timelines effectively.

18
Q

PERT (Program Evaluation and Review Technique) Benefit

A

Overall, PERT helps project managers plan, schedule, and coordinate tasks more effectively, especially in complex projects.

19
Q

Bottom-Up Estimating

A
  1. The work has to be very detailed for this type of estimation to take place.
  2. Takes a very long time to complete, but highly accurate.
  3. You break down the work to the lowest levels and then aggregating the
    work back up to find an overall duration
20
Q

Bottom-Up Estimating B

A

is a project management technique where you estimate the costs and durations of individual tasks or components of a project and then aggregate those estimates to determine the total project estimate. This method is often more accurate than top-down estimating because it relies on detailed information about each task.

21
Q

Example:
For a project to build a new website, you might break it down into tasks like:

Research: $1,000
Design: $2,000
Development: $5,000
Testing: $1,500

A

Using bottom-up estimating, you would sum these individual costs to get the total project cost:

Total Cost = $1,000 + $2,000 + $5,000 + $1,500 = $9,500.

This gives you a comprehensive estimate for the entire project based on detailed task estimates.

22
Q

Reserve Analysis

A

is a project management technique used to determine and manage contingency reserves for unforeseen risks or uncertainties that may affect a project’s timeline or budget.

It involves evaluating the potential risks and their impact on the project, allowing for better planning and resource allocation.