PMP Glossary C Flashcards
lead
a lead is when you start one task before the previous one is completely finished. It’s a way to speed things up by having some tasks overlap.
Using leads can help you finish a project sooner by having different parts of the project work at the same time.
lead Example:
If you’re building a house, you might start painting the inside while the outside is still being worked on.
Why Lead is Useful
Leads help move things along faster, allowing you to get more done in less time.
Lag
A lag is the delay or waiting time between two tasks in a project.
Lag Example
In painting a house, lag happens when, after applying the primer (Task 1), you wait 24 hours before applying the paint (Task 2) to let the primer dry properly.
Analogous Estimating(top-down estimating)
This relies on historical information to predict estimates, (i.e. Time, Budget, Difficulty), for current projects.
Often used when there is limited amount of information available. Cost less in Time and Money to uses, but it gives the least accuracy when it comes to estimating.
Analogous Estimating(top-down estimating) example:
For example, if a previous video project took 30 days and cost $10,000, you might estimate a similar new project will also take 30 days and cost $10,000. This approach is fast but less detailed.
why is it called top-down estimating?
It’s called top-down estimating because you start with a high-level estimate for the whole project, rather than breaking it down into detailed tasks.
Parametric
A technique that uses a statistical relationship between historical data and other variables (for example, square footage in construction, lines of code in software development) to calculate an estimate for activity parameters, such as scope,
cost, budget, and duration.
Parametric B
Parametric estimating uses statistical relationships between historical data and other variables to calculate estimates. It’s more precise than analogous estimating because it relies on measurable factors.
Example:
If laying 1 kilometer of road costs $500,000, and you need to build 3 kilometers, parametric estimating would give you:
3 kilometers × $500,000/kilometer = $1.5 million.
Three Point Estimate
Calculates an expected duration using a weighted average of 3 estimated, Optimistic, Pessimistic, Most Likely.
Example:
For a mobile app project, you estimate:
Optimistic: 4 weeks
Most Likely: 6 weeks
Pessimistic: 10 weeks
PERT (Program Evaluation and Review Technique)
is a project management tool used to analyze and represent the tasks involved in completing a project. It focuses on the time required to complete each task and the overall project timeline.
PERT Key Features 01:
Uncertainty Management: PERT is useful for projects with uncertain activity durations, allowing for better risk management.