PMP Glossary B Flashcards

1
Q

Signed off

A

means that someone has reviewed, approved, and given formal authorization for something, usually a document, project, or decision.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Variance analysis

A

is the process of comparing actual performance to planned or expected results to identify differences, or “variances.”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Schedule Management

A

includes the processes required to
manage the timely completion of the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Rolling Wave Planning

A

Rolling Wave Planning details near-term tasks and refines future tasks over time, allowing flexibility as the project evolves.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Precedence Diagramming Method, (PDM)

A

is a project scheduling technique used to visualize the sequence and dependencies between activities in a project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Precedence

A

اولویت

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Finish to Start (The most commonly used )

A

The start of the successor’s work package depends upon the
completion of its predecessor work package

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Finish-to-Start (FS) ex:

A

You can’t start painting (Task B) until the walls are built (Task A) are finished.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Finish to Finish

A

The completion of the successor work package depends on the
completion of the predecessor work package

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Finish-to-Finish (FF) ex:

A

Editing a document (Task E) can only finish once the writing (Task F) is finished.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Start to Start

A

The start of the successor’s work package depends upon the
start of its predecessor work package

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Start-to-Start (SS) ex:

A

Pouring concrete (Task C) and leveling it (Task D) both start at the same time.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Start to Finish

A

One task (A) cannot finish until another task (B) starts.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Start-to-Finish (SF) ex:

A

Imagine a traffic light. The red light (Task A) cannot turn green until the light has started changing (Task B).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

وابستگی آغاز به پایان (SF):

A

تعریف: پایان یک کار بستگی به آغاز کار دیگری دارد.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

مثال

A

برداشتن پل موقت کار(ب) نمیتواند انجام شود تا وقتی که کار ساخت یا نصب پل دائمی (کار الف) شروع شده باشد.
در اینجا کار ب نمی تواند تمام شود تا زمانی که کار الف آغاز شود.

17
Q

توضیحات بیشتر:

A

پل دائمی (کار الف): این پل باید در حال ساخته شدن باشد. حتی اگر هنوز به طور کامل تکمیل نشده باشد، آغاز کار روی آن مهم است.

برداشتن پل موقت (کار ب): پس از شروع کار بر روی پل دائمی، شما می‌توانید به تدریج پل موقت را بردارید.

18
Q

Start-to-Finish (SF) ex c:

A

“The shop will not be officially closed until the last customer leaves.” In this case, the end of closing the shop is dependent on the start of the customers leaving.

19
Q

Start-to-Finish (SF) ex b:

A

We can’t have an empty glass until we drink the water

20
Q

Mandatory dependencies, or hard logic

A

are essential task relationships in a project that must occur in a specific sequence.

21
Q

Mandatory dependencies, or hard logic: EX:

A

Paint can’t be applied until drywall is up.

22
Q

Discretionary dependencies, or soft logic

A

These dependencies are flexible and are set based on preferred sequences rather than necessity.

23
Q

Discretionary dependencies, or soft logic ex:

A

Cooking both Dinner & Dessert at the same time in the oven