PM tools Flashcards
what is a GANTT chart?
provides a visual of what needs to be done and when. excellent for tracking schedules because you can see interdependencies between tasks. NOT EFFECTIVE WHEN THERE IS A HIGH NUMBER OF ACTIVITIES.
what are the 4 types of relations/ interdependencies?
FS: one task must finish before another can start, most common
SS: several tasks can begin simultaneously
FF: a task cannot end until the previous one is completed
SF: least common task relationship, one task cannot end until another has started (shift work)
benefits of GANTT
break down a project in to manageable tasks
easily view dependencies and relationships
visualize and monitor the progress of tasks over time
identify a critical path
what is critical path analysis (CPA)?
used to identify activities on a critical path. breaks a project into tasks, displays them in a flow chart, and then calculates the project duration based on estimated time frames.
advantages of CPA
identifies most important tasks
reduces timelines
compares planned progress and actual progress
disadvantages of CPA
reliability is based on accurate estimates and assumptions
does not guarantee success of a project
resources may not be as flexible as planned
what is a PERT chart?
Program Evaluation and Review Technique
they map the project roadmap ahead. graphical representation of a project’s timeline, tasks, and the dependencies between those tasks.
when should you use a PERT chart?
when your project has simultaneously moving parts
when you’re conducting a feasibility study
what is the formula for the estimated expected duration of a project?
E = (O + 4M + P) / 6
E= estimated expected time O= optimistic time P= pessimistic time M= most likely time