PLANNING 24% Slide 134 Flashcards

1
Q
List the following processes in the order
in which they should be completed:
• Create WBS
• Collect Requirements
• Plan Scope Management
• Define Scope

Planning • Scope Management • Plan Scope Management

A
Although iterative, the general
order is as follows:
1) Plan Scope Management
2) Define Scope
3) Collect Requirements
4) Create WBS
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

The project management plan uses the
______ process to react to the realities of a constantly changing project environment.

Planning • Scope Management • Plan Scope Management

A

Change Control

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q
When the Develop Project
Management Plan (4.2) process
initially begins, it is a fully fledged
and comprehensive plan.
True or False:

Planning • Integration Management • Develop Project Management Plan

A
False
At this point in the project, the
project management plan is
merely a “shell”, and likely only
contains or references the project
charter, business documents, and
the stakeholder register.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q
Which input feeds into the Develop
Project Management Plan (4.2)
process to be the foundational
input to opening the project
management plan?

Planning • Scope Management • Plan Scope Management

A

Project charter

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

A project _____ meeting is a common practice to clearly communicate project objectives and
build team and stakeholder buy-in.

Planning • Scope Management • Plan Scope Management

A

Kick-off

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is the major output created
by the four scope management
processes in the Planning
Process Group?

Planning • Scope Management • Plan Scope Management

A

Scope baseline

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

_______ defines all the necessary work that is required
to complete the project.

Planning • Scope Management • Plan Scope Management

A

Project scope

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q
The development of other plans often
produces additional information and
realizations that make it necessary
to refine the scope and resource
management plans.
True or False:

Planning • Integration Management • Develop Project Management Plan

A

True
The planning process is iterative.
As each plan is created, it is very
common to adjust the scope.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

A ______ is a condition or capability that must be present in the finished product to satisfy
a business need.

Planning • Scope Management • Collect Requirements

A

Requirement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Why is the Collect Requirements
(5.2) process completed before the
Define Scope (5.3) process?

Planning • Scope Management • Define Scope

A

The Collect Requirements process transforms

highlevel requirements

into clear objectives required to

define the scope of the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is the difference between requirements documentation and requirements traceability matrix?

Planning • Scope Management • Collect Requirements

A

The requirements documentation
serves to clearly define all potential
project requirements needed for
creating the scope baseline.

The requirements traceability
matrix organizes and presents the
requirements in a visual manner
that links each requirement to the
individual deliverables that satisfy it.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

______ documentation details how each requirement
supports the project’s business needs.

Planning • Scope Management • Collect Requirements

A

Requirements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

The ____________ is used to
track the status of requirements
throughout the project.

Planning • Scope Management • Collect Requirements

A

Requirements

traceability matrix

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

A trained facilitator is often used in
the _______ process to obtain requirements from stakeholders and others with expert judgement.

Planning • Scope Management • Collect Requirements

A

Collect

Requirements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is the definition of an
affinity diagram?

Planning • Scope Management • Collect Requirements

A

An affinity diagram classifies
requirements into distinct
groups for review and analysis.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

_______ a model of the
potential product and providing it for review can be a fast and inexpensive method for obtaining
feedback on requirements.

Planning • Scope Management • Collect Requirements

A

Prototyping

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

A well-defined scope statement
creates clear boundaries,
reducing _______.

Planning • Scope Management • Define Scope

A

Scope creep

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

What is the project scope
statement?

Planning • Scope Management • Define Scope

A

Definition of the project and product scope,
major deliverables, assumptions, and
constraints.

The statement
clearly defines what is and is not
in the project scope.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

What is the difference between
project scope and product scope?

Planning • Scope Management • Define Scope

A

Project scope describes the work
performed to deliver a product,
service, or result.

Product scope describes the
features and functions of the
actual product, service, or result.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Three documents comprise the
scope baseline: _____, ______ ,_______

Planning • Scope Management • Create WBS

A

• Scope statement
• Work breakdown
structure (WBS)
• WBS dictionary

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

The lowest level of work in the WBS is
referred to as the work package.

True or False:
Planning • Scope Management • Create WBS

A
True
The work package is the lowest
level of the WBS and represents
the smallest amount of work
for which cost and duration can
be estimated and managed.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q
The WBS should follow the
\_\_\_\_\_\_\_\_\_\_ rule: the total of
all work at the lowest level (work
packages) should “roll up” so that
nothing is left out and no extra
work is performed.

Planning • Scope Management • Create WBS

A

100%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

The _______ and ______
are two major scheduling approaches.

Planning • Schedule Management • Plan Schedule Management

A

Critical path

method; agile

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q
List the following processes in the order
in which they should be completed:
• Define Activities
• Plan Schedule Management
• Sequence Activities
• Develop Schedule
• Estimate Activity Durations

Planning • Schedule Management • Plan Schedule Management

A

1) Plan Schedule Management
2) Define Activities
3) Sequence Activities
4) Estimate Activity Durations
5) Develop Schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

The _______ process describes
the actions that deliver the
deliverables created by the Create
WBS (5.4) process.

Planning • Schedule Management • Define Activities

A

Define Activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

An _____ is a distinct,
scheduled portion of work to
be performed.

Planning • Schedule Management • Define Activities

A

Activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

Why is the Create WBS (5.4) process
completed before the Define
Activities (6.2) process?

Planning • Schedule Management • Define Activities

A

The Create WBS process identifies
the work packages needed to satisfy
the project deliverables.

The Define Activities process is the first step in
transforming the work packages into
the detailed schedule of activities
that the team will complete.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

Activity attributes evolve and
deepen in description as the
project progresses.
True or False:

Planning • Schedule Management • Define Activities

A

True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

_______ have zero duration.
They define a point in time, not an
activity.

Planning • Schedule Management • Define Activities

A

Milestones

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

What is rolling wave planning?

Planning • Schedule Management • Sequence Activities

A

Rolling wave planning is an iterative technique to define

activities where the near-term work is planned in detail and later work is planned at a high level.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q
Which of the following relationship
types is the most common of the
precedence diagramming method?
A) Finish to start (FS)
B) Finish to finish (FF)
C) Start to start (SS)
D) Start to finish (SF)

Planning • Schedule Management • Sequence Activities

A

A) Finish to start (FS).
The successor cannot start until
the predecessor has finished.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
32
Q
Which of the following relationship
types is the least common of the
precedence diagramming method?
A) Finish to start (FS)
B) Finish to finish (FF)
C) Start to start (SS)
D) Start to finish (SF)

Planning • Schedule Management • Sequence Activities

A

D) Start to finish (SF)
The successor cannot finish
until predecessor has started.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
33
Q

What is the difference between
mandatory and discretionary
dependencies?

Planning • Schedule Management • Sequence Activities

A

Mandatory dependencies are
required by the nature of the work
or are legally or contractually
required.

Discretionary dependencies are
not mandatory, but are preferred,
usually based on best practices.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
34
Q

________ moves a successor LEFT (earlier);
________ moves a successor RIGHT (later).

Planning • Schedule Management • Sequence Activities

A

Lead;

lag

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
35
Q

_______ are calculated in terms of the number of work
periods needed to complete an activity.

Planning • Schedule Management • Estimate Activity Durations

A

Duration estimates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
36
Q

What two outputs produced by the Estimate Activity Durations (6.4) process are leveraged by the Develop
Schedule (6.5) process to produce the project schedule?

Planning • Schedule Management • Estimate Activity Durations

A
  • Duration estimates

* Basis of estimates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
37
Q

Duration estimates do not contain
any lags.
True or False:

Planning • Schedule Management • Estimate Activity Durations

A

True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
38
Q
Which of the following estimating techniques is less costly and time consuming, but also the least accurate?
A) Parametric estimating
B) Analogous estimating
C) Bottom-up estimating
D) Three-point estimating

Planning • Schedule Management • Estimate Activity Durations

A
B) Analogous estimating
Analogous estimating uses
historical data from similar
projects to produce a gross
value estimate for a project’s
activity duration.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
39
Q
Which of the following estimating
techniques uses a statistical or numerical
relationship to calculate activity
durations?
A) Parametric estimating
B) Analogous estimating
C) Bottom-up estimating
D) Three-point estimating

Planning • Schedule Management • Estimate Activity Durations

A

A) Parametric estimating

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
40
Q

________ estimating requires significant resources and time, but can be very accurate.

Planning • Schedule Management • Estimate Activity Durations

A

Bottom-up estimating
This technique aggregates
estimates of individual
lower-level activities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
41
Q

Which of the following estimating techniques
uses the triangular distribution mathematical
equation to incorporate risk and uncertainty
into the estimate?
A) Bottom-up estimating
B) Parametric estimating
C) Three-point estimating
D) Analogous estimating

Planning • Schedule Management • Estimate Activity Durations

A

C) Three-point estimating

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
42
Q

What’s the difference between
contingency reserves and
management reserves?

Planning • Cost Management • Estimate Costs

A
Contingency reserves address
known-unknowns (for example,
the project manager expects
rework but the exact amount is
unknown).

Management reserves
address unknown-unknowns
(unforeseen work).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
43
Q
When creating the cost baseline
in the Determine Budget process,
\_\_\_\_\_\_\_\_ reserves are included
in the baseline, but \_\_\_\_\_\_\_\_
reserves are not included.

Planning • Cost Management • Determine Budget

A

Contingency;

management

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
44
Q

Which of the following is not a core objective of
the Planning Process Group?
A) Define the project scope and objectives
B) Define the plans that will govern the
project
C) Identify, evaluate, and implement changes
D) Develop a course of action

Planning • Integration Management • Develop Project Management Plan

A
C) The identification, evaluation,
and implementation of changes
within the project is one of the two
core objectives of the Monitoring
and Controlling Process Group.

The second core objective of the
Monitoring and Controlling Process
Group is to track, regulate, and
review process completion.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
45
Q
The \_\_\_\_\_\_\_ process builds on
the progress started with the charter
by defining in greater detail how the
project will be executed, monitored
and controlled, and closed.

Planning • Integration Management • Develop Project Management Plan

A

Develop Project Management Plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
46
Q

After the time, scope, and cost baselines are defined within the project management plan, all future
changes can be made only through the _______ process.

Planning • Integration Management • Develop Project Management Plan

A

Perform Integrated Change
Control process (included in
the Monitoring and Controlling
Process Group)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
47
Q
List the following processes in the order in
which they should be completed:
• Identify Risks
• Plan Risk Management
• Perform Qualitative Risk Analysis
• Plan Risk Responses
• Perform Quantitative Risk Analysis

Planning • Risk Management • Plan Risk Management

A

1) Plan Risk Management
2) Identify Risks
3) Perform Qualitative Risk
Analysis
4) Perform Quantitative Risk
Analysis
5) Plan Risk Responses

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
48
Q
The project management plan
consolidates all subsidiary plans and
project baselines. Which of the following
is not one of the three project baselines?
A) Scope baseline
B) Schedule baseline
C) Benefits baseline
D) Cost baseline

Planning • Integration Management • Develop Project Management Plan

A

C) Benefits baseline
The benefits baseline is not
one of the project’s three core
baselines.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
49
Q

What is name of the plan that
documents how the project and
product scope will be defined,
validated, and controlled?

Planning • Scope Management • Plan Scope Management

A

Scope management plan

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
50
Q

Which document visually translates the project
deliverables into small, manageable components?

Planning • Scope Management • Create WBS

A

Work breakdown structure (WBS)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
51
Q

The __________ process describes
how the product and project
requirements will be analyzed,
documented, and managed.

Planning • Scope Management • Plan Scope Management

A

Requirements Management Plan (also
known as the business
analysis plan)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
52
Q

What is the definition of a
requirement?

Planning • Scope Management • Collect Requirements

A

A requirement is a condition/
capability that must be present
in the finished product to satisfy
a business need.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
53
Q

What are the two key outputs of the
Collect Requirements process?

Planning • Scope Management • Collect Requirements

A

Requirements documentation
and requirements traceability
matrix

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
54
Q

The requirement documentation
details how each requirement _____ the project’s
business need.

Planning • Scope Management • Collect Requirements

A

Supports

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
55
Q

The requirements traceability
matrix links each requirement to the
individual _____ that satisfy the requirement.

Planning • Scope Management • Collect Requirements

A

Deliverable

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
56
Q
Which data gathering technique
used to collect requirements involves
observing and comparing similar,
products, practices, processes, or
companies?

Planning • Scope Management • Collect Requirements

A

Benchmarking

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
57
Q

Which data representation technique
involves classifying large numbers of
ideas into distinct groups for review
and analysis?

Planning • Scope Management • Collect Requirements

A

Affinity diagramming

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
58
Q
The \_\_\_\_\_\_ process builds on
the Collect Requirements process,
selecting and defining the final
requirements list in detail and crafting
a descriptive scope statement.

Planning • Scope Management • Define Scope

A

Define Scope

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
59
Q

What is scope creep?

Planning • Scope Management • Define Scope

A

Scope creep is the
expansion of project
work beyond the
project boundaries.

60
Q

What is the one key output of the
Define Scope process?

Planning • Scope Management • Define Scope

A

Project scope statement

The project scope statement
provides a detailed definition of
the project and product scope,
major deliverables, assumptions,
and constraints.
61
Q
The \_\_\_\_\_\_\_\_\_ process
translates the project scope
statement (created in the 5.3 Define
Scope process) into an actionable
list of work that must be delivered.

Planning • Scope Management • Create WBS

A

Create WBS

62
Q

What is the key output created by
the Create WBS process?

Planning • Scope Management • Create WBS

A

Scope baseline
The scope baseline consists of
the scope statement, WBS, and
WBS dictionary.

63
Q

The ________ establishes
the standard by which work
completion is compared
throughout the project.

Planning • Scope Management • Create WBS

A

Scope baseline

64
Q

“Work” refers to the deliverables
produced, not the activities that
produce the deliverables.
True or False:

Planning • Scope Management • Create WBS

A
True
Using an example of a project to
dig a long ditch, the work would
be defined as the completed
ditch, not the activities required
to dig the ditch.
65
Q

What information does the WBS
dictionary provide?

Planning • Scope Management • Create WBS

A

The WBS dictionary provides

detailed information on the
delivery, activity, and schedule of
every component in the WBS.

66
Q

Name the technique used to create
the WBS by subdividing the scope
into progressively smaller, more
manageable parts.

Planning • Scope Management • Create WBS

A

Decomposition

67
Q

Define a work package.

Planning • Scope Management • Create WBS

A

lowest level of the WBS.

smallest amount of work for
which cost and duration can be
estimated and managed.

68
Q

How is the 100% rule used?

Planning • Scope Management • Create WBS

A
The 100% rule is used to confirm
that the total of all work at the
lowest level (work packages)
“rolls up” to the higher level in a
way that no work is omitted and
no extra work is performed.
69
Q

The schedule management processes in the Planning Process Group progressively translate the _____ of the scope baseline into a logically sequenced work schedule.

Planning • Schedule Management • Plan Schedule Management

A

Deliverables

70
Q

What is the purpose of the Define
Activities process?

Planning • Schedule Management • Define Activities

A

The Define Activities (6.2) process describes the actions that deliver
the deliverables defined by the Create WBS (5.4) process

71
Q

What are the three key outputs
produced by the Define Activities
process?

Planning • Schedule Management • Define Activities

A

Activity list, activity attributes, and

milestone list

72
Q

What is the definition of an
activity?

Planning • Schedule Management • Define Activities

A

An activity is a distinct, scheduled portion of work

to be performed.

73
Q

The _______ displays all of the specific actions required
to produce the work packages defined in the WBS.

Planning • Schedule Management • Define Activities

A

Activity list

74
Q

__________ extend the description of activities defined in the activity list, providing details on the effort
type and work location.

Planning • Schedule Management • Define Activities

A

Activity attributes
Activity attributes evolve and
deepen in description as the
project progresses

75
Q

The _______ document frames the schedule constraints
impacting the project.

Planning • Schedule Management • Define Activities

A
Milestone list
The milestone list is created as
an output of the Define Activities
process. The defined milestones
identify significant points/events
that are used in creating the
detailed schedule.
76
Q
The process \_\_\_\_\_\_\_  aims
to organize the activities into a
schedule network diagram that
graphically shows the order in
which work will be completed.

Planning • Schedule Management • Sequence Activities

A

Sequence Activities

77
Q

What is the key output produced
by the Sequence Activity process?

Planning • Schedule Management • Sequence Activities

A

Project schedule network diagram

The project schedule network
diagram shows the logical
relationships of all activities from
start to finish.

78
Q

Would the software required to build
a network diagram be classified as an
EEF or OPA?

Planning • Schedule Management • Sequence Activities

A

EEF
The software design is outside of
the control of the company and
therefore an EEF.

79
Q

What is the most common
relationship type in precedence
diagramming?

Planning • Schedule Management • Sequence Activities

A
Finish to start
When two activities have a
finish-to-start relationship, the
successor cannot start until the
predecessor has finished
80
Q

The _______ process brings depth and perspective to the network diagram by defining the amount of effort and resources each activity demands.

Planning • Schedule Management • Est. Activity Durations

A

Estimate Activity Durations

81
Q

The _______ process analyzes
all schedule data, created by processes 6.2 to 6.4, to define a comprehensive final schedule model
and schedule baseline.

Planning • Schedule Management • Develop Schedule

A

Develop Schedule

82
Q

The ___________ is the approved version of the schedule model used to evaluate actual vs. planned
progress throughout the project.

Planning • Schedule Management • Develop Schedule

A

Schedule baseline

83
Q

All project baselines must be
approved by the project sponsor.
True or False:

Planning • Schedule Management • Develop Schedule

A

True
All project baselines must be
approved by the project sponsor

84
Q

What key output created by the Develop Schedule process fully presents the planned start and finish dates for all activities in a clear visual format?

Planning • Schedule Management • Develop Schedule

A

Project schedule

85
Q

What is free float?

Planning • Schedule Management • Develop Schedule

A

Free float is the measure of the amount of time an activity can be delayed without delaying the early start of a successor activity.

86
Q

What is the difference between
free float and total float?

Planning • Schedule Management • Develop Schedule

A

Free float is the amount of time an
activity can be delayed without
delaying the early start of a
successor activity.

Total float is the amount of time
an activity can be delayed without
delaying the project finish date.

87
Q

What is the difference between crashing activities and fast tracking activities?

Planning • Schedule Management • Develop Schedule

A

Crashing refers to the addition of resources to reduce the time required to complete an activity.

Fast tracking refers to the reorganization of sequential
activities into parallel activities to reduce the time required to complete the activities.

88
Q

Which question explores the
opportunity for fast tracking
activities?

“Could these activities be done in
parallel?” or “How much faster
could this be done if we added
resources?”

Planning • Schedule Management • Develop Schedule

A

“Could these activities

be done in parallel?”

89
Q

What is the largest negative impact of crashing that must be evaluated and accounted for?

Planning • Schedule Management • Develop Schedule

A

Additional cost

90
Q

The Estimate Costs (7.2), Estimate Activity Durations (6.4), and Estimate Activity Resources (9.2) processes all have similar output structures. What are the
three key outputs produced by each of these processes?

Planning • Cost Management • Estimate Costs

A

Estimates, basis of estimates, and project document updates

91
Q

The process _______ develops an approximation of the
project’s total monetary resource need that is used in the Determine Budget process to create the cost baseline.

Planning • Cost Management • Estimate Costs

A

Estimate Costs

92
Q

The _________ explains the logic behind each cost estimate, allowing the team to understand how the costs were derived.

Planning • Cost Management • Estimate Costs

A

Basis of estimates

93
Q

What are the triangular and beta distribution three-point
estimating equations?

Planning • Cost Management • Estimate Costs

A

Triangular distribution:
cE = (cO + cM + cP) / 3

Beta distribution:
cE = (cO + 4*cM + cP) / 6

  • Most likely (cM)
  • Best case (cO)
  • Pessimistic (cP)
94
Q

The __________ produced by the Estimate Costs (7.2) process are used to create the cost baseline in the
Determine Budget process.

Planning • Cost Management • Determine Budget

A

Cost estimates

95
Q

The Determine Budget process creates the project’s budget and baseline by _______ the cost
estimates into a time-phased view.

Planning • Cost Management • Determine Budget

A

Aggregating

96
Q

The project budget and cost baseline are different.
True or False:

Planning • Cost Management • Determine Budget

A

True
The project budget includes the
management reserve; the cost
baseline does not.

97
Q

Which type of reserve accounts for
identified risks?

Planning • Cost Management • Determine Budget

A
The contingency reserve
accounts for identified
risks. In comparison, the
management reserve accounts
for unplanned work.
98
Q

Quality planning should be
performed in ___________ with
other planning processes.

Planning • Quality Management • Plan Quality Management

A

Parallel
The realities of meeting quality
standards may impact cost and
schedule plans.

99
Q

The cost of preventing mistakes
is ____________ than the cost
of correcting mistakes found by
inspection or use.

Planning • Quality Management • Plan Quality Management

100
Q

The __________ describes the
activities and resources necessary
for the project team to achieve the
project’s quality objectives.

Planning • Quality Management • Plan Quality Management

A

Quality management plan

The quality management plan
also defines procedures for
addressing nonconformance,
corrective actions, and
continuous improvement.
101
Q
Quality metrics defined in the
Plan Quality Management process
are used in later processes to
determine the overall quality
status and communicate status
to stakeholders.
True or False:

Planning • Quality Management • Plan Quality Management

A

True
Quality metrics describe a product attribute and how the
Control Quality process will verify compliance to it.

102
Q

What two components comprise the
cost of quality?

Planning • Quality Management • Plan Quality Management

A

Cost of conformance and

cost of nonconformance

103
Q

The cost of conformance includes what two types of costs?

Planning • Quality Management • Plan Quality Management

A

Prevention and appraisal costs

Prevention costs are those associated
with building quality into a product
(training, equipment, etc).

Appraisal costs are those associated
with assessing the quality (testing,
destructive testing loss, inspection).

104
Q

The cost of quality (COQ) only considers the cost incurred while completing the project’s physical work.
True or False:

Planning • Quality Management • Plan Quality Management

A

False
The cost of quality includes all
quality-related costs over the
entire life of the project

105
Q

What is the difference between the project charter and team charter?

Planning • Resource Management • Plan Resource Management

A

The project charter is the
foundational document that
authorizes the existence of
the project.

The team charter defines the team’s agreed-upon
operating guidelines.

106
Q

What is the purpose of the resource management
processes?

Planning • Resource Management • Plan Resource Management

A

The resource management processes ensure that sufficient resources are available at the right place and right time to complete the project work.

107
Q
Which chart type is commonly used
in the Plan Resource Management
process to clarify and define the roles
and responsibilities of each team
member?

Planning • Resource Management • Plan Resource Management

A
RACI chart
The responsibility assignment
chart (RACI) clarifies the
roles of each team member
(Responsible, Accountable,
Consult, Inform).
108
Q
Working directly with the Estimate
Costs process, the
\_\_\_\_\_\_\_\_ process approximates the total
physical and human resources needs
of the project.

Planning • Resource Management • Est. Activity Resources

A

Estimate Activity

Resources

109
Q
What is the primary output of the
Estimate Activity Resources process
that defines what is needed to
complete every work package and
activity defined on the WBS?

Planning • Resource Management • Est. Activity Resources

A

Resource

requirements

110
Q

The _________ organizes the resource estimates into a
hierarchical chart that can be used to help acquire and monitor resources.

Planning • Resource Management • Est. Activity Resources

A

Resource breakdown structure

111
Q

In which resource estimating technique are similar activities from previous projects used to
estimate resource needs?

Planning • Resource Management • Est. Activity Resources

A

Analogous

estimating

112
Q

When lower-level components are “rolled up” to create an estimate of the higher-level activities, what estimating activity is being leveraged?

Planning • Resource Management • Est. Activity Resources

A

Bottom-up

estimating

113
Q

Throughout the Resource Estimating process, various options must be evaluated to determine the optimal
resource solution given the project’s constraints. Which data analysis technique does this describe?

Planning • Resource Management • Est. Activity Resources

A

Alternative

analysis

114
Q

Which two documents must be
updated to reflect the planned
communications activities?

Planning • Communications Mgmt. • Plan Communications Mgmt.

A

Project schedule and stakeholder register

115
Q

How are the stakeholder register
and requirements documentation
leveraged in the creation of the
communications management plan?

Planning • Communications Mgmt. • Plan Communications Mgmt.

A
Stakeholder communication
needs were determined
during the development of
the stakeholder register and
requirements documentation.

The communications
management plan creates
strategies to address each need

116
Q

Define the steps in a basic
sender-reciever communications
model.

Planning • Communications Mgmt. • Plan Communications Mgmt.

A

Encode, transmit,
decode

Encode = Message put in text/sound
for transmission

Transmit = Message sent via
communication channel

Decode = Data translated by
reciever into a usable form

117
Q

Name the three most common
communication methods.

Planning • Communications Mgmt. • Plan Communications Mgmt.

A

Interactive, push, pull

Interactive = Multidirectional
communication

Push = Sent to specific recipients,
but no confirmation that the
information is understood

Pull = Allows content access at the
user’s own discretion

118
Q

____________ is anything
compromising the understanding of
a communicated message.

Planning • Communications Mgmt. • Plan Communications Mgmt.

A

Noise
Noise can be caused by a receiver
being distracted or lacking adequate
perception and/or knowledge.

119
Q

What is the equation for calculating
communication channels?

Planning • Communications Mgmt. • Plan Communications Mgmt.

A

Communication channels
= N x (N - 1) / 2

N = number of
stakeholders

120
Q
By posting project updates at
regularly scheduled intervals on
a corporate intranet page that is
accessible to all stakeholders, a
project team is using which method
of communications?

Planning • Communications Mgmt. • Plan Communications Mgmt.

A
Pull
Pull communications allow
content access at the user’s
own discretion. This is ideal
when communicating with
large audiences or transmitting
complicated information.
121
Q

One-on-one meetings are an example
of which type of communication
method?

Planning • Communications Mgmt. • Plan Communications Mgmt.

A
Interactive
Interactive communication
involves multi-directional
communication between two or
more parties.
122
Q
List the following processes in the order in
which they should be completed:
• Plan Risk Management
• Plan Risk Responses
• Perform Qualitative Risk Analysis
• Identify Risks
• Perform Quantitative Risk Analysis

Planning • Risk Management • Plan Risk Management

A
The risk management processes
in the Planning Process Group are
completed as follows:
1) Plan Risk Management
2) Identify Risks
3) Perform Qualitative Risk
Analysis
4) Perform Quantitative Risk
Analysis
5) Plan Risk Responses
123
Q

Which type of risk describes an
uncertain event or condition?

Planning • Risk Management • Plan Risk Management

A

Individual risk

124
Q

Which type of risk describes the
total resulting effect of all risks
on a project?

Planning • Risk Management • Plan Risk Management

A

Overall risk

125
Q
The Plan Risk Management
process is focused on developing
processes for identifying and
analyzing risks and what other
key risk activities?

Planning • Risk Management • Plan Risk Management

A

Developing and implementing
risk responses

In conducting the Plan Risk Responses
process, the project team is focused on
defining how risks will be both identified
and managed to increase the chance of
project success. 
It is key that the team
develop processes for developing and
implementing risk responses to mitigate/
avoid negative risks and exploit/enhance
positive opportunities.
126
Q

Which document is created during
the Identify Risks process to
record specific details on every
individual project risk?

Planning • Risk Management • Identify Risks

A

Risk register
The risk register is a key output of
the Identify Risk process.

127
Q

What are the two key outputs of
the Identify Risks process?

Planning • Risk Management • Identify Risks

A

Risk register and

risk report

128
Q

Once created, the risk register and
risk report are not adjusted.
True or False (and Why?):

Planning • Risk Management • Identify Risks

A
False
The risk register and risk report
are continually adjusted to
deepen the understanding of the
current risk profile and to include
additional risks identified.
129
Q
Which document often used in the
Identify Risks process leverages a
predetermined list of risk categories
that serve as a framework and starting
point for identifying, describing, and
planning for project risks?

Planning • Risk Management • Identify Risks

A

Prompt list

130
Q

What factors are used to evaluate each risk on the risk register during the Qualitative Risk Analysis
process?

Planning • Risk Management • Perform Qual. Risk Analysis

A

probability of occurrence and impact

Qualitative risk analysis is
subjective, as it based on
perception of each risk’s
probability of occurrence
and impact.
131
Q
Which process determines the
aggregate effect of a project’s
individual risks using the prioritized
list of risks created as an output
of the Perform Qualitative Risk
Analysis process?

Planning • Risk Management • Perform Qual. Risk Analysis
Planning • Risk Management • Perform Qual. Risk Analysis

A

Quantitative Risk

Analysis process

132
Q

What type of matrix is used to rank
each individual risk by two factors
(probability, impact)?

Planning • Risk Management • Perform Qual. Risk Analysis

A

Probability-impact

matrix

133
Q

An S-curve is produced by which
type of risk analysis?

Planning • Risk Management • Perform Quant. Risk Analysis

A
Monte Carlo
analysis
The S-curve from a Monte Carlo
risk analysis visually shows
the probability of achieving any
project outcome.
134
Q

What is purpose of a tornado
diagram?

Planning • Risk Management • Perform Quant. Risk Analysis

A

determines which individual risk has the greatest
impact by correlating different project outcomes to individual risks.

The tornado diagram (used in 11.4 Perform Quantitative Risk
Analysis)

135
Q

Which analysis method is used to
select the best of several alternative
courses of action?

Planning • Risk Management • Perform Quant. Risk Analysis

A
Decision tree analysis
Decision tree analysis is a
mathematical method in which
alternate decision paths are shown and
evaluated for their overall expected
monetary value. The net path value is
calculated for each and the decision
path with the best value is selected.
136
Q

What is the term for the strategies
developed to address risks
with highest impact overall and
individual risks?

Planning • Risk Management • Plan Risk Responses

A

Risk responses

137
Q

_________ are fallback plans
developed for use if and when the
selected risk response strategies
don’t work.

Planning • Risk Management • Plan Risk Responses

A

Contingency plans

138
Q
What are the two data analysis
methods used to evaluate and
select the preferred risk response
strategies the during Plan Risk
Responses process?

Planning • Risk Management • Plan Risk Responses

A

Alternative analysis and

cost-benefit analysis

139
Q
Which of the following is not a
desired characteristic of a proper
risk response plan?
A) Appropriate
B) Cost-effective
C) Timely
D) Realistic

Planning • Risk Management • Plan Risk Responses

A

Timely
Risk response plans should be
appropriate, cost-effective,
and realistic.

140
Q

What are the five alternative risk strategies that
must be considered when planning for threats?
A) Escalate, avoid, transfer, mitigate, accept
B) Escalate, avoid, expedite, mitigate, accept
C) Escalate, exploit, share, enhance, accept
D) Escalate, exploit, transfer, enhance, accept

Planning • Risk Management • Plan Risk Responses

A

A) Escalate, avoid,
transfer, mitigate,
accept

141
Q
Which strategy for addressing
risk threats involves shifting
ownership of the threat to a third
party so that it bears the impact if
the threat occurs?

Planning • Risk Management • Plan Risk Responses

142
Q
Which output produced in the Plan
Procurements Management process
defines the procurement need in
detail sufficient to allow the sellers
to assess if they are capable of
providing the work?

Planning • Procurement Mgmt. • Plan Procurement Mgmt.

A

Procurement

statement of work

143
Q

Which type of contract is used
when the scope of work is
expected to change significantly
during the project?

Planning • Procurement Mgmt. • Plan Procurement Mgmt.

A

Cost-reimbursable contract

The seller is reimbursed for all
allowable costs (per contract).
144
Q

Which documents produced as
outputs of the Plan Procurement
Management process must not be
provided to the potential sellers?

Planning • Procurement Mgmt. • Plan Procurement Mgmt.

A

Source selection criteria and
independent cost estimates

Source selection criteria provide an
objective means to evaluate each
proposal in order to select the seller
offering the greatest overall value.
Independent cost estimates provide a
frame of reference for evaluating bids
submitted. These documents are for
internal project team use only!
145
Q
Which plan documents the
specific actions and strategies
used to deliver the desired level
of stakeholder engagement and
what process creates it?

Planning • Stakeholder Management • Plan Stakeholder Engagement

A

Stakeholder management
plan, which is created as an
output of the Plan Stakeholder
Engagement process

146
Q

The stakeholder engagement
matrix is used to visually compare
which two levels of stakeholder
engagement?

Planning • Stakeholder Management • Plan Stakeholder Engagement

A

Current vs. desired

engagement

147
Q
Which document created by the
Identify Stakeholder process is a
key input to the Plan Stakeholder
Management process, helping
to provide detailed stakeholder
information?

Planning • Stakeholder Management • Plan Stakeholder Engagement

A

Stakeholder

register