CLOSING - 7% slide 770 Flashcards

1
Q

Define the key objectives of the
Close Project or Phase process.
Closing • Integration Mgmt. • Close Project or Phase

A

Finalize all activities of the
project, phase, or contract

–Archive all project or phase
information

–Formally close the project, phase,
or contract

–Release all organization team
resources

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Describe why the Close Project
or Phase process is an ideal
integration management process.
Closing • Integration Mgmt. • Close Project or Phase

A
The Close Project process is
ideally an integration management
process in that it consolidates the
planned work and all documents
and translates them into a final
form that satisfies the customer
and records information for
further learning.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

In executing the Close Project process, you have
created a final project report, transferred the final
product to the ownership of the customer, and
dismissed your project team. You believe that you
can now formally close the project. What activity
have you forgotten to complete?

A) Obtain approval from the project sponsor
B) Formally acknowledge the success of the team
C) Complete and archive the lessons learned
register and all project documents
D) Close the charter document

Closing • Integration Mgmt. • Close Project or Phase

A

C) Complete and archive the
lessons learned register and all
project documents

To fully complete the Close Project or
Phase process, you must ensure that
all project documents are updated,
marked as final, and archived.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q
Which term is used to describe
project deliverables after they have
been inspected and approved by
the customer as having met the
acceptance criteria?

Closing • Integration Mgmt. • Close Project or Phase

A

Accepted deliverable

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q
In closing the project, the project
manager reviews the \_\_\_\_\_\_\_\_\_
to ensure that all project work is
complete and the project has met
its objectives. 

Closing • Integration Mgmt. • Close Project or Phase

A

Project management plans

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q
Projects that are terminated
before all the work is
completed do not require the
Close Project process.
True or False:
Closing • Integration Mgmt. • Close Project or Phase
A
False
Every project, whether completed
or prematurely terminated, must
be formally closed. For projects
terminated before completion,
the close project or phase process
investigates and documents the
reasons for termination.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q
While developing the final report
for formal project closure, you
utilize which project document to
demonstrate compliance with the
project scope?

Closing • Integration Mgmt. • Close Project or Phase

A

Requirements documentation

The requirements documentation
created during the Collect
Requirements process describes how
individual requirements meet the
business need for the project.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Due to a company reorganization, the project sponsor was recently terminated and the project was canceled. What action should the project manager take first upon
being informed of this?

Closing • Integration Mgmt. • Close Project or Phase

A

Conduct lessons learned

Regardless of whether a project is completed fully or terminated before completion, lessons learned
must be captured and recorded. These lessons learned help to inform future projects.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

The Close Project or Phase process
is ________ the finalization of all processes and process groups.

Closing • Integration Mgmt. • Close Project or Phase

A
Formal finalization
The Close Project or Phase
process is the formal finalization
of all processes and process
groups.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Which three outputs must be
completed before a project is
properly closed?
Closing • Integration Mgmt. • Close Project or Phase

A
-- Final product, service, or
results officially transferred
to the customer
-- Project documents updated
and marked as final
-- Final report created
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q
The Close Project process is where
the final product is actually handed
over to the customer. In which
process did the customer approve
the project deliverable?
Closing • Integration Mgmt. • Close Project or Phase
A

Validate Scope
The customer formally approves
the project deliverables in the
Validate Scope process.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Of the four data analysis techniques used
in the Close Project or Phase process, which
technique is focused on identifying lessons
learned and knowledge sharing opportunities
to help improve future projects?
A) Document analysis
B) Regression analysis
C) Trend analysis
D) Variance analysis
Closing • Integration Mgmt. • Close Project or Phase

A
A) Document
analysis
Document analysis is
a technique that helps
identify lessons learned for
future projects.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q
When using , \_\_\_\_\_\_the
interrelationships between project
variables are analyzed to identify
opportunities to improve the
performance of future projects.
Closing • Integration Mgmt. • Close Project or Phase
A

Regression analysis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

You inform your team that a critical output of the Close
Project process is the completion and archival of the lessons learned register. What is the main reason why ensuring that the register is updated and archived important?

A) To create a means of identifying talented individuals that
can assist in future projects
B) To identify and make easily available improvement ideas
that can be used on comparable projects
C) The project cannot be formally closed until every output
is produced
D) To highlight the largest risks and opportunities that were
overcome during the project
Closing • Integration Mgmt. • Close Project or Phase

A

B) To identify and make easily available improvement ideas that can be used on comparable projects

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q
After all project work is complete,
it is proper to release all team
members.
True or False:
Closing • Integration Mgmt. • Close Project or Phase
A
False
Team members should only be released
from a project after all the work is verified
complete, project documents have been
fully evaluated/closed out/archived,
lessons learned collected/archived, the
final report generated, and the final
deliverable transferred to the customer.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is the purpose of the final
report and what does it contain?
Closing • Integration Mgmt. • Close Project or Phase

A

The final report summarizes the project performance elements such
as benefit, cost, quality, schedule, etc.

The project manager should follow the communications plan
to ensure proper dissemination is achieved.

The final report is normally delivered to the project sponsor and
all stakeholders.

17
Q

During the Close Project process, your team is investigating the project’s current risk status and
attempting to identify if there are any open risks remaining. Which project document should the team leverage to investigate these questions?
Closing • Integration Mgmt. • Close Project or Phase

A
Risk report
The risk report provides
information on the risk status
and is used to check that there
aren’t any open risks at the end
of a project.
18
Q

The Close Project process uses which of the
following tools and techniques to evaluate
that the closure activities are completed to
the appropriate levels?
A) Project management information
system
B) Expert judgement
C) Product analysis
D) Inspection
Closing • Integration Mgmt. • Close Project or Phase

A
B) Expert judgement
Expert judgement is applied
when performing administrative
closure activities. These experts
ensure that the project or phase
is performed to the appropriate
standards.
19
Q

Which two logs should be analyzed
prior to closing the project?
Closing • Integration Mgmt. • Close Project or Phase

A
Issue log and change log
The issue log should be evaluated to
determine if any issues remain that
may impact the success of final product
transferred. 
In analyzing the change log,
the team must confirm that all outstanding
change requests are fully implemented
before closing the project.
20
Q

Which of the following is not an objective of the
Close Project or Phase process?
A) Transfer the finished deliverable to the
customer
B) Obtain customer approval of the project
deliverables
C) Obtain verification from the customer
that they accept the project deliverables
D) Update and archive all project documents
and OPAs
Closing • Integration Mgmt. • Close Project or Phase

A
B) Obtain customer
approval of the project
deliverables
Customer approval is obtained
during the Validate Scope process.