PgMP Test Questions Flashcards

https://www.simplilearn.com/pmi-pgmp-exam-prep-free-practice-test

1
Q
  1. A program comprises of 10 projects. As the projects are performing the Validate Scope process, what should be the focus of the program manager?

a. Create a high level work breakdown structure for the program (PWBS)

b. Manage by exception and handle the change requests coming out of this process through the program level change management processes

c. Verify that the project deliverables will help deliver the intended benefits

d. Ensure that the projects are following the appropriate test procedures and strategies Score

A

Answer: c) The program manager needs to integrate the project deliverables in order to deliver the benefits to the organization.

Validate scope at the project level refers to the final acceptance tests for the projects. Here, the program manager needs to make sure that the** deliverables enable the program to deliver the intended benefits.**

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q
  1. An engineering company is working on a program for a client that is spread across 6 countries and 12 sites. Each site is considered a project and the program manager also manages the client relationship and the finances. Which of the following is the most important risk for the program manager?

a. The tax regime in one of the countries is volatile and may have implications for a project in the program.

b. The program earns revenues in dollars and spends in 6 different currencies, hence exchange rate fluctuations is a risk.

c. One of the sites is fairly remote and this causes transportation costs to go up.

e. Though the client representative is quite friendly, she is known to be a tough task master and will not tolerate delays in completion.

A

Answer: b) This question is essentially trying to get the participant to prioritize the risks. Remember we are talking about the program manager’s view point.

A and C are valid risks, but probably will be managed by the respective project managers.

B and D are both program level risks. D says the client is particular about dates (all clients are!), whereas B talks about a currency fluctuation risk and seems to be higher priority.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q
  1. A program consists of 10 projects, each headed by a project manager. Who should be responsible for the identification of risks on the program?

a. The program manager

b. The program managers and the project managers

c. The program team

d. All the stakeholders of the program

A

Answer: d) The risk identification process ideally should involve everybody associated with a program. Hence choose the broadest possible answer, which in this case is D.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q
  1. A program has several projects that rely on the services of a vendor for delivery of critical parts. The parts are pretty standardized and usually procured under firm fixed price contracts. During a particular year, the supplier asks for renegotiating the prices because the dramatic increase in input costs has made the supply of parts unviable. What should you do as a program manager?

a. Forward the request to the procurement team and let them handle this as per their normal procedures

b. Agree to the request only in the cases of projects which have a positive cost variance and can accommodate an increase

c. Refuse the request as the supplier bears the cost risk in a fixed price contract

d. Agree for the negotiation taking the project managers and the procurement team into confidence

A

Answer: d) Though it is true that the supplier bears cost risk in case of fixed price contracts, the** buyer needs to be considerate in case of events that go beyond the control of the supplier**.

The contract is good only if it helps both seller and buyer to realize value from it. When the seller loses money on a contract, their commitment to deliver will go down, which would be a major impact for the program. So, it is only reasonable that renegotiations are entered into.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q
  1. A program manager wants to initiate a new component that will help improve the efficiency of the existing components. One of the members of the program board disputes the reasons for the new component and feels the results can be achieved without a new component. The program board is split equally in the two camps. What is the best way to arrive at a decision?

a. The program sponsor should decide

b. There should be a vote and the majority decision should be respected

c. The discussions should continue until a consensus is reached

d. The request should be turned down as there is not enough support behind the component

A

Answer: a) This is clearly a program board decision, but the board seems to be split in the two camps. Under the circumstances, the best way to proceed would be for the program sponsor to take a decision. The governance board is not a consensus committee, but the program sponsor normally has veto powers.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q
  1. The World Bank is evaluating whether or not to fund a mass transportation improvement program in a major city. Since the funding is for a social benefit, the first ask is to conduct a benefits analysis and identify benefits. Which is the best description of what will take place during benefits identification?

a.Create and prioritize projects and establish benefits metrics

b. Determine benefits, evaluate benefits, and setting up metrics to measure benefits

c. Monitor projects, maintain benefits register, and create benefits reporting

d. Create benefits monitoring and the benefits realization plan and align benefits into the program management plan

A

Answer: b) The activities and deliverables of benefits identification are determine benefits, evaluate benefits, and set up mechanisms to measure benefits.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q
  1. Project A and Project B are part of a program. Project B depends upon the output of project A. From the project perspective, this is an example of:

Internal dependency

External dependency

Mandatory dependency

Finish-to-Start dependency

A

Answer: b) For project B, the dependency is on another project, hence from a project perspective, it is an external dependency. There is not enough information to say if it is mandatory or finish-to-start.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q
  1. The program scope statement has been finalized, the distribution of work among various components has been determined and the program WBS has been created. The program manager asks the project managers to create a work breakdown structure. The project managers are having difficulty understanding what purpose the project level WBS will serve over and above the PWBS. Which statement best explains the need for a project level WBS?

a. To be able to determine which parts of the program’s work should be done in-house and which parts can be outsourced.

b. To gain a better understanding of the dependencies among the work of different projects and to sequence the activities accordingly.

c. To better organize the work of the projects into smaller, more manageable units that the project manager can keep a track of.

d. To be able to meet compliance requirements to the relevant standards in project and program management.

A

Answer: c) The reason to develop a WBS is to basically break the work down into smaller deliverables that can be better managed by the project managers.

All other answers have some inaccuracies. For example, WBS does not involve make or buy analysis or determine sequencing. The WBS is a tool that benefits better management, not necessarily to satisfy some compliance requirements scope.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q
  1. Company A is performing due diligence and is in talks to acquire Company B. One of the agenda items is to understand the ongoing programs from Company B and getting an understanding about likely cash inflows and outflows on the programs in the coming years. Where is this information most likely to be found?

a. Program management plans and benefits realization plans of ongoing programs in Company B

b. The portfolio and strategic management plans for Company B

c. The financial management and benefit realization plans of the ongoing programs

d. The business case and program charters of ongoing programs

A

Answer: c) The program financial management plan documents funding schedules, initial budgets, contract payments and financial metrics.

The benefits register provides the list of planned benefits and target dates and milestones for benefits achievement.

Together, these documents can provide the information necessary for due diligence.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q
  1. A program manager is a big believer in the value of industry academia partnership. She would like the projects to establish an internship program and perform some research work with university support. The project managers have not been forthcoming on this front, as they believe their work is business critical and cannot rely on academic alliances. What is the best way for the program manager to proceed?

a. Establish a policy that 10% of the project’s staff should be student interns

b. Call for a meeting with the project managers and impress upon them the value of the partnership

c. Find a component that is willing to pilot this concept and start small

d. Call the dean of the local university to make a presentation so that the project managers can be convinced

A

Answer: c) This concept cannot be pushed by diktat (Option A) or rhetorical speeches (Option B). Calling the university to pitch this concept may not be advisable until the apprehensions of the project managers have been allayed (Option D). Option C seems to be a reasonable option. Start a small pilot and build on it.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q
  1. How exactly can a program manager ensure that the benefits from a program are indeed being realized?

By dividing responsibilities between the program team members

By planning specific activities for benefits realization, then monitoring and tracking benefits delivery

By creating a benefits realization plan

By setting appropriate performance objectives for the project managers around benefits realization

A

Answer: b) Merely creating benefits realization plan does not help in realizing the benefits, nor does assignment of responsibility or assigning performance objectives. The program manager needs to plan specific activities for benefits realization.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q
  1. A program manager who is being appointed to a new program is insisting that the program charter be issued. Which of the following is the MOST important purpose of the program charter?

It lays down the initial set of requirements and intended benefits

It defines the structure of the program and the related components

It formally authorizes a program and secures senior management buy in to apply organizational resources to it

It provides the business case for the program

A

Answer: c) The main reason for a charter is that through a charter, the senior management of the organization formally brings a program into existence and agrees to commit organizational resources to it.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q
  1. A retail store is expanding in a new country and is looking for an IT supplier to provide PoS equipment, networking, computers, and application maintenance services for its stores. An RFP has been floated. How should the prospective sellers respond to the RFP?

a. They should establish their capability of meeting the requirements specified in the RFP and accordingly supply a quote for the work involved

b. They should work on feasibility, followed by detailed estimation and then send a detailed proposal after looking at the requirements

c. The feasibility has to be established from a financial, technical and capabilities view point and the commercial viability of the proposal has to be established before filling in the bid documents

d. They should understand the decision criteria and the people who will be making the decision and see how best they can be influenced to win the contract

A

Answer: b) The response to an RFP has to be a detailed proposal.

Not just a quote or a bid.

Trying to influence the decision makers before the decision is not in keeping with professional responsibility.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q
  1. Which of the following areas should NOT be the focus of the program management domain?

Managing interfaces between the components

Managing transition of components and the overall program

Aligning the program with strategy

Ensuring strategic decisions are taken in accordance with legal frameworks

A

Answer: d) The program manager is expected to ensure A, B, and C but not D. Strategic decision making typically happens at a level above the program manager and the program manager is not competent to vouch for the legal validity of the decisions.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q
  1. A construction program frequently needs diesel generation sets for construction activity in a remote site where electricity supply has not yet arrived. The program policy is to rent the generator sets rather than buy them. A project manager made a request to buy a generator for his project, because he would like to have greater control over the availability, specifications and conditions of use. The other projects are perfectly happy with the renting arrangement. What should you do as a program manager?

Refuse the request and explain the rationale behind the rent vs. buy policy

Discuss the requirements of the project manager with the supplier from whom the sets are rented and try to work out a solution

Agree to the request of the project manager after making an exception

Change the policy of buy vs. rent for the entire program rather than only one project

A

Answer: b) The reason for the project manager’s dissatisfaction has to be understood and discussed with the supplier before making the call. There may be reasons behind the policy being what it is and it should not be changed lightheartedly. Nor should the request be denied out of hand without establishing the need and trying to address it.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Fix

Answer: b) The work is known to be technically complex and the scope of work is unstable. Therefore fixed price contract cannot be used. Among options A, B, and C which all recommend cost reimbursable contracts, option B is best because it would provide an incentive to the vendor.

A

Answer: b) The Ishikawa diagram is useful for isolating the area or areas that could be causing the problem. Identifying the root cause is the first and important step in finding a remedy. The Pareto diagram is useful for determining the priorities between possible underlying causes. The flowchart is a diagram that displays the connectivity between pieces of a system. The control or run chart is useful for determining the measured output over the manufacturing process for acceptable and failed products.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q
  1. What is the ideal role for the Program management in the change management process?

To control unnecessary changes

To act as a process police, ensuring that the process is followed at all times

To expedite the routing of the change requests to the program board

To delay changes as far as possible so that the program can stay on track with plans

A

Answer: a) Preventing unnecessary changes is the best service that the program manager can provide to a program with regard to change management. They are uniquely positioned to do this because they have a view of the organization’s expectations about benefits and the correlation of the activities to achieving the benefits.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q
  1. A company working in the pharmaceutical industry has been acquired by another company. The new owners are reviewing the existing programs and taking a decision whether they fit into their strategy or not. Which of the following will be LEAST useful while making the decision about strategic alignment?

Business Case

SWOT analysis

Governance plan

Benefits realization plan

A

Answer: c) The governance plan is about how the program will be administered and governed, and does not really address the strategic alignment.

The business case gives an idea about the high level goals of the program.

SWOT analysis gives the positioning of the program with regard to its environment

and the benefits realization plan outlines the benefits and the plan to realize them.

Except for the governance plan, all others are useful for determining alignment with strategy.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q
  1. Three projects which were part of a program are complete. The deliverables have been validated and accepted by the customer. While a final review before transition was in progress, the manager of the operational unit responsible for supporting the deliverables has expressed concern that his staff has not been trained in the support procedures. What should the program manager do?

Withhold the transition until the operations have been adequately enabled.

Set up a training plan and identify resources for the training before approving the transition.

Ask the customers if they are willing to accept a drop in service quality while the training is completed.

Ask the project managers why the training was not completed and log in the lessons learned.

A

Answer: a) The transition plan needs to be executed (not just planned as in option B) before the transition can be completed.

Without adequate enablement of the operations staff, there is no point in approving the transition.

Asking customers to put up with a lower quality of services exposes the lack of maturity in the program’s processes.

Analyzing the reasons for the training not being completed is necessary but would not be the first thing on the program manager’s mind at this point.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q
  1. Which of the following will NOT feature as subsidiary plan(s) of the program management plan?

Benefits management plan

Governance plan

Stakeholder engagement plan

Project management plans

A

Answer: d) The program management plan is a high level plan that outlines how the overall program will be management. It provides guidance and direction to individual project management plans but does not necessarily contain all the project management plans as subsidiaries.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q
  1. A project manager is selecting a vendor for a complex piece of work on her project, for the project does not have in-house technical expertise. Which of the following vendors should the program manager recommend?

Vendor A, which is the preferred vendor for the program at large

Vendor B, which has quoted the lowest price

Vendor C which has the most experience in the technology

Vendor D, which has the best reputation for after sales service

A

Answer: c) The selection of the vendor should be based on the reasons for outsourcing. Here, the reason is absence of in-house technical competency. Therefore (in absence of any other information), Vendor C, which seems to be the best choice

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q
  1. A project is part of a program. The project manager has used different techniques to identify and analyze risks and plan responses. She has further provided for contingency reserves. However, she tells the program manager that her gut feel suggests there are probably more risks that could arise during the project execution. What would be your advice while finalizing the plan?

To have a set of workarounds ready in case some unidentified risk occurs.

Tell the project manager not to worry because the program level contingency reserves can be utilized for these.

Set aside some management reserves to be used in case an unknown risk event occurs.

Tell the project manager not to worry too much; if an unknown risk occurs it is always possible to raise a change request to cover for the impact.

A

Answer: c) The program manager must advocate a proactive approach towards risk management. C is the best choice because it recognizes the existence of some risks which may not have been identified upfront and provides for it. Workaround by definition is an unplanned response, so it cannot be decided in advance. The program level contingency reserves should be used for program level risks, not to cover unknown unknowns at project level.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q
  1. A manufacturer of luxury automobiles is keen on entering into a new market, which seems to have a lot of potential. What should be the first step for the company on this venture?

Establish a joint venture with a local automobile company which has a better understanding of the local market and local regulations.

Prepare a business case to understand the implications of this venture for the overall organization.

Undertake a detailed market study to figure out the demand for luxury automobiles in the target market.

Issue a program charter and appoint a program manager who is a resident of the target market region and an expert in the automobile industry.

A

Answer: b) The first step should be to prepare a business case and come up with a business justification.

The market study may be a part of the business case preparation activity, but not necessarily so.

If there is already data available about the target market, then the market research may not be required.

Also, establishment of a joint venture may or may not be desirable and seems a bit presumptive, when the program is still in the evaluation stage.

For similar reason, issuance of a program charter is a little premature. The business justification needs to be created first.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q
  1. Project A and Project B are part of a program. Project B depends upon the output of Project A’s deliverable and has been delayed. What should the program manager do?

Work with the manager of project A to complete the deliverable as soon as possible

Work with the manager of project B to mitigate the impact of the delay to the extent possible

Analyze the impact of the delay on the ability of the program to deliver the benefits

Understand the impact of the delay on the overall program schedule

A

Answer: c) The program manager should focus on the benefits that are expected from the program rather than on individual projects or specific aspects of the Scope, Cost, and Time equation for the program.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q
  1. A project manager is outsourcing a complex piece of work on her project, as the project does not have in-house technical expertise. As a result of this change, the program had to shell out additional funds. Further, the program and project now needs to worry about the reliability of the vendor. This is an example of:

Residual risk

Secondary risk

Peripheral risk

unknown unknown

A

Answer: b) Secondary risks arise from the response plans employed to address an existing risk.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q
  1. A program is initiated to reduce the energy needs of a chemicals refinery. One of the measures is to adopt renewable resources for preheating which reduce the overall energy needs. However, this will lead to increase in the operational costs. How should the program manager handle this?

Go ahead with this change as it is in line with the program benefits

Since it impacts operations, get their buy in before submitting the change request

Submit the change request to the program board for approval

Reject this change as the program manager cannot unilaterally bring in a change that increases operational cost

A

Answer: b) This change is definitely valid because it is in line with the requirements for this program. However, the impact on operations has to be studied and evaluated before going ahead with the change request.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q
  1. A program comprises of 8 projects with complex interlinkages. What is the level of detail expected in the program management plan?

a. The plan should be as detailed as possible to cover all possible scenarios and provide detailed guidance to the program and project team members.

b. The level of detail in the plan should be customized to the degree of granularity that the program manager and program office desire and can effectively handle.

c. The plans should be very high level, leaving all the details in the project management plans.

d. The level of details should be customized based on the guidance received from the program management office.

A

Answer: b) The program manager (not the PMO) should determine how detailed or high level the plan should be. This should be based on the assessment of how much detail the program office can handle and require.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q
  1. An organization is embarking on a change initiative to use six sigma principles on its operations to achieve higher quality. The program is sponsored by a senior executive and the program manager has been appointed. The program manager fears that there would be a lot of passive resistance at lower levels of the organization. Which approach is likely to be most effective in overcoming this?

A communication campaign around the benefits of six sigma and the expected benefits to the organization.

A top down approach where the CEO throws his weight behind the initiative and sets up objectives for all departments.

The program manager meets the stakeholders in smaller settings and tries to convince them about the need for change.

Start with a group that is willing to pilot it and then use the success of the pilot to win support across the organization.

A

Answer: d) Change initiatives that cut across organizational boundaries are likely to create resistance. Of the stated approaches, D seems most likely to succeed, because it will use past data in the same organization to propagate in a wider setting. Hence, start with a group that is willing to pilot it and then use the success of the pilot to win support across the organization.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q
  1. What is the normal order in which the closure processes take place on a program?

Component closure, Program Procurement closure, Program transition and benefits sustainment, Program Financial Closure, Program closure

Program transition and benefits sustainment, Components closure, Program Financial closure, Program Procurement closure, Program Closure",0, ,,,Program Closure

Components Closure, Program Closure, Program transition and benefits sustainment, Program Financial closure, Program Procurements closure

A

Explanations:Answer: a) It makes sense that the components of the program must close first. The program procurements must be closed, which may have an impact on the transitions and finances. The program will close only when all of these processes are completed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q
  1. A music company based in the UK is launching a new album with a new upcoming artist who has recently won a popular reality show on television. The album is expected to be a big hit and all the reviews have been excellent. The company now learns that one of the songs in the album may have been copied from a song popular in Korea What risk response strategy should the program manager use in this case?

Risk Avoidance

Risk Acceptance

Risk Mitigation

Risk Transference

A

Answer: a) This is a professional responsibility question. This risk should be avoided at all costs.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q
  1. A program has been initiated by a telecom company to launch 4G telecom services. There are multiple components to this program with complex interlinkages. The program manager is working on preparing the Program Work Breakdown Structure. A newly joined program coordinator who is assisting with the data collection is confused. What can you tell him about the contents of the PWBS?

Work packages contained within all the components of the program

Key activities and milestones within the program

The breakup of the program deliverables into smaller units

A detailed description of all the program packages which are in scope

A

Answer: c) The PWBS is “deliverables based”, which rules out option B.

It does not contain all the work packages it only goes up to a level of granularity that the program manager wants to manage at.

The PWBS does not contain the description of the program packages.

It merely breaks up the program deliverables into smaller, more manageable units.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
32
Q
  1. Project A has a budget of $400K and is 100% complete, Project B has a budget of $150K and is 90% complete, Project C is worth $400K and is 75% complete. What is the earned value for the overall program?

$835K

$900K

$850K

$990K

A

Answer: a) The earned value is the budgeted value of the work complete and can be computed as: 400 * 1 + 150 *0.9 + 400 * 0.75 = $835K

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
33
Q
  1. A consumer electronics company is looking forward to launch a new version of an electrical shaver. What is the best way for it to get clear requirements?

Questionnaires sent to existing customers

Interviews with customers who do not currently use electric shavers

Experts in the personal goods industry

Observations and historical records of feedback from customers

A

Answer: d) In this case it is hard for a customer to articulate or verbalize requirements; hence the team needs to figure out the requirements based on past customer feedback and by observing and experimenting.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
34
Q
  1. A program manager is reviewing the business case for a few projects which have been suggested for funding in the forthcoming portfolio cycle. Project A is forecasting a NPV of $15 million; Project B is forecasting a payback period of 26 months; Project C has a benefits cost ratio of 1:1.5; Project D has an IRR of 12% as against a cost of capital of 8%. Which project would you select if you can only invest in one?

Project A - NPV of $15 million

Project B - payback period of 26 months

Project C - BCR 1: 1.5

Project D - IRR 12% vs cost of capital 8%

A

Answer: d)

Option C is not a viable project as BCR < 1.

NPV and IRR are better measures of benefit cost analysis than payback period as they consider the time value of money.

Option D provides more conclusive supporting data because it provides not just a value for the IRR, but also informs that it exceeds the hurdle rate.

Option A Whereas an NPV of $15 million may be good or bad, depends upon the overall return on investment it provides and whether it is an acceptable rate of return.

BCR - Benefit-Cost Ratio
NPV - Net Present Value - calculated in absolute terms
IRR - Internal Rate of Return - uses %

Decision making is easy in NPV but not in IRR

NPV - estimate future cash flows disccounted to present value (discount rate is the cost of captial)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
35
Q
  1. A music company based in the UK is reviewing new artists for its latest album when they come across a new upcoming artist who has recently won a popular reality show on television. The music is of a very high quality and there seems to be tremendous potential to create value for the company, though the artist is relatively junior and not very well known. Which strategy might be most useful in this case?

Enhance

Transfer

Exploit

Share

A

Answer: d) The opportunity exists both for the artist and the company, so the best approach would be to establish a venture to share the opportunity. This would involve the company signing up the junior artist for a specific duration to create music.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
36
Q
  1. A program manager is keen on ensuring a high level of quality. Which of the following policies are most suitable to be imposed from the program level?

The program will follow applicable ISO standards

All projects will follow uniform and standardized acceptance tests for raw materials and project deliverables

The test processes in all projects will be reviewed and approved by the program manager

All projects will have mandatory quality consciousness trainings for all team members

A

Answer: a) The program’s role in quality is to determine policies and standards that can be applicable to multiple components.

The adherence to ISO standards is an example.

Other statements may not be universally applicable and attempts to impose them without considering project level realities may backfire.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
37
Q
  1. Project A and Project B are part of a program. Project B depends upon the output of project A. Work in project B can start about 1 week after Project A has handed over its deliverables. This is an example of:

Lag

Lead

Critical Path

Start to Finish relationship

A

Answer: a) When there is a time gap between two activities, it is an example of a lag.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
38
Q
  1. A program manager and the project managers working on the program are working on the resource management plan. One of the difficulties is to figure out which resources are managed at the program level as opposed to the project level. Which is the best set of guidelines to follow to resolve this issue?

Typically human resources are managed by the projects, whereas other resources are managed by the program.

All resources are owned by the program and merely allocated to the projects as necessary.

Expense thresholds are established and the less expensive resources should be managed by projects and more expensive ones at the program level.

Resources that are shared by multiple projects can be managed at the program level, dedicated resources can be managed by projects.

A

Explanations:Answer: d) Program manager can add value by ensuring optimal utilization, assignment and prioritization of shared resources. This is probably the most logical distribution of responsibilities for resource management in the program.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
39
Q
  1. A textile company is working on introducing a new technology that will reduce the cost of manufacturing which will be done through a program. Which of the following would probably be the first step in the sequence of activities for the program?

Evaluate the risk level on the program to make sure it aligns with the risk threshold

Ensure the strategic alignment of the program

Assign a program manager

Determine the time lines by which the cost reductions can be realized

A

Answer: c) Explanation: A, B, and D are activities that the program manager will work on. The assignment of the program manager should probably be the first logical step.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
40
Q
  1. A program for developing new models of mobile phones in line with market trends is part of an important portfolio within an organization. After the phones are launched in the market, they are maintained and serviced by the customer service department. The program manager makes a case that the maintenance and service for the phones launched through the program should also be an operational part of the program. What is the best justification that the program manager provide for this to the program board?

It will streamline operations and projects and make the management simpler.

Customers can get better services due to the involvement of the development teams.

Knowledge of the customer complaints and feedback will enable development of newer models that are more in tune with the market realities.

This will create a revenue stream for the program which can be deployed in the new model development activity.

A

Answer: c)

A is too generic a statement and will not make any sense to the business.

There is no guarantee that option B will actually occur.

D may be valid, but there is no justification provided about why the program needs additional funds.

C makes most sense to the business owners because it provides a clear indication about how this operation can help the program add more benefits to the organization.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
41
Q
  1. Project A is part of a program for a steel plant. Building a motor assembly is an activity on the critical path for Project A, which ultimately delivers mixing units to the program. The team working on the motor assembly estimates the time required to be 30 days. The manager of project A reckons it should be 20 days, and the program manager thinks it should take no more than 15 days. What can be done to resolve the issue?

Buy the motor assembly from the market

Use the program manager’s estimate and try to crash the schedule

Use the project manager’s estimate and reset expectations at the program level

Use the team’s estimates and try to look for options to reduce the time

A

Answer: d) If the team’s estimate does not meet the elapsed time expectations of the project and program manager, options to crash the schedule can be explored. But mismatch in time expectations cannot on its own be the basis of a procurement decision (Option A). The team’s estimates cannot be replaced with that of the program manager (B) or project manager (C) because the team’s estimates are likely to be more reliable.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
42
Q
  1. In preparing the lessons learned and historical records for a program that was driven by several research projects which would be the most valuable information?

What findings were uncovered and how, what decisions were made and how, new techniques discovered.

Decisions taken, record of changes approved, financial and legal records.

Findings and basis for making conclusions, change requests received and decisions made, final acceptance.

Schedule and cost variances, benefits realized vs. initially planned, final acceptance and change records.

A

Answer: a) A is the most valuable information because it focuses on the research aspects and documents the findings, decisions and new techniques. For such a project, variances, final acceptances and decisions made are probably less important.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
43
Q
  1. What should be the outlook of a program manager about the quality management planning processes?

Quality is the responsibility of the projects and the project managers should get specific goals around quality.

Program level quality planning is to provide guidelines and policies and set up governance frameworks around quality.

Quality is of paramount importance and there should be all out efforts to create a quality conscious culture.

The program must review the cost of quality calculations for all the projects to make sure that the investment in quality enhancements is well targeted.

A

Answer: b) Option A puts the onus on the projects through performance goals. This is a hands-off approach and does not gel with the concept of management ownership of quality. C is a philosophical statement with no real action. D is only partially correct, because although the theory of cost of quality is correct, the program manager cannot review the calculations for every project. The program manager’s efforts are best spent on setting up guidelines, policies, and a governance mechanism.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
44
Q
  1. A program manager has 15 project teams distributed across the globe. What would be least effective in enabling effective communications on the program?

Provide for high travel budget to have more face-to-face communication

Leverage technology such as instant messaging, video conferencing and team wikis

Standardize a reporting format so that the details of all the tasks on all the projects are available to all team members through a weekly report

Cultural sensitivity training for everybody on the program

A

Explanations:Answer: c) A, B, and D are all mechanisms that can be used to enhance and enable communications on a distributed team. C is not a good idea because details of all tasks on all projects would result in information overload and add little value.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
45
Q
  1. Which of the following quality philosophies embraces management ownership for quality?

Kanban

Total Quality Management

Kaizen

Zero Defects

A

Answer: b) Deming’s quality philosophy was Total Quality Management (TQM) which involves being proactive, utilizing accountability and leadership, and continuously improving as a company.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
46
Q
  1. A program consisting of 10 projects is very demanding on resources. In planning for resources what should the program manager be most concerned about?

Making sure that the resources with the right skill set are available at the right time to all the projects.

Policies around compliance, diversity, equal opportunity, etc. are respected while recruiting resources.

Making sure that the resources are under the direct management control of the projects so that their availability can be guaranteed.

Making sure that the existing resources are being utilized optimally across the program management plan.

A

Answer: d) The program manager needs to ensure that the resources are being optimally utilized by the projects, especially given that the program is resource intensive.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
47
Q
  1. A program has a number of projects with a lot of interdependencies. One of the senior technical architects in a project made a change to the specifications of one of the deliverables. The other projects are dependent on the original specifications and now need to rework. Who is responsible to solve this problem?

The program board and program sponsor along with the program manager

The program manager, concerned project managers and technical experts

The program manager and the concerned project managers

The project manager who approved the change to the specifications

A

Explanations:Answer: b) The change is technical in nature, so it needs technical expertise. It also needs the project and program managers to analyze the impact. Therefore B represents the best set of people to solve this problem

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
48
Q
  1. During the project level HR planning, which aspect of the planning process should the program manager pay MOST attention to?

Resource leveling to ensure that there is optimum resource utilization

Recruiting the right set of resources with the correct set of skills

Ensuring that the correct team culture is maintained within all projects in the program

Performance management and effective employee engagement to ensure that employee retention is maximized

A

Answer: a) One of the ways in which program managers provide additional benefits and control is by ensuring that the resources are shared and their utilization across projects is optimized. Especially for the critical resources, this is what the program manager will focus on.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
49
Q
  1. A program manager believes in the Y-Theory and giving maximum autonomy to the team. Most of the project managers believe in the X-Theory and close management. What should be the recommended management style for the program?

The program manager should manage at a high level and the projects should have closer management

The program manager should adapt to the project manager’s style of managing

The project managers should adapt to the program manager’s style of management

It should depend on the needs of the projects and program at any given point in time

A

Answer: d) The management style should be driven by whatever is appropriate at the given moment in time. There is no right or wrong style.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
50
Q
  1. A program manager is discussing with the project managers about the best form of contract to be used with the suppliers to the program. Which of the following is the most accurate statement in this regard?

The advantage of cost reimbursable contracts is that the costs can be kept in check and the seller will be judicious in incurring expenses

The advantage of fixed price contracts is that it locks the two parties into a price and guarantees on time delivery

The risk associated with a time and materials contract is that the seller has too much control over the resources

The risk associated with a fixed price contract is that if the agreed price becomes unremunerative for the sellers, their commitment to the contract may diminish

A

Answer: d) All other statements have some issue. The seller has no incentive to control costs in a CR contract. FP contracts do not guarantee on time delivery. In a T&M contract, the buyer is in control of the resources.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
51
Q
  1. A program manager works in a matrix organization and is leading a cross functional program. The project managers all report into specific functions and have no direct reporting relationship with the program manager. Midway through the program, the VP of the IT function suddenly withdraws all the resources assigned to this program saying it is no longer fitting into his function’s priorities. What should the program manager do?

Escalate the matter to the Program Sponsor and ask for his assistance

Set up a meeting with the VP to explain the importance of the resources to your program

Analyze the impact of the absence of resources on the program

Note this as a risk in the program risk register and come up with a risk response plan

A

Explanations:Answer: a) In a matrix organization, the resources are owned by the functions. The program manager needs to seek senior management intervention to protect the program’s resources by approaching the program sponsor.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
52
Q
  1. A program manager is reviewing the business case for a few projects which have been suggested for funding in the forthcoming portfolio cycle. Apart from establishing financial, market and technological feasibility, what other consideration may be most important for the program manager to evaluate during the chartering process?

Whether the organization has the necessary resources, capabilities, and willingness to work on the project

Whether there is a valid business case behind the project

Whether the project manager is certified as a PMP

Whether the project will indeed deliver the benefits that have been promised in the statement of work

A

Answer: a) Feasibility from an organization’s standpoint needs to be evaluated. In asserting that financial and market feasibility is established, the business case is already taken care of. The project manager being certified will be beneficial but not sufficient factor for accepting it. Whether or not the project actually delivers the results cannot be known for certain in the beginning.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
53
Q
  1. During the “Deliver Program Benefits” phase of the program lifecycle, the program manager ensures that components are initiated and transitioned. While issuing the charters for the components, what should be the most important consideration for the program manager?

The components should be initiated in the right sequence, as per the schedule laid out in the program management plan.

Prior approval of the program board is secured to make sure there only the necessary components are chartered.

To make sure that the business cases for the components are thoroughly reviewed and validated before charters get issued.

To make sure that the components that are being initiated are contributing to the benefits that the program is expected to deliver.

A

Answer: d) Components that are initiated should contribute to the benefits. This should be the primary concern of the program manager, since we are in the benefits delivery phase. Other considerations are also valid, but option D is the most important.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
54
Q
  1. An engineering company known for excellence in turnkey programs has recently won a large order from a foreign government for a large infrastructure program. Which of the following represents the first set of priorities for the program manager?

Terminate existing programs with lower ROI so that all resources are potentially available for the new program if needed

Ensuring that the programs are broken down to the appropriate level of details for the project managers

Ensuring that as much of the work as possible is outsourced

Ensuring that the right resources are in place for the new work

A

Answer: d) Ensuring availability of resources to work on a foreign government project is of paramount importance as compared to the other statements.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
55
Q
  1. A program for implementing a critical upgrade to a company’s IT systems was implemented using 5 vendors spread across 6 continents. The program is approaching a deadline and there are several issues that are discovered during testing. There is a lot of finger pointing going on and very little progress being made towards resolving the issue. Which of the following will be most useful in this situation?

Colocation

Add penalty clauses to the contracts of all the vendors

Call for a program summit and issue a firm deadline to all the project managers

Increase the contingency reserves with regard to cost and time in anticipation of overruns

A

Answer: a) The word finger pointing indicates that nobody is taking ownership for the issues. At such a time, bringing everybody together in the same location (Colocation) may help getting focus back on resolving the problems in a timely manner.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
56
Q
  1. A program is considered to be fraught with risk. The program manager would like to ensure that the initial risk identification uncovers as many risks as possible so that they can be planned by the program and its components. Which of these techniques would help in coming up with wide range of risks?

Pareto analysis

The Delphi technique

Ishikawa diagrams

Mind maps

A

Answer: b) The requirement is to identify risks, which requires lateral thinking. Pareto analysis is used to prioritize and not really useful in the initial identification. Ishikawa diagrams are used to uncover root causes and may hint at some risks, but will not really give rise to a lot of them. Mind map is a technique used to organize the thoughts in a systematic manner. It might also help in risk identification, but the technique that will probably result in the biggest bang for the buck in terms of number of risks uncovered would be the Delphi technique.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
57
Q
  1. Who should be involved in the preparation of the Program WBS?

The program manager, the project managers, and the teams.

The program manager, the project managers, and the program sponsor.

The program manager and the program office team.

The program manager, the project managers, and subject matter experts.

A

Answer: a) The preparation of the PWBS should ideally involve the teams, along with the program and project managers because it creates a buy in from the team.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
58
Q
  1. The program scope statement has been finalized, the distribution of work among various components has been determined and the program WBS has been created. Which of the following activities should the program manager and the project manager’s focus on next?

Baseline the scope first, then move on to scheduling, budgeting and risk planning.

Work on scheduling, budgeting, risk, and quality planning.

Baseline the scope first, then move on to planning the resources and procurements related to the projects and the program.

Determine the schedule, cost, and resource requirements and the implications on risk and quality.

A

Answer: d) A and C are incorrect because the scope cannot and should not be baselined independent of the schedule and financial requirements. Among the rest, D is a more complete answer than B as it recognizes that schedule, cost, and resource needs will have to be balanced and this will impact risk and quality considerations.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
59
Q
  1. A program includes an operational department that provides support to the products produced by its projects. Since it is a newly introduced function the program manager is closely monitoring it. The program manager notices that average time to serve a customer has gone up for the past 7 consecutive days even though it is still within the service standard threshold set by the organization. What should the program manager do?

Continue to monitor the situation, intervening if the trend continues for some more time.

There is no need to do anything as long as the service threshold is not breached.

Make discreet inquiries about what is happening behind the scenes.

Direct the operations manager to launch an investigation and present an action plan.

A

Answer: d) The rule of 7 states that 7 consecutive points in ascending and descending sequence calls for an investigation and the process is deemed to be out of control. Hence the program manager must intervene and make sure that action is taken to rectify the situation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
60
Q
  1. During a routine scan through of the project reports, the program manager noticed that one of the projects on the program had not yet baselined the scope and was into the execution stage for a long time. What should the program manager do?

Advice the project manager to move towards base lining the scope immediately

Ask the project work to be stopped until a clear scope baseline can be arrived at

Ignore the finding because managing project scope is the project manager’s responsibility

Discuss with the project manager about the scope definition activities on the project and help if necessary

A

Explanations:Answer: d) The scope not being baselined is not necessarily a showstopper. For example, sometimes projects will want to try out different options before deciding how and what it wants to accomplish. However, the program manager should inquire if there is anything that can be done to bring scope clarity for the project and help if necessary.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
61
Q
  1. Program management has similarities and differences with project management. Which of the following captures the essence of the differences?

Programs and projects create deliverables, projects create incremental benefits

Programs are run within a governance structure, projects have a lose governance framework

Programs and projects create deliverables, programs create benefits

Projects are run within a governance structure, programs have a lose governance framework

A

Answer: c) Program and projects can both create deliverables, with the main focus of the program being to create incremental benefits via the project deliverables. Projects themselves do not create incremental benefits, those come via the program. Both programs and projects should be run within a governance structure.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
62
Q
  1. A large construction complex is being built. The complex consists of many residential apartment blocks and some commercial establishments. The program manager is about to start the planning process after the approval of the program charter. Which of the following steps should be done first?

Prepare the project level plans first and then the program management plan can be an aggregation of the plans.

Identify the potential benefits from the program compared with the likely cost and see if the program is justified.

Determine the features needed, budget, and time available; and seek the best possible compromise.

Proceed to define the scope and how it should be managed.

A

Answer: d) Scope planning is usually the starting point in all the planning processes on a program or project. The project plans cannot be the starting point for the program plan (Option A). Identification of benefits and costs is done during business case development, so B is not correct. The scope, cost, and time cannot all be fixed at the same time. Therefore, D is the best answer.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
63
Q
  1. A program has achieved most of its objectives and is nearing closure. Which of the following represents the most comprehensive list of activities to be performed?

Approve closure and transition of components, close contracts, perform financial closure, plan for benefits transition and sustainment and create lessons learned.

Approve component transitions, document lessons learned, archive project and program records, close contracts and take acceptance from the customer.

Close the program, approve component transitions, deliver required reports along with financial and benefit realization reports and document lessons learned.

Close projects and document lessons learned, produce financial and benefit realization reports, close contracts and release the resources of the program.

A

Answer: a) A is the most complete set of activities. B and D are missing the transition and sustainment of benefits, whereas C is missing closure of contracts.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
64
Q
  1. Which is the best statement about projects, programs, and portfolios?

A project provides a set of deliverables to a program which integrates them to create benefits which flow into the portfolio which is of strategic importance to the organization.

A project provides benefits to a program, which coordinates them to create a strategic value, whereas portfolios effectively maintain and sustain the benefits for the organization.

A projects goal is to create something of temporary and unique value, whereas a program takes over what a project creates and a portfolio elevates it to a strategic level.

A portfolio creates a program for effectively delivery management of projects, which then deliver the strategic benefits.

A

Answer: a) A is the best statement keeping in mind the definitions of projects, programs and portfolios. A project provides a set of deliverables to a program which integrates them to create benefits which flow into the portfolio which is of strategic importance to the organization.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
65
Q
  1. A program has created a new service for a telecom company that is ready for a rollout. The cost of a marketing campaign and the whole launch process is $5 million. Expectations are that the first year’s cash margin itself will recover the launch costs. However, there is a 50% chance that revenues may be lower due to problems in the broader economy. What parameters should the program manager take into consideration before deciding whether to go ahead with the launch?

Economic forecasts, the launch costs, the capital expenditure incurred till date, cash flow projections for the coming year.

Launch costs, cash flow projections for the coming years and NPV based on the launch costs and future cash flows.

Economic forecasts, the capital expenditure incurred till date, NPV of the projected cash flows in the future.

Economic forecasts, the capital expenditure including the launch costs incurred till date, projected payback period based on these.

A

Answer: b) The principle sunk costs suggests that the costs that are already incurred should not be taken into consideration while taking forward looking decisions. This rules out considering capital expenditure incurred in the past (A, C, and D). Option B makes sense because it is considering the cash flows in the coming year and using the time value concepts to make an informed decision.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
66
Q
  1. A program for developing road infrastructure has multiple stakeholders and getting everybody’s expectations understood and aligned is proving to be a challenge. Which is the best way to move forward?

Identify the stakeholders, establish their interest and impact, determine the engagement strategy.

Get the project managers to identify the stakeholders, determine who is positive and who is negative, and focus on engaging the positive stakeholders first.

Call all stakeholders for an all-expenses paid offsite meeting with drinks and cocktails to secure their buy in and reduce their opposition.

Ask the sponsor to provide guidance on which stakeholders should be managed and who can be ignored.

A

Answer: a) Option A provides a systematic approach for stakeholder engagement. Options B and D imply that engaging some stakeholders is not important, which may be a folly. Option C is a distracting answer, which seems to imply that taking stakeholders on a junket will magically align their expectations.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
67
Q
  1. A program manager is working on an IT application maintenance program consisting of multiple projects that take care of a suite of custom software applications for a client. The program has been transitioned to a new supplier at an offshore location recently. The project manager for one of the teams escalates to the program manager that she is having difficulty figuring out requirements for the new release because the customer is not providing clear requirements and is not being responsive to emails. What is the best way to deal with this situation?

Ask the project manager to quantify the impact of unclear requirements and send a note to the sponsor warning of a slip in the plans

Take help from the program sponsor to make the customer more willing to provide requirements

Consider collocating the customer with the team for some time until clarity about requirements is reached

Tell the project manager that it is her problem to solve

A

Answer: c) Option A does not solve the problem it merely documents the impact. Option D also does not solve the problem it pushes it back without any value addition. Option C is superior to option B because B is about arm-twisting the customer which may prove to be counterproductive in the long run, whereas C is providing a way to get past the situation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
68
Q
  1. Zulu communications is a cell phone handset manufacturer. Its models have been popular in the past but it has been out paced by other companies which have introduced models with new features at a much faster rate, leading customers to believe Zulu is an old and stale company. It is launching a program to introduce next generation of phones that can successfully compete in the market. How should the program manager go about gathering the requirements for this program?

Organize brainstorming with representatives from the stakeholder groups and the team.

Circulate questionnaires and surveys to gather inputs.

Let the project managers drive the requirements process with the direction that they need to appeal to Gen Y.

Contact some industry experts and apply Delphi techniques to arrive at a feature set.

A

Answer: a) This is a program that will require a lot of lateral thinking to figure out which set of features will enable the company to compete successfully. This is best accomplished in a face-to-face setting that facilitates ideation. Option a (brainstorming) is the only technique that involves face-to-face discussions and seems most appropriate in this case.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
69
Q
  1. A project manager was just appointed to a project within a program and is wondering how to go about planning activities for the project. What is the best guidance that the program manager can provide?

Discuss with the other project managers in the same program and follow the same templates so that it is easier to standardize

Each project is unique by definition and the project manager needs to invent the best methodology for the unique needs of the project

Work with the project manager to prepare the plan to make sure it is of good quality

The best place to start is to refer to historical records and seek guidance from the Program Management Office

A

Answer: d) Where they are available, historical records is the best place to begin planning and such information and guidance can be provided by the PMO. The other answers also have some merit, but remember PMI places a lot of emphasis on creation and usage of historical records.

70
Q
  1. A program to launch a new commercial vehicle is almost complete. The design is accepted and has passed all the mandatory tests and received the approvals. The dealerships and service stations are established and trained. A week from launch, you realize that the spares inventory is missing some key parts which may impact the launch date. Which of the following is the best way to resolve the problem?

Go ahead with the launch; it is unlikely that the parts will be required within the first three months of purchase.

Meet with the project and operations managers and determine the requirement for the parts and make arrangements to acquire them as soon as possible.

Stop the launch and expedite the process of creating a complete parts inventory.

Initiate a root cause analysis of why the requirement was missed and then determine a long term action plan.

A

Answer: b) A is a risky option. You do not want customers to be stranded for parts. D is a long term action plan, but does not address the immediate problem. C is a reasonable choice, but perhaps too extreme. B takes the middle ground where the program understands the needs and tries to expedite. Decision about the launch can only be taken after the analysis

71
Q
  1. A program has entered into a cost reimbursable contract with incentives. The incentive is for lowering baseline costs and the sharing ratio is 60:40 in favor of the buyer. The baseline cost was $1million and the cost came in at $900,000. What should be the final payment to the seller?

$904,000

$900,000

$940,000

$1,040,000

A

Answer: c) The cost of $900,000 has to be reimbursed and the early completion incentive will have a 40% share for the seller, which amounts to 40,000. Hence the final payment should be $940,000.

72
Q
  1. A program is about to start. The sponsor has just issued the program charter. Which is the LEAST effective way for the program manager and the component managers to utilize the program charter?

To come up with acceptance tests that validate the completion of the program and its components

To establish key benefits and outcomes desired by the organization

The high level constraints and assumptions for the program

To establish alignment of the program with the strategy of the organization

A

Answer: a) The charter is high level and will not contain enough detail to come up with acceptance tests. All the other statements about the charter’s contents and intent are correct (Section 8.3.1.6 of the standard for program management, 3rd edition).

73
Q
  1. A large construction complex is being built. The complex consists of many residential apartment blocks and some commercial establishments. More than 1000 workers are working on the construction. Based on this information, this seems to be an example of:

Large project with multiple subprojects

Program

Portfolio

Complex operation

A

Answer: a) There is no information provided here about how the construction work is linked to strategic business objectives, hence it cannot be considered a portfolio. Construction is typically a time bound activity, so it is not an operation. There is no information in the question about whether the activities (components) are being managed in a coordinated way to obtain additional benefits and control. Hence from the available information, this seems like a large project with multiple subprojects.

74
Q
  1. A program to build a commercial complex is in full swing. The program reports a CPI of 0.8 and SPI of 1.2. Which of the following might explain such a scenario?

The projects may have used crashing to speed up the work

The projects may have used less expensive resources to save on cost

Some of the dependencies between the projects may not have been met

The cost of materials may have gone up

A

Answer: a) CPI of 0.8 and SPI of 1.2 means that the project is ahead of schedule and over budget. Option A explains both, whereas option D explains only CPI. Options B and C explains neither.

75
Q
  1. What is the primary purpose of the program transition phase?

To address the transfer of program resources into organizational operations

To address the transfer of program assets into organizational operations

To address the transfer of component and program work or benefits into organizational operations

To address the transfer of resources and assets from organizational operations into the program

A

Answer: c) During program transition, the program manager needs to make sure that the benefits are transitioned to the organization. This may involve transfer of resources (A) or assets (B) or both (D).

76
Q
  1. A program manager was overwhelmed trying to keep tabs on the different projects and the sponsor suggested to her to set up a program office to help out. Which of the following explains the role of the program office?

It represents the center of excellence for program management in an organization.

It provides administrative support to program managers and program management teams.

It provides guidance and mentorship to the program managers in an organization.

It provides and maintains guidelines, best practices, templates and historical information for an organization.

A

Answer: b) The program office provides administrative support to a specific program. Statements A, C, and D describe the program management office, which is more organization wide.

77
Q
  1. A program manager works in a matrix organization and is leading a cross functional program. The project managers all report into specific functions and have no direct reporting relationship with the program manager. The program manager herself is reporting into her function and has an additional responsibility to make the program successful. What would be the biggest challenge for the program manager in this situation?

Getting a clear scope defined for the projects through the functions

Getting a charter issued for the program

Getting the resources assigned to the projects

Integrations and interfaces across projects

A

Answer: d) Typically the biggest challenge in a matrix organization is one of communication. This will likely lead to issues while managing the integrations and interfaces across projects, where communication is most essential.

78
Q
  1. Which of the following is MOST likely to use homogenous teams?

Programs

Operations

Projects

Portfolios

A

Answer: b) Operations involve ongoing, repetitive work and hence it is most likely that they would involve homogenous teams than projects, programs, or portfolios.

79
Q
  1. A surgical equipment maker has come up with a new procedure for cataract surgery that reduces the time taken and leads to faster recovery of the patient. Which is the least effective way for the program manager articulates the benefits of the program for a hospital?

Hospitals will be able to improve their patient turnover and improve revenues by being able to perform more procedures.

It will simplify claims procedures for customers of insurance companies.

It will reduce improve patient satisfaction because they will make a faster recovery.

By freeing up time spent on surgery, it will enable doctors to focus more on innovating on patient care.

A

Answer: b) All the benefits are valid, but benefit B is probably more relevant for patients and insurance companies rather than to hospitals. While articulating program benefits, the program manager needs to make sure that the projected benefits are relevant to the audience.

80
Q
  1. A program to launch a new commercial vehicle is almost complete. The design is accepted and has passed all the mandatory tests and received the approvals. The dealerships and service stations are established and trained. A week from launch, you realize that the spares inventory is missing some key parts which may impact the launch date. Who is responsible to solve this problem?

The program manager

The program sponsor

The manager of the portfolio within which the operation will reside

The program board

A

Answer: a) The program manager is responsible for planning the transition. As the rollout plan has gone haywire, the program manager needs to find out what has gone wrong and fix the problem.

81
Q
  1. A music company is launching an advertisement campaign. The campaign is highly visible and involves different projects. It recently came to light that the program manager leading the campaign has indulged in favoritism while appointing agencies and is suspected to have taken bribes to issue purchase orders. The company is worried about the risk to the campaign and its image if this comes to light. How should the program board proceed?

Let the campaign run its course, but issue a show cause notice to the program manager to protect its image in case of disclosures.

Terminate the program manager and review all the purchase orders issued during his tenure.

Appoint a private investigator to conduct a thorough investigation before deciding future course of action.

Put in place a succession plan for the program manager and gradually transition the responsibilities for the campaign.

A

Answer: b) This is a code of ethics question. Remember there should be very low tolerance for professional misconduct as revelations like these can severely dent the image of an organization.

82
Q
  1. A program has high visibility and several executives are monitoring it closely. A project has reported the likelihood of a 2 month delay. This delay is not yet critical as the project is not on the critical path. How should the program manager present this information in the next program status report?

Maintain the “on schedule” status as the program still has enough buffers

Hide the delay in the program buffers

Proactively escalate this delay to avoid surprises later

Show the program status as “on schedule” but increase the risk level

A

Answer: d) The program manager should be transparent and not try to hide the facts. At the same time, raising alarm bells by escalating what might not be a significant delay may also not be useful. It is factually true that the program is on track, but there is now a higher level of risk due to the delay.

83
Q
  1. During a routine PMO review, they asked to review the program’s benefit register. The program manager, who was newly appointed, pointed to the program scope statement, where a list of deliverables was provided. How can the PMO help the program manager understand the differences between the deliverables and benefits?

Deliverables are commonly recognized at the program and project level, but benefits occur only at the program level

Benefits are specific products, results or outcomes, deliverables represent the value that they add to the organization

Benefits are usually realized only at the end, deliverables are produced throughout the program

Benefits may be tangible or intangible, deliverables are usually tangible

A

Answer: d) The benefits from a program could be tangible (e.g. specific product, or process or result) or intangible (e.g. improved morale, better capabilities, etc.). Deliverables are usually tangible, and more easily recognized and validated. Among the given statements, this one comes closest to correctly explaining the differences between benefits and deliverables

84
Q
  1. A program has rolled out a major upgrade to the Enterprise wide resource planning (ERP) system at a perfumes and fine chemicals company. During the benefits review meeting six months from the rollout, the IT department claimed that the deployment had been smooth and without incident, whereas the business claimed it had disrupted the normal business and added to the operational costs. This is MOST likely to be a result of:

The verification and validation processes before rollout may have ignored obvious quality issues

Stakeholders were not taken into confidence about the features of the new upgrade and the value it adds

The project managers did not adequately engage the business analysts to understand the true requirements

The transition process did have sufficient involvement from all the stakeholders

A

Answer: d) The dispute seems to be about the deployment (i.e. transition) process and not really the benefits of the upgrade or the quality of the system. Hence it is most likely to be a case of stakeholders not being involved in the transition and having differing set of expectations from this process.

85
Q
  1. A mining program is trying to extract commercially viable minerals. However, this is a difficult task due to the geological complexities. Which one of the following would be least useful as success measures for the program?

Variance report on the original v/s approved budget of the program

Total commercial value of the minerals extracted

Compliance with environmental regulations

Safety records

A

Explanations:Answer: a) This program involves an uncertain outcome and geological complexity; hence variance reports would probably not be relevant. Even if the budget was exceeded, it might be worthwhile if the returns were sufficient. On the other hand, ending up under budget may not necessarily indicate success either, unless the program delivered the benefits in the form of commercially valuable minerals.

86
Q
  1. A program delivers a set of components for a new range of mountain bicycles that is about to be launched. About 2 weeks from the launch, the project manager in charge of the chain assembly tells you that it tends to break under certain conditions. Who is responsible for deciding what to do at this stage?

The project manager in consultation with the program manager and program board

The program manager in consultation with the program board and project manager

The program board in consultation with the operations and program manager

The marketing function in consultation with the customers and program manager

A

Answer: b) The program is just a couple of weeks from launch and the impact of this information on the launch parameters need to be carefully considered, taking the board into confidence.

87
Q
  1. While evaluating a new project that has come up for chartering, a program manager realizes that it seems to have a valid business driver and will add value to the organization, but is not aligned with the latest strategy of the company. What should the program manager do?

As long as the project has a valid business driver, the program manager can issue the charter

Review the business case with the project manager and double check the calculations to make sure that it is valid

Check whether the program has resources available and if it does, then issue the charter

Check with the program board before going ahead

A

Explanations:Answer: d) The program manager is responsible to ensure that the program maintains alignment with the organization’s strategy. Even though the project makes business sense, this needs to be validated with the program board, which represents the interest of the organization.

88
Q
  1. A project is getting delayed and the delay is causing a cascading effect on other projects in the program. In order to nip the issue in the bud, the program manager is discussing with the project manager possible ways to speed up the work. Which of the following is the most useful suggestion?

Double the number of resources allocated to the project

Outsource the work to a third party with strict penalty clauses

Provide incentives for team members of the project if they work overtime and bring the project back on track

Find out the bare minimum work that needs to be done in the delayed project to enable other projects to proceed

A

Answer: d) The program manager should be most concerned with resolving the interdependencies and getting the other projects unblocked. The project manager will be responsible for determining which of the other means would be most effective to speed up the specific project.

89
Q
  1. A financial services program manages the investment portfolios of high net worth clients using a proprietary quantitative formula. What metric is best suited for this program?

Current and forecast returns on investments

Returns on investment as compared with benchmarks

Planned vs. actual returns on investment

Number of positive reviews from customers

A

Answer: b) The return on investment needs to be compared against benchmarks to be meaningful. In the year where the markets have been booming, even a high rate of return may not be viewed as success, whereas in a recessionary condition even a modest return would be viewed as success.

90
Q
  1. The program manager and the project managers are reviewing the program level procurement management plan. Which of the following best describes the activities of the program manager and team that must be addressed in the plan?

The details of all the contracts entered into at the program and project levels and the duties and obligations of the vendors and the program team

The list of standard suppliers, evaluation guidelines, bid documents, etc. that will be used for procurement

The way in which the procurement processes will be carried out in the program

All the contract related documentation, invoices received and paid out related to the procurements of the program contract closure, and archiving of contract documentation

A

Answer: c) The correct description of the procurement management plan is given in Option C. It is a high level plan that describes how procurements will be carried out.

91
Q
  1. A program has several projects which use 3 point estimation techniques. Project A has an expected duration of 56 weeks and a standard deviation of 11 weeks. Project B has an expected duration of 24 weeks and a standard deviation of 13 weeks. Project C has an expected duration of 67 weeks and a standard deviation of 24 weeks. Project D has an expected duration of 41 weeks and a standard deviation of 18 weeks. Based on this information, which project’s schedule performance should the program manager manage most closely?

Project A

Project B

Project C

Project D

A

Answer: b)The variability of project B as compared to the mean (σ/μ) is the highest, so there seems to be maximum uncertainty about it. In the absence of any other information, the program manager needs to keep a closer eye on Project B.

92
Q
  1. A startup company was acquired by a larger company. In the acquiring company it is mandatory to follow certain processes for compliance purposes. The members of a project team drawn from the acquired company are finding these processes cumbersome and are resisting them. The issue has been escalated. What should the program manager do?

Ask the project manager to deal with this and warn him that lack of compliance will reflect poorly on his performance ratings.

Relax the regulations for six months because process compliance requires a culture change, so it is bound to take some time.

Meet with the team members along with the senior leaders from the acquired company to impress upon them the need to comply with the regulations.

Fire one of the defaulters to set an example for the rest of the team members so that they fall in line.

A

Answer: c) Option A is passing the entire onus to the project manager. Option B has some merit in that the employees of the startup company need to make a cultural transition, but it is not often that you have 6 months to deal with this. Firing just one of the defaulters (Option D) seems to be arbitrary and unfair. The best way is to impress the importance of the culture change and take help from the leaders who are familiar with the team members from the acquired company.

93
Q
  1. During execution of a project that is part of a program, the project manager wants to implement a change that is well within the reserves of the project. In reviewing this change request, what should be the program manager’s biggest concern?

Ensuring that the proper change management processes are being followed.

Ensuring that the alignment with strategy of the organization is maintained.

Ensuring that the impact (if any) on other components is also analyzed and considered while making a decision.

Ensuring that all the stakeholders are taken into confidence and their views are considered during the process.

A

Answer: c) The project manager seems to have already done the due diligence with regard to the impact assessment, so there is not much “process” related concern here. It may not always be necessary to consider the views of ALL stakeholders (D) and while maintaining the strategic alignment may be important, it is unlikely to be compromised by a change that is of a scale that can be accommodated by a project’s reserves. The most logical choice is C, because the program manager definitely needs to worry about the impact of the change on other components.

94
Q
  1. One of the projects in a program makes embedded software for pacemaker devices for use during critical heart surgery. The program manager has issued quality policy guidelines for the projects. Which one is most appropriate for this project?

Total Quality Management

Fitness for Use

Zero Defects

Kaizen

A

Answer: c) Zero defects involve establishing what the customer wants and providing it the first time without waste or having to repeat work. In a scenario where the devices are lifesaving, even a single defect can cause loss of life. Hence the philosophy should be geared towards zero defects.

95
Q
  1. A program manager recently took over a troubled program after the previous program manager left. Most of the project managers complained that the delays were due to poor estimation of the central component which is now running behind schedule and cascading the delay to other projects. What should the new program manager do?

Ask all the projects to contribute resources to first rectify the central component before work on other projects can begin

Ask for details about estimates of the central component and review it to make sure they are reasonable

Work with the manager of the central component to expedite it, and estimate the impact of the likely delays

Introduce a rewards program for team members working overtime to make up for the delays

A

Answer: c) The program manager must recognize that there are delays and see how best they can be addressed. Option A may not make sense, unless the delay can be addressed by adding resources. Option B will not make sense unless the program manager is also an expert and in a position to validate the estimates. Option D is not a sustainable option as it is likely to burn out the team.

96
Q
  1. Which of the following best describes the role of the program manager in benefits management?

Create benefits, transition, and sustain the benefits for the organization

Identify benefits, plan for benefits delivery, ensure benefits are realized and transitioned

Create the benefits, measure the benefits and sustain the benefits

Create the benefits register, benefits realization plan, and the benefits transition plan

A

Answer: b) The program manager does not himself or herself create the benefits. The program manager identifies benefits, plans for them and ensures that the program takes steps to realize, monitor and transition the benefits.

97
Q
  1. A program manager is working on an IT application maintenance program consisting of multiple projects that take care of a suite of custom software applications for a client. The program has been transitioned to a new supplier at an offshore location recently. The managers from one of the business units of the customer escalates to the program manager that the project teams are contacting him too frequently about requirements and causing disturbance. What should the program manager do?

Tell the customer that clarifying requirements is his responsibility and cannot be avoided

Tell the project teams to limit communication with the customer except in extreme circumstances

Review the scope statement and communication plan for the program and the concerned project teams to make sure they address everybody’s needs

Establish a single point of contact with the customer

A

Answer: c) It is true that communication about requirements is necessary. The program manager should make sure that the scope statement is providing enough clarity to the teams and that the communications plan is addressing the needs of the team as well as the customer during the requirements clarification process.

98
Q
  1. The projects within a program have just finished initial risk identification, analysis of the risks, and planning the responses. Contingency reserves have been established at the project and program levels. How frequently should the program manager review the project level risks during the program?

Every week

It should be reported out to the Program board at a regular frequency

Only as requested by the project manager

At regular, scheduled risk reviews

A

Answer: c) The monitoring of the project level risks should be done by the project manager. The program manager should step in only when a risk gets escalated or crosses a threshold.

99
Q
  1. All the projects in a program are under extreme time pressure. Time-to-market is a critical success factor with regard to all the deliverables. The project manager of one of the projects which is still ongoing received a major change request that will increase cost, risk, and time. The project manager approached the program manager for advice on how to deal with the change. How should the program manager deal with this situation?

Reject the change request

Accept the change and propose an extension to the timeline of the project and the program

Accept the change and propose an increase in cost to address it in the given timeline

Negotiate with the customer to reduce the scope

A

Answer: d) There are two important pointers in the question. The program is time critical and the change is impacting not just cost and time - but also adding to risk. Given these two statements, it is best to scale back on the scope by negotiating with the customer, rather than going ahead with time or cost extensions or rejecting the change out of hand.

100
Q
  1. A program budget is estimated using three point estimation technique, where the most optimistic estimate was $35 million; pessimistic was $55 million and most likely was $42 million. What is the likelihood of the program finishing up under $44 million?

68%

54%

< 50%

> 50%

A

Answer: d) The expected value for the budget is (35 + 4 * 42 + 55)/6 = 43. This means the program is equally likely to be ending up with expenses above or below 43. Since 44 > 43, the likelihood of expenses being under 44 is > 50%.

101
Q
  1. A program with a large number of components is about to start. Governance is a key issue for the program manager due to the complexity of the components and the program manager is trying to address this by preparing a program governance plan. Which of the following is the LEAST important component of this plan?

Summarize the goals of the program

Composition of the governance board and roles and responsibilities of the members

Schedule of the regular and phase gate review meetings

Key performance indicators and thresholds for measuring benefits achievement

A

Answer: d) A, B, and C are all valid points to include in the program governance plan. D is more likely to be a part of the benefits register or benefits realization plan. (Section 6.2.4 of the standard for program management, 3rd edition).

102
Q
  1. Who is responsible for authorizing a component within a program?

Executives in the performing organization

Portfolio manager

Sponsor

Program management office

A

Answer: c) The sponsor funds a component within the program. The Executives authorize the sponsor and the program board. The portfolio manager is responsible for managing a portfolio. The program management office plays a supporting role to a program and does get into decision making or authorization.

103
Q
  1. A program manager is working on benefits management and has prepared program architecture. How should the program architecture be utilized?

Program architecture represents the technical framework and design principles for the program.

Program architecture establishes the correlation between the components and how they contribute to the benefits.

Program architecture identifies a monitoring and process control framework which will govern the benefits management processes.

Program architecture represents the initial understanding of the requirements and needs expressed by the stakeholders from a program.

A

Answer: b) The program architecture defines the structure of the components by identifying the relationships among the components and the rules that govern their inclusion. (Section 4.2.2 of the standard for program management, 3rd edition). Hence, Option B maps closest to this idea of the architecture.

104
Q
  1. Project A and Project B are part of a program. Project B depends upon the output of Project A’s deliverable has been delayed, which has a severe impact on Project B. Who is responsible for solving this problem?

Manager of Project A

Manager of Project B

Program Manager

The functional managers

A

Answer: c) The management of interdependencies within a program is a responsibility of the program manager. This is one of the reasons for managing them as a program as opposed to a project.

105
Q
  1. Which of the following best describes the differences between a portfolio and a program?

A portfolio is strategic and a program is operational

Programs can have operations, whereas a portfolio cannot

Programs deliver benefits, whereas a portfolio need not

Programs have a definite time frame, portfolios are not initiated with a time frame in mind

A

Answer: d) Portfolios is a strategic collection of components that meets some business objectives. They are not constituted with a time line in mind. A program can be long and the duration may not even be known upfront, but they are by nature temporary

106
Q
  1. During the benefits delivery phase, what is the best role for the program manager?

Controlling and managing change

Developing and engaging the team

Monitoring and tracking benefits delivery

Initiating and transitioning components

A

Answer: c) A, B, and D are all valid roles and activities that the program manager must perform during this phase. However, it all should be with a view to delivering the benefits, so the best role for a program manager is to make sure that the benefits are indeed being realized.

107
Q
  1. The program team is developing rules for progress reporting on the program and related projects. At the program level, the duration of most activities is equal to or less than two reporting periods. Which of the following methods would be most appropriate for this program? As it evaluates methods, which approach should the team use?

Weighted milestone

Fixed formula progress reporting

Forecast reporting

Earned value reporting

A

Answer: b) Fixed formula progress reporting uses a partial credit approach (e.g. 50/50) and is useful when the duration of an activity is equal to or less than two reporting periods. The weighted milestone approach is useful when the duration of an activity is longer. Earned value reporting shows variances and forecast reporting focuses on future activities of the project.

108
Q
  1. A petroleum exploration company has a need for submersible pumps for extracting oil. These pumps are expensive and highly customized based on geography and oil characteristics. The availability and maintenance of these pumps is a bottleneck in the operations for the company, so they have decided to open a submersible pumps business themselves. The main purpose is to serve in-house requirements and not compete in the open market. This is an example of:

Program governance

Backward integration

Forward integration

Concentric diversification

A

Answer: b) The Company is going for backward integration by deciding to insource the machinery needed for its operations.

109
Q
  1. A cross functional program is set up to be executed in a matrix organization. The project managers all report into specific functions and have no direct reporting relationship with the program manager. The program manager will report into a function and has an additional responsibility to make the program successful. What would be the most important skill for the program manager in this situation?

Negotiation skills, ability to extract maximum mileage from interactions

Pleasant personality, getting along with everybody

Influencing without authority, getting others to contribute

Expertise in general management, gaining respect from the team

A

Answer: c) Whilst all of these are useful qualities, the most important attribute for this program manager is going to be the ability to influence the project managers and the team members without having direct authority over them.

110
Q
  1. A company operating in the biotechnology space is working in several areas. They have a new drug development program that comes up with new prescriptions based on biochemical processes. They have a clinical research business where they perform outsourced projects targeted towards specific goals. They also have a biofuels business looking to extract fuels from natural sources. This describes a collection of:

Programs

Product lines

Portfolios

Operations

A

Answer: c) Portfolio is a strategic grouping of components that meet specific business objectives. The description best aligns with the definition of a portfolio.

111
Q
  1. A project manager is outsourcing a complex piece of work on her project, as the project does not have in-house technical expertise. The requirements for this piece of work will evolve over a period of time. A vendor has been identified. Which form of contract should the program manager recommend for use in this case?

Cost reimbursable

Cost reimbursable with incentive clauses

Cost reimbursable with penalty clauses

Fixed price with penalty clauses

A

Answer: b) The work is known to be technically complex and the scope of work is unstable. Therefore fixed price contract cannot be used. Among options A, B, and C which all recommend cost reimbursable contracts, option B is best because it would provide an incentive to the vendor.

112
Q
  1. A product created by a project team within a program is about to transition into operations. During the training and enablement of the operational team, the operations manager suggests that a little expenditure on marketing would greatly increase the potential revenues from the new product. What kind of a response strategy is being suggested here?

Enhance

Workaround

Share

Exploit

A

Answer: a) There is an opportunity and we are trying to increase the size of the opportunity through marketing efforts. This is an example of enhance strategy.

113
Q
  1. A large automobile company invited an engineering company to construct a new factory. The work was completed 6 months ahead of schedule and the quality of work was excellent. Pleased at this result, the customer invited the program manager and 10 key members of the team to their board meeting in Alaska for a special felicitation ceremony. This is an example of:

Incentive fee

Rewards and recognition

Fringe benefits

Bribe

A

Answer: b) There is no evidence in the question that the special recognition was in the contract as an incentive. This is a recognition from the customer to the supplier’s employees hence it cannot count as a fringe benefit. There is no evidence of an expectation of a kickback or favor for this transaction so it is not a bribe. This seems to be an example of rewards and recognition.

114
Q
  1. A project manager is working on a program that has recently received approval to transition and close. The project manager receives a change request from a customer, which will require extension to the schedule by a few weeks. What should the program manager do?

Ask the project manager to ignore the change for a few days until the closure formalities are completed

Inform the customer that the program is closing down and the change cannot be accommodated

Close the project and the program and initiate a new component for the change that has been requested

Evaluate the impact on the program’s benefits and take a decision

A

Answer: d) In this scenario, the program manager needs to make a decision based on the impact of the changes on the program’s benefits

115
Q
  1. A rehabilitation program has been put in place for a community that was affected by severe flooding. The program is funded by International Red Cross and a number of nongovernmental organizations and trusts. What kind of reporting and communication is most appropriate for this program?

Program performance reports, program forecasts, earned value reports, and benefits realization reports

Forecasts, earned value reports, press releases, and community outreach programs

Forecasts, program performance reports, communications messages, and updates to the communication management plan

Forecasts, program performance reports, and communications message

A

Explanations:Answer: b) The program is very public and visible, therefore there needs to be a public outreach and proactive outward communication that needs to happen, in addition to providing confidence that the existing funds are being deployed productively, which comes from earned value and forecasts. Therefore B represents the best reporting and communications framework for this program.

116
Q
  1. While preparing the program WBS, a member of the program team is wondering if the “other work” should be included. What is the best way to address this question?

It should not be included. The PWBS only focuses on linkages with project level WBS.

It should be included. The PWBS should cover all the work of the program at a high level.

It depends whether the other work contributes to the “value creation” activities or are merely supporting activities.

It doesn’t matter, because the program manager directly oversees the other work, while the project managers take care of their components.

A

Answer: b)The PWBS is created at a relatively high level so that the program manager can manage at a fairly high level of granularity. However, for it to be useful, it must include all the work in the program at a high level, not just the work performed on the projects.

117
Q
  1. A program manager is trying to identify risks on a program. The team members of the projects are known to each other and the company has a culture of respect for seniority. The program manager is really keen on making sure maximum possible risks are identified at an early stage. Which of the following techniques would be most helpful?

Debono’s six thinking hats

Delphi technique

Brainstorming sessions

Interviewing and questionnaires

A

Answer: b) The culture of respect for seniority will stifle the free flow of ideas and lateral thinking necessary for the six thinking hats and brainstorming to be successful. Interviewing and questionnaires will be helpful, but Delphi technique better utilizes the collective wisdom of the group by maintaining anonymity and removing the fear of contradiction by seniors.

118
Q
  1. Which of the following represents the difference between change management at the project level and the program level?

Project level change management focuses on preserving the ability to fulfill requirements, whereas program level change management focuses on preserving the ability to deliver benefits

Project level change management focuses only on the triple constraints, program level change management focuses on all the 9 knowledge areas

Project level change management looks to avoid change, program level change management looks to embrace change

Project level change management is proactive whereas program level change management is reactive

A

Answer: a) The program manager looks at changes from the point of view of impact to the ability of the program to deliver benefits, whereas the projects look at it from delivering on the requirements within the triple constraints.

119
Q
  1. A program is being executed in the public domain with multiple stakeholders and high instance of conflict. What is the best way to handle conflict on programs?

Programs should try to avoid conflicts by anticipating stakeholder needs and architecting the program to deliver the benefits that are relevant to them.

Conflict is inevitable, but should not be allowed to fester indefinitely; program managers should drive towards effective conflict resolution by collaboration.

Conflicts arise mainly due to ineffective decision making; providing effective governance mechanism can preempt conflict and keep the program running smoothly.

Conflicts are inevitable and even desirable; the program manager should respect the views of all the parties but take the decision in the end keeping the larger interest of the organization in mind.

A

Answer: b) Statement A is incorrect conflicts cannot be avoided as they are inevitable. Statement C is also naive because effective governance may lead to effective decision making, but conflicts can still arise. D is correct for the most part, but differs when it says that program manager should always take the final decision. B is a better statement as it drives towards collaboration which is the most effective conflict management technique.

120
Q
  1. Project A and Project B are part of a program. Project B depends upon the output of Project A’s deliverable has been delayed. How can the program manager help the manager of project A speed up the delivery?

Assign more resources from the program’s resource pool to speed up work

Ask the manager of project A to identify activities that can be performed in parallel

Issue a deadline for project A and an incentive for completing work before the deadline

Ask the manager of project A for options to speed up the delivery

A

Answer: d) The program manager needs to first understand the reasons for the delay and what might be helpful in this case. This insight can only come from the project manager. Assuming that crashing (A) or fast tracking (B) will work on pulling back a schedule that has already slipped may be incorrect. Applying rewards and penalties (C) may help, but the best way to decide how to intervene is to ask the project manager what kind of intervention will be most effective.

121
Q
  1. In the middle of the financial year, there were severe expense reductions ordered to shore up the financial performance of the company. Which of the following techniques will help the program manager exercise better control over the expenses of the program?

Change control system

Work results

Work authorization system

Performance reports

A

Answer: c) A work authorization system helps to ensure that only the planned and essential work is being performed at any given point in time. It can be used to minimize gold plating and unnecessary expenditure.

122
Q
  1. A program has several projects and a couple of them have already transitioned into operations which are part of the same program. The operations are fairly stable and the projects have also matured to a significant extent. A new senior executive has taken over as the program sponsor recently and has directed the program manager to “increase the focus on quality”. Which of the following will be most useful skills and qualities for the program manager in this scenario?

Total Quality Management

Kanban

PDCA cycle

Kaizen

A

Answer: d) Kaizen involves proactively improving the organization and continuously trying to improve as an organization. Since this is a mature program, there are unlikely to be spectacular gains coming out of implementing novel philosophies. Kaizen is least intrusive and at the same time provides for the possibility of continuous, incremental improvements.

123
Q
  1. A pharmaceutical company has a thriving new drug development program. One of the projects has created a new medicine, which is approaching clinical trials. There is a risk that this medicine causes some side effects. The project does not have sufficient reserves to cover liabilities, nor does the program. So the program manager decides to move the trials to a different country where the liability clauses are not so stringent. This requires additional funding, so the change request has gone to the Program Board. How should the Board decide?

Decision should be based on a comparison of the additional cost of trials and the likely liabilities

The Program Board should have a discussion and the Program Sponsor should take a final call

This should be sent to the Legal department as they are in a better position to take a call about liabilities

The change should be rejected on grounds of ethical practices

A

Answer: d) The scenario seems to indicate that the medicine has some serious side effects (from the fact that the contingency reserves are not sufficient to cover them). This being the case, the shifting of trials to another country simply to escape liabilities is an unethical practice. The board should ask the program to go back to the drawing board and try to reduce the risk.

124
Q
  1. A program manager in a technology startup company thought of a new idea and is trying to seek a charter to pursue it. What should be the first step for the program manager?

Prepare a detailed business case with funding and resourcing requirements and likely benefits

Identify a potential sponsor for the program

Identify resources needed for successful execution of the idea

Prepare a proposal that can be sent internally as well as externally for funding approval

A

Answer: b) The first requirement is to identify a sponsor who can provide resources and champion the program within the organization. Without the firm backing of the sponsor, even the best articulated business cases backed up with the best resources and proposals can fail to take off.

125
Q
  1. A function within an organization focuses on developing and fostering program management expertise, maintaining best practices, and mentoring and guiding program managers. This is an example of:

Functional organization

Projectized organization

Project Management Office

Tight matrix

A

Answer: c) The Program Management Office fits the description provided.

126
Q
  1. You are the Program Manager on a defence program, deploying sophisticated weaponry on a potential battle front. There was a serious disagreement at one of the meetings, which led to a couple of the deputies coming to blows and almost using their weapons. What is the best way for the program manager to deal with this conflict?

Collaboration/problem solving

Compromising

Smoothing

Forcing

A

Answer: c) Smoothing refers to trying to reduce the temperature of the conflict to buy time so that a better solution may be found. If the two parties to the conflict are coming to blows and almost at the point of injuring each other, you need to allow time for the situation to calm down.

127
Q
  1. An electronics company is working on an advanced system for an early warning system to predict the weather. The program will have 20 major projects that will have sites in 12 states. Which of the following components is least appropriate for inclusion in the program?

A research project to figure out the correlation between the data points and the parameters of the weather.

An operational unit within the weather office to process the data collected by the systems.

An operational unit to manage relief operations.

A project to install and commission the radar systems integrated with computing resources to process the readings.

A

Answer: c) The program’s main purpose as stated in the question is in providing early warning systems. A, B, and D are aligned to the purpose. C (relief operations) can benefit from the early warning data, but is not directly able to contribute to the main purpose of the program.

128
Q
  1. A program delivers a set of components for a new range of mountain bicycles that is about to be launched. About 2 weeks from the launch, the project manager in charge of the chain assembly tells you that it tends to break under certain conditions. Who is responsible for this situation?

The project manager

The program manager

The program sponsor

The team members of the chain assembly project

A

Answer: a) According to the principle of total quality management, the management and not the worker is responsible for quality. From the description provided, it seems to be a case of projects not adhering to quality parameters and therefore the responsibility lies with the project manager.

129
Q
  1. A program to build a commercial complex is in full swing. The program reports a CPI of 1.2 and SPI of 0.8. Which of the following might explain such a scenario?

The projects may have used crashing to speed up the work

The projects may have more expensive resources to speed up the work

Some of the work on the projects may not have started on schedule

The cost of materials may have gone down

A

Answer: c) CPI of 1.2 and SPI of 0.8 means that the project is behind schedule and under budget. Option C explains both, whereas option D explains only CPI. Options A and B explain neither.

130
Q
  1. A pharmaceutical company has a thriving new drug development program. One of the projects has created a new medicine, which is approaching clinical trials. A competitor company has learnt about this development and has expressed interest in licensing this formula. Who should be involved in making this decision?

The Program Board, based on the recommendations of the Program Manager

The Program Manager, Project Manager and the Sponsor, based on the recommendations from the team

Senior executives within the company, based on the recommendations of the Program Board

The Legal and Finance departments based on the financial and legal implications

A

Answer: c) This is a corporate tie up and decisions of this nature should go right up to the executive levels in the company, especially because the formula seems to be strategic enough to invite the proposal from a competitor. Legal and Finance departments will undoubtedly be involved in the decision, but this is primarily a business decision.

131
Q
  1. Project A has a budget of $400K and is 100% complete, Project B has a budget of $150K and is 90% complete, Project C is worth $400K and is 75% complete. If the total spending on the program is $900K, what is the cost variance for the program?

$65K

$65K

$35K

$35K

A

Answer: b) CV = EV - AC = 835 - 900 = $65K

132
Q
  1. An airline company is trying to improve customer satisfaction. A program has been initiated and work is in progress on various fronts. Which is the most useful metric that would drive customer satisfaction?

Average miles flown per customer per year

Average revenue per customer

On time arrival of flights

On time departure of flights contribution

A

Answer: c) The customer of an airline would be most interested in the on time arrival of flights. Thinking from the customer’s perspective, the other metrics do not make much of a difference in terms of their experience of using the airline’s services. Hence (C) is the metric that is most useful for the program manager.

133
Q
  1. The program consists of 10 projects. Each project performs a Validate Scope process to determine whether the deliverables of the project should be accepted. What should be the role and interest of the program manager in this process?

The program manager should provide oversight and guidance about the scope. The program manager should ensure that the deliverables produced by the projects can contribute to the creation of benefits for the customers of the program.

The program manager should be deeply involved in this process, because the program is responsible for guaranteeing quality and fitness of purpose of the deliverables. The program manager may play this role directly or through the program management office.

The program manager should not be concerned about the project level activities, which are best managed by the project managers. The program manager should be more interested in the transitioning of the project deliverables into operations.

The program manager should play a peripheral role in this process. The project level work should be left to the project managers, but the program manager views this process from the perspective of managing overall program risks.

A

Answer: a) In this case, the key words are “oversight and guidance” and “creation of benefits”. The program manager will let the projects determine the way the activities are conducted, but focus more on providing guidance and ensuring that the benefits are realized.

134
Q
  1. A program manager is trying to consolidate the suppliers on a program by merging multiple contracts issued by different projects into a single contract. The program manager has invited existing suppliers as well as some new suppliers to a bid for the contract. What kind of a bid document is best suited for this situation?

Request for Proposal

Invitation to Bid

Request for Quote

Invitation to Tender

A

Answer: a) This is a bunched contract combining several existing contracts. Even if the suppliers are familiar with some aspects of the larger contract, it would be necessary for the program manager and project managers to validate the seller’s understanding of the requirements and also evaluate the seller’s competencies to do the work. RFP will provide an opportunity to evaluate detailed proposals.

135
Q
  1. The CPI for a program is 1.2 and that of a project within the program is 1.1. Which of the following is the least plausible explanation for this?

The project might have been utilized resources allocated to the other projects and shored up its own performance at the cost of others.

The project may not have managed to start all the activities as per plan which may have resulted in similar delays to other projects on the program.

The cost of inputs may have gone down as a result of the changes in the broader economy.

The program manager and the project manager may have been too conservative in estimating costs.

A

Answer: a) B, C, and D explain why the project and the overall program are under budget. Statement A does not make sense. If the project utilized resources allocated to other projects, its cost would have gone up and it would not have been under budget.

136
Q
  1. Two project managers who were working on a program were involved in a conflict for resources. The program manager got the two together and entered into a discussion to find the best possible solution. At the meeting, everybody agreed on a way forward. What more should the program manager do to make sure the conflict is resolved?

Make sure that the resolution agreed upon is implemented as fast as possible to prevent it from rearing its head again.

Meet with the project managers separately after some time and ask them if they are satisfied with the resolution.

Inform the program board about the decision to take their buy in.

Log the reasons for the conflict, the history, and the resolution into the lessons learned document for the program for future reference.

A

Answer: b) The program manager needs to make sure that both parties are indeed happy with the resolution. One of the dangers with collaboration as a conflict management technique is that one of the parties simply withdraws or gives in without really buying into the outcome. Hence, it is important to log the reasons for the conflict, the history, and the resolution into the lessons learned document for the program for future reference.

137
Q
  1. A critical resource within a project has resigned. Though the project has a succession plan, there is likelihood that some of the other projects may experience interface issues. How should this be handled?

It should be logged in the risk register for the project as well as the program

It should be logged into the project risk register and the program issue register

It should be logged in the project issue register and the program risk register

It should be logged in the issue register for both project and program

A

Answer: c) As far as the project is concerned, the risk (resource leaving) has already occurred, so it has to be logged in the project’s issue register. For the program this gives rise to an interface related risk (since it involves an uncertainty), so it needs to go into the program risk register.

138
Q
  1. A project is part of a program. The project had identified a risk, which has now actually occurred. This will cause a cost escalation of $5 million. How should this be handled within the program?

From the contingency reserves of the project

From the contingency reserves of the program

From the management reserves of the project

From the management reserves of the program

A

Answer: a) The risk was already identified; hence it is a known unknown. Contingency reserves are used for known unknowns. The program level reserve is not a replacement for the project level reserves; hence this comes from the project contingency reserve.

139
Q
  1. An automobile company just finished a program to launch a new vehicle on a hybrid platform. Which of the following would be LEAST important artifact from the closure processes?

Lessons learned

Cost benefit analysis of the program

Training plan for the customers, dealers and service stations

Acceptance report from the road safety authority

A

Answer: b) A, C, and D are obviously expected outputs. B is least important, because the benefits from this development will not be realized until it transitions into operations and the customers start buying it. So, it doesn’t make sense to prepare a cost benefit report yet.

140
Q
  1. What are the typical outputs of the program definition phase?

Business case, Roadmap, Charters for the Program and Projects, and Funding commitments

Program Charter, Roadmap, Governance structure, and Program Management plan

Business case, strategic directive, initiated components, and governance structure

Program charter, program roadmap, Program team, and project manager assignments

A

Explanations:Answer: b) The components of a program are initiated typically during the benefits delivery phase. Hence A, C, and D contain at least one invalid output. Option B contains the best set of outputs that would be associated with the program definition phase.

141
Q
  1. A program manager is anticipating a 50% budget reduction in the forthcoming accounting period due to a particularly difficult economic environment. Which of the following is the best way to ensure that the components are taking necessary measures to cope?

Ask all components to replan with a 50% budget reduction

Review the program and component funding requirements using zero base budgeting techniques

Escalate to the program board and push for maximum funding

Inflate the budget demand by 50% to ensure that the program does not get impacted

A

Answer: b) Since the cut is drastic, the program manager needs to review and shrink the budget needs to the lowest common denominator. One of the techniques to do this is zero base budgeting where each item of budget has to be justified afresh.

142
Q
  1. A program manager is trying to consolidate the suppliers on a program by merging multiple contracts issued by different projects into a single contract. The program manager has invited existing suppliers as well as some new suppliers to a bidder conference. What is the best description of a bidder conference?

Meetings which provide sellers opportunities to ask questions and obtain clarifications

Meetings during which the buyer evaluates the sellers before making the decision on the selection

Meetings during which buyers can ask questions and obtain clarifications about seller’s capabilities

Meetings that impress upon the sellers the intensity of competition so that the buyer gets the best terms

A

Answer: a) The bidder conference is meant to give sellers an opportunity to ask question and obtain clarifications before deciding about their proposals.

143
Q
  1. A program manager has recently taken over a program that has been in progress for 2 years. There are 8 projects and 15 vendors on the program. What should the program manager do?

Set a 6 month timeline to consolidate to top 3 vendors in each area.

Ask for the review reports of the vendors and gradually phase-out the bottom 5 vendors.

Let the project managers decide on which vendor to use depending upon their specific requirements.

Look for opportunities to consolidate in consultation with the project managers and the procurement manager.

A

Answer: d) The program manager should definitely look for consolidation opportunities, but it should be done in consultation. Option A and B are too specific without providing any justification about why the plan is being recommended. Option C loses out on the potential benefits of consolidation.

144
Q
  1. A consumer of electricity is signing a power purchase agreement with a producer. The rate agreed is $0.4 per unit of electricity, with a clause to revise the rate whenever there is a 10% movement in the price of the feedstock (natural gas) in the market. What kind of contract is this?

Fixed price with economic price adjustment

Fixed rate contract

Cost reimbursable

Fixed price with incentive and penalties

A

Answer: a) The rate in this case is agreed upfront in this case with a clause to revise it based on a parameter based on broader economic parameters. The buyer has not agreed to reimburse the seller for all the costs, so it is not a cost reimbursable contract, nor is there an incentive or penalty involved. So, this is FP with EP.

145
Q
  1. A project is being initiated within a program to replicate in wireless telephony, the success of a project in wired telephony. Which type of estimation might result in quickest results in this case?

Bottom up estimation

Analogous estimation

Parametric estimation

Expert estimation

A

Answer: b) Since a similar project has been done in the past within the same program and there is data available from that project, analogous estimation will result in the quickest results.

146
Q
  1. A project manager is working on a program that has recently received approval to transition and close. The project manager receives a change request from a customer, which will require extension to the schedule by a few weeks. What should the project manager do?

Inform the program manager about the change and present alternatives about handling the change request

Start working on the change and try to expedite it so that it can finish before program close

Inform the customer that the program is closing down and the change cannot be accommodate at this stage

Evaluate the impact on the program’s benefits

A

Answer: a) The project manager should neither try to prevent the change (Option B) nor accept it (Option C) without concurrence from the program manager, especially at this stage. Evaluation of the impact on the program is something that the program manager will do. The project manager should try and come up with various options and present them to the program manager so that an appropriate decision can be made.

147
Q
  1. An earth-moving machine is allocated to a construction program. This machine has some custom attachments that make it particularly useful for the site on which the construction is taking place. Many projects have a need for this machine and it is leading to frequent conflict among projects. Which is the best way to deal with this situation?

Raise a change request to buy or lease more such equipment

Discuss with the project managers and decide based on the relative priorities

Let the project managers decide through dialogue

Set up a policy that whichever activity is on the critical path gets higher priority

A

Explanations:Answer: b) This conflict is affecting multiple projects, so the program manager must get involved. The decision is about a specific piece of machinery; hence it needs to be taken after discussing the needs of all projects and coming up with a priority order. Critical path may not always be the right choice.

148
Q
  1. Project A has a budget of $400K and is 100% complete, Project B has a budget of $150K and is 90% complete, Project C is worth $400K and is 75% complete. If the total spendingon the program is $900K and the current trend of cost performance is likely to continue in the future, what is the expected cost of the program?

$1,024K

$900K

$881K

$1,015K

A

Answer: a) EAC = BAC/CPI = 950/ (835/900) = $1,024K

149
Q
  1. A well-diversified company is present in multiple businesses ranging from automobiles to textiles. The financial performance has been lackluster and the debt burden has been mounting. The company is looking to exit some businesses in order to shore up the balance sheet. Which is the best way to achieve this?

Initiate a program to review existing businesses and recommend the optimal portfolio

Appoint a consultant to advise the company on portfolio rationalization

Undertake a review of the portfolio and the competitive positioning of the company

Find out the bottom 3 performing businesses in the past year and put them on the block for sale

A

Answer: c) The Company is looking to rationalize portfolio. Option C best represents the steps they need to take.

150
Q
  1. In setting up the information management system for the program and its components, what is the most important consideration for the program manager?

To make sure that the information required by the stakeholders of the program is being made available to them in time, and in the format and medium that they prefer to receive it.

There should be a well-defined set of information gathering tools and templates so that management and consolidation of information becomes easier.

To keep track of cultural sensitivities and variations while making communication plans.

All communication going out of the program should be reviewed and vetted by the program manager or the program office.

A

Answer: a) The program manager needs to make sure that the information needs of the stakeholders are met. B and C contribute towards this larger objective. D is actually incorrect because the intent should not be to stifle communication or set up roadblocks in the flow of information.

151
Q
  1. A change request has been received by a project manager that seems to be in line with the objectives of the program. It will cause a delay in the project’s delivery and require additional funding from the organization. Who can take a decision about this change?

Program Governance Board

Program Manager

Project Manager

Program Sponsor, Program Manager, and Project Manager

A

Answer: a) Since it has an impact on funding requirements and time lines, this decision needs to go to the Program Governance Board.

152
Q
  1. A program has 6 projects and the projects are up against a tight deadline. The program manager wants to initiate a 7th project that will produce reusable parts that will help reduce time and cost on the 6 projects. The program manager has appointed a project manager, who is demanding a project charter before she can begin. How should the program manager respond in this situation?

Since this is an internal efficiency improvement project, it does not need a charter

Work with the project manager to produce a charter and seek approval for it

Forward the request to the program board and await the charter issuance

Start work and continue to push for the charter

A

Answer: b) The request for a charter is valid. The charter formally establishes the need for a project and commits organizational resources to it. Therefore, the program manager must work with the project manager to produce and seek approval for the charter.

153
Q
  1. A program has a number of projects with a lot of interdependencies. One of the senior technical architects in a project made a change to the specifications of one of the deliverables. The other projects are dependent on the original specifications and now need to rework. Who is responsible to solve this problem?

The program board and program sponsor along with the program manager

The program manager, concerned project managers and technical experts

The program manager and the concerned project managers

The project manager who approved the change to the specifications

A

Answer: b) The change is technical in nature, so it needs technical expertise. It also needs the project and program managers to analyze the impact. Therefore B represents the best set of people to solve this problem

154
Q
  1. Which of the following happens during the closure formalities of a program, but not necessarily during the closure of a project?

Formal acceptance

Provision for sustenance of benefits

Release of resources

Closing the associated contracts

A

Answer: b) Programs create strategic benefits for the organization and the responsibility for the long term sustenance of the benefits lies with the program. This is less true in case of projects. All other options are valid for both.

155
Q
  1. What is the main role of the Functional Manager in a program?

To manage the project when the Project Manager isn’t available

To manage the Project Managers

To define business processes

To control resources

A

Answer: d) The functional managers control the resources and provide functional expertise.

156
Q
  1. How does stakeholder management in projects differ from programs?

Projects work at a minute level and will have larger number of stakeholders; Programs need to manage relatively fewer stakeholders.

The program manager will need to be in touch with stakeholders throughout the program; the project managers will not have frequent contact.

When a project is part of a program, the project managers may not be involved in stakeholder management as it will be performed at program level.

Program manager will focus on program level stakeholders whereas the project managers will focus on project level stakeholders and there will be some areas of overlap.

A

Answer: d) The statement given in option D makes more sense. There is no thumb rule about number of stakeholders (A) and it is not true that frequency of stakeholders in projects is lower (B). It is also untrue that the projects will delegate the stakeholder management to programs (C).

157
Q
  1. A project is part of a larger program. During the planning activities, the project manager complains that the work of the project is research-oriented and cannot be estimated or planned for in the beginning. What should the program manager do in this case?

Proceed with the planning for the rest of the program without taking this project into consideration.

Ask the project manager to submit a coarse estimate and use rolling wave planning.

Coach the project manager so that she can make a commitment to a plan even in uncertain environments.

Ask the project manager to use bottom-up estimation to improve the confidence level in the estimates.

A

Answer: b) In an environment where there is a great degree of uncertainty, it is good to use a rolling wave planning approach. This approach allows team members to plan as much as possible. While executing that part of the plan, as they continue to refine their plans as they learn more about the work. Option A is not workable, as the program manager cannot ignore a project while preparing the overall plan. Bottom-up estimates may not be possible where there are too many uncertainties about the work. Hence, the program manager can ask the project manager to submit a coarse estimate and use rolling wave planning.

158
Q
  1. A product created by a project team within a program is about to transition into operations. During the training and enablement of the operational team, the operations manager suggests that a little expenditure on marketing would greatly increase the potential revenues from the new product. How should the program manager handle this suggestion?

Discuss the proposal with the project manager and the project team and accordingly decide.

Ask the operations manager to fund the marketing campaign from operational budget.

Log this into the risk register as an opportunity, but focus attention on smooth transition that is higher priority.

Treat this as a potential change request and based on merit, recommend inclusion of a marketing campaign to the program board.

A

Answer: d) The suggestion is in line with the intended benefits of the program and must be considered. Making provisions for the transition and sustenance of the benefits is indeed a part of the program’s responsibility.

159
Q
  1. A program is on extremely tight deadlines. The sponsor wants the program manager to work on ensuring that all the critical path activities should complete on time. How should the program manager respond?

The critical path is a project level concept and does not apply to programs

Work with the project managers to identify the critical path for the program

Inform the sponsor about the activities that need to be crashed or fast-tracked

Ask the project managers to identify the critical paths on their projects

A

Answer: b) A is an incorrect statement. Critical path can be determined for a program as well as a project if you know the activities and interdependencies. For this, the program manager will need to work with the project managers (option B). C is a presumptive statement the sponsor has not asked for time lines to be compressed. Statement D makes sense, but knowing the project’s critical paths does not necessarily help the program manager as several projects may be happening in parallel and the program manager really needs to understand the dependencies between the projects.

160
Q
  1. A program manager is conducting a lessons learned meeting for the overall program. Which is the best set of attendees for this meeting?

Selected team members, project managers, program manager, program sponsor

All team members, project managers, program manager, program sponsor

Selected team members, project managers, a neutral facilitator, program board

Program manager, project managers, PMO representative, selected stakeholders

Explanations:

A

Answer: d) D represents a good choice because it covers a balanced set of representatives. Apart from the program and project managers, selected stakeholders (including team members) can provide insights into what went well and what could be better, The PMO representative can function as a neutral facilitator as well as provide guidance with regard to what kind of information may be useful to capture. The other options are missing one or more of these elements. For example, A is missing a neutral facilitator, B misses the point by asking ALL team members to be present, and C is missing stakeholders who may not be team members

161
Q
  1. A project within a program has identified an opportunity that will help realize a $1 million early completion bonus. The program has some spare resources that can be deployed to make early completion a reality. What risk response strategy is being deployed here?

Exploit

Workaround

Avoid

Transfer

A

Answer: a) The program is helping the project realize an opportunity. The way it is going about is to remove the uncertainty of early completion by deploying additional resources from the program pool. Hence, this is an example of Exploit risk response strategy.

162
Q
  1. There are various electronic components being developed for a pathological laboratory in a hospital. These are developed by different projects and integrated into a central information repository through a program. Which of the following should be a part of the program level quality plan?

Calibration and threshold tests for the devices

Tests that validate equipment performing under different temperature and humidity levels

Tests that validate integration of equipment with the central data store

Boundary condition tests

A

Answer: c) A, B, and D are the tests that should be part of the project level quality plan. C addresses integrations and is more likely to be part of the program level quality plan.

163
Q
  1. A program manager and the project managers working on the program are trying to come up with the contingency reserve requirements. However, the job is made difficult by the numerous parameters which can change and the wide probability distributions associated with each. Which of the following tools will be most useful in determine the overall risk level and hence the reserve requirements for the projects and the program?

Decision tree

Expected Monetary Value

Probability Impact Matrix

Monte Carlo simulation

A

Answer: d) Monte Carlo simulation allows you to forecast the variation in target values based on a mathematical model and probability distributions, which seems to be available with the program team.

164
Q
  1. A program has been initiated by a telecom company to launch 4G telecom services. There are multiple components to this program with complex interlinkages. The program manager has completed writing a Program Scope Management Plan. How can this plan be used by the project managers?

To derive their project’s scope statement

To understand the Program WBS and the Project level WBS

To determine how the scope of the overall program will be managed

To validate the scope of individual projects and the overall program

A

Answer: c) The program scope management plan does not contain the actual scope of the program; rather it explains how the scope of the overall program will be managed. Hence it cannot be used for any other purpose than C.

165
Q
  1. A well-established retail company in clothing products has issued the charter for a program to increase Sales by 100% in the next 3 years. The program manager is at a loss to figure out how to meet these requirements. Where can she get guidance about possible means?

Ask for data about current sales and the competitive environment, focusing on what is holding back additional sales.

Perform a SWOT analysis of the company to understand what strengths can be leveraged by the company to realize the opportunities.

Explore new markets especially in countries with emerging economies and try to establish joint ventures in those countries.

Talk to the Marketing about what kind of a campaign will be needed to capture a bigger share of the market.

Explanations:

A

Answer: b) For an established company in a commodity (clothing) market, 100% growth in 3 years is an ambitious target by any yardstick. All the answers have some merit and may have to be explored. However, the program manager should start with a SWOT analysis to understand what opportunities can be identified and how the organization can be positioned to take advantage of them.

166
Q
  1. After completing the planning processes for the program and the components, the program manager would like to baseline the plans. What does the baseline program management plan represent?

Baseline represents the bare minimum expectations that the stakeholders can have from the program and its components. The program should strive to deliver more than the baseline.

Baseline tells the program manager the correlation between the work of the components and the desired benefits.

Baseline represents the agreement between the program and its stakeholders about what the program will deliver.

The baseline’s main purpose is to prevent changes to the scope of the program and its projects.

A

Answer: c) C is the most correct statement. Option A is partly correct, wherein it talks about expectation management. But it errs while stating that the program should strive to deliver more which would amount to gold plating. Option B is incorrect as the baseline does not correlate the components with the benefits. The baseline does assist in performing change management more systematically, but the idea is not to PREVENT changes but to MANAGE them.

167
Q
  1. How is program level risk management different from project level risk management?

Risks are managed primarily at the project level only escalated risks are managed by the program.

Program level risk management does not replace project level risk management; Program manager focuses more on risks impacting overall program.

Risk identification is best done at the project done, whereas response planning can be done at the program level.

In the interest of efficiency, it is best to maintain a single risk register for the overall program, with input from all the projects including time allocation, cost, and resources needed to established responses.

A

Answer: b) B is the best statement. Risk management is required both at project as well as program levels. The focus is different for both

168
Q
  1. Due to the funding constraints, a program manager needs to manage the utilization of allocated budgets by the projects very closely. Which reports would be most helpful for the program manager?

Milestone based reporting

Trend and Forecast reporting

Earned value reportsProject level Scurves

A

Explanations:Answer: c) The earned value method measures the utilization of budget against the actual work done and provides a holistic view to the program manager. These reports will be most helpful for the program manager to keep tabs on the budget utilization and progress.

169
Q
  1. A relief and rehabilitation program funded by international lending agencies and staffed by UNESCO volunteers is being managed by volunteer program managers from PMI and executed in sub-Saharan Africa, which has been hit by several years of drought. What is the role of governmental agencies in this program?

They are the executive sponsors of the program

They are the performing organization

They establish constraints and boundaries for the program

They provide procedures and policies for effective governance of the program

A

Answer: c) The government is not providing resources, hence they are not sponsors. The teams also do not come from the government, so they are not the performing organizations. The program management is from PMI volunteers, so government does not provide any procedures and policies for program governance. Hence the best option seems to be that they will establish the constraints and boundaries within which the program can carry out its work.

170
Q
  1. A rise in the cost of raw materials has caused a significant impact to many projects in a program. What risk response strategy can be adopted at the program level to manage this risk?

The project managers should handle this risk by building contingency reserves

The program manager should replan the whole program and file a revised budget proposal

The program manager should explore possibilities of locking in prices by entering into forward contracts

Get a forecast from economists about the future movement of prices

A

Answer: c) Option C represents the most proactive strategy that addresses the risk. Option D is merely gathering information which may be needed, but is not a risk response strategy in itself. Option B is also not a risk response strategy, but a wholesale replanning exercise. Option A is being reactive and leaving the onus on the project managers, which may not be appropriate.