1
Q

A program has a budget at completion of $1,250,000 and has already spent $425,000. The program is running late due to some vendor delays; the program is only 30 percent complete though it was scheduled to be 45 percent at this time. Based on this information how much more money will this program need to finish?

A. $978,445
B. $919,325
C. $991,667
D. $987,544

A

C $991,967

First, You need to calculate EAC = BAC/CPI. Then use the formula to calculate ETC = EAC - AC

BAC 1,250,000
EV (BAC * 0.03) 375000
AC 425000
CPI (EV/AC) 0.882352941
EAC = AC + (BAC – EV) 1,300,000
ETC = (BAC – EV) / CPI 991,667 (Answer C)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

You are the program manager for the BHN Program. Your program has 122 stakeholders that you’ll need to plan to communicate with. Considering the size of the program how many communication channels do you have in this program?

A

A. 244
B. 122
C. 14,884
D. 7,381

Number of potential communication channels = n x (n-1)/2
122 X (122-1)/2 = 7,381

How well did you know this?