Official concrete and masonry study guide Flashcards
What Subpart is concrete and masonry under?
Subpart Q 1926.700 – 1926.706
Failure to protect employees from impalement – rebar not capped or covered.
(1926.701(b))
Failure to establish a limited access zone (LAZ) to limit the number of workers in the danger zone where a masonry wall is under construction.
(1926.706(a)(1))
Failure to brace unsupported section of masonry wall over 8 feet in height.
(1926.706(b))
Failure to have drawings or plans at the jobsite to indicate jack layout and formwork placement.
(1926.703(a)(2))
Mushroom Cap
Ineffective
Square Cap with Reinforced
Effective
For Post Tensioning work, the following precautions have to be followed:
- Access shall be limited behind jack to those performing the work
- Signs & barricades are required to limit access
Concrete Placing by Crane and Bucket
- Employees are not allowed to work under concrete buckets being lowered or elevated into position.
- As much as practical, buckets should be routed to minimize the number of employees exposed to overhead buckets.
Concrete mixers with capacity greater than ___ must have mechanical device to clear skip of materials.
1 cu. yd.
Guardrails should be on each side of ___.
skip
Compressed air hoses on concrete pumping systems must have _____.
fail-safe connectors
Masonry saws must have _________.
Semicircular guard enclosure
Concrete buggy handles cannot extend ______.
past wheels on either side
Concrete pump hose must have ______ to prevent separation under load.
connectors
Concrete buckets with hydraulic release must have a device to prevent ______.
accidental dumping
Power concrete trowels must have a ____.
dead man switch
Bull float handles must ______ if electrical contact is possible.
non-conductive
Tremies must be secured with _______.
wire rope or equivalent
_______ required for work on equipment used for concrete & masonry.
Lockout/tagout
When dealing with cast-in place concrete,____ must be designed, fabricated, erected, supported, braced and maintained so that it will be capable of supporting without failure all vertical and lateral loads.
Formwork
When dealing with cast-in place concrete, Drawings or plans and any revisions for_______. must be available at the jobsite.
jack layout, formwork, scaffolding, and shoring equipment
April, 1978 ___workers killed in the collapse of scaffolding used to pour concrete for a cooling tower under construction. ___ workers fell more than ___ feet and six were crushed to death on the ground.
51, 45, 150
____to be inspected prior to erection, before , after, & during, concrete placement
shoring