Notifiable work Flashcards

1
Q

Name the organisation that must be notified of this.

A

WorkSafe New Zealand

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

State how long before work commences a notification form must be received by the
organisation in

A

At least 24 hours.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Give a situation where notifiable work may be performed prior to sending the notification form.

A

The blockage or breakdown of any drain or sewer.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

List FIVE types of construction work that are defined as notifiable work.

A
  • Work where workers could fall 5 m or more
  • Scaffolds from which a person could fall 5 m or more
  • Excavation which is more than 1.5 m deep
  • Explosives are used or stored
  • Lifts of half a tonne (500 kg) or more
  • Working using compressed air to breath
How well did you know this?
1
Not at all
2
3
4
5
Perfectly