NAVAIR 13-1-6.1-1 Life Rafts Flashcards

1
Q

What is covered in the NAVAIR 13-1-6.1-1 chapter 4?

A

The LR-1, a one man life raft assembly

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is covered in the NAVAIR 13-1-6.1-1 chapter 6?

A

The LRU-18/U, a one man life raft assembly

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is covered in the NAVAIR 13-1-6.1-1 chapter 9?

A

The LRU-13/A, seven man life raft assembly

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the LR-1 life raft constructed of?

A

Polychloroprene coated cloth

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the colors inside and outside of the weathershield in the LR-1?

A

The weathershield is nonspecular sea blue outside and bright red on the inside

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What size and type of thread is used to safety tie the LR-1 ripcord pins?

A

E thread single

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

LR-1 measure time of inflation; liferaft shall inflate to designed shape without evidence of restriction in less than______?

A

One minute

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

How many pounds you use for the cable proof load test?

A

50 pounds

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What PSIG do you inflate the LR-1 for visual test?

A

1.0 PSIG

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

The LR-1 weight of CO2 is 0.50 lbs plus or minus what?

A

Plus or minus 0.01 pounds

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

LR-1 leak test fill to 2.0 psig, wait 15 minutes record temp, barometric pressure, and allow to remain undisturbed for how long?

A

4 hours

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

After an minimum of four hours test pressure shall not decrease to let than?

A

1.6 psig from a maximum test pressure of 2.0 psig

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

LR-1. Tighten coupling nut to life raft inlet valve to a torque value of?

A

85 plus or minus 5 lbs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

LR-1 prepare solution of detergent (MIL-D-16791) consisting of 1/4 to 1/2 once of detergent per _____?

A

Gallon of water

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

LR-1. Toluene shall be the primary solvent used in the fabrication or repaired of this assembly. ______ may be used if toluene is not available.

A

MEK

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

One patch is completed, allow adhesive to cure a minimum _____ hours.

A

48 hours

17
Q

LRU-13/A. Special inspection shall be performed every?

A

30 days

18
Q

LRU-13/A. what radio is installed in the LRU-13/A?

A

AN/URT-33A

19
Q

LRU-18/U. What material is the LRU-18/U made of?

A

Heat-sealable, polyurethene-coated nylon cloth

20
Q

What is the configuration of the LRU-18/U?

A

It has two separate cells, each comprised of a series of tubes. The upper second, third and fourth tubes are inflated with carbon dioxide and the remaining tubes are inflated orally.

21
Q

What is the application of the LRU-18/U?

A

Mandatory for use by all authorized helicopter (Helicopter backpacks) and E-2C aircraft equipped with A/P22P-11 Crew backpack during overwater flights.

22
Q

What is the ideal temperature to perform maintenance on the LRU-18/U?

A

68 degrees F (20’ C)

23
Q

During the beaded inflation handle pull test, what is the the force to which fasteners should snap?

A

25 lbs

24
Q

During the leakage test on the LRU-18/U, to how many PSIGs should the CO2 cell be inflated and how many the Oral cell?

A

CO2 cell shall be inflated to 2.0 and minimum pressure to lose after 4 hours is to 1.6.
Oral cell shall be inflated to 1.0 and lose no more than to 0.6 after 4 hours.

25
Q

When reinstalling the inflation assembly with a new valve gasket, what is the torque value of the nut onto valve stem?

A

8 plus or minus 1 in-lb.

26
Q

When patching the LRU-18/U life rafts, how much larger than the damaged side should the patch be?

A

One inch larger on all sides

27
Q

How to secure the tether line to the inflation assembly of the LRU-18/U?

A

One loop with a lark’s head knot large enough to pass over the entire CO2 assembly, (between anti-chafing disk and life raft). Tighten the knot around the manifold stem. Tack knot with two turns of waxed, size 6 cord, single. Tie with ends of threads with a surgeon’s knot, followed by square knot.