Module Four - Managing Change Processes Flashcards
What is PVE
Peach Academy’s Process Value Enhancement
What are the 4 main components of Major Project Life Cycles and Deliverables (PVE)
- Request for Change (RFC) 2. Product Development Document (PDD) 3. Quality Plan (QP) 4. Quality Reviews (QR)
What is QMS and what does it do
Quality Management System - Maintains procedures and templates to define quality
What is TQM
Total Quality Management
What are the 6 stages of the PVE Life cycle
- Initiation 2. Analysis and Process Improvement 3. Design 4. Code Building 5. Testing 6. Going Live
What are the 4 stages of Initiation
- Request for change (RFC) 2. Define and agree TOR (Terms of reference) and FS (Feasibility Study) 3. PDD (Project Planning and Development Document) 4. QP (Quality Plan)
What is the stage in Analysis and Process Improvement
FR - Functional Requirements
What are the 3 stages of Design
- TS - Technical Specification 2. Parallel Activities 3. SDS (System Design Specification)
What are the 2 stages of code building
- PRS (Program Specification) 2. Programming and unit testing
What are the 5 stages of testing
- STP (Complete system test plan) 2. System test and performance test 3. CAT (Complete Customer Acceptance Test 4. Pre Customer Acceptance Test Deliverables Review 5. Initial Training and Customer Acceptance Testing
What are the three stages of Go Live
- Further Training, handover and installation 2. “Warranty run in” period 3. PIR (Post implementation review)
What are the 6 stages of change project management delivery
- Identify Potential Change 2. Analyse Change Request 3. Evaluate Proposed Change 4. Plan for change. 5. Implement the change 6. Review and close change project
What are the 3 ways of Identifying potential change
- Requiring new functionality 2. Encounter Problem 3. Requested from Customer
What are the 2 steps to analysing the change request
- Determine technical/Business feasibility 2. Determine costs and benefits
What are the 2 steps to planning for a change
- Analyse the change impact 2. Create a project plan and evaluate