Module 4 - Section C - Material Planning Requirements Flashcards

1
Q

Material Requirements Planning (MRP)

A

-set of techniques that uses bill of material data, inventory data, and master production schedule to calculate requirements for material

-time phased –> makes recommendations to reschedule open orders when due dates and need dates are not in phase

time phased MRP begins with items listed on mPS and determines:
1. quantity of all components and material are required
2. date that components/material are required

-explode bill of material, adjusting for inventory quantities on hand or on order, and offsetting net requirements by appropriate lead times

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Bill of Material (BOM)

A

-listing of all subassemblies, intermediates, parts, and raw materials that go into a parent assembly, showing quantity of each required to make an assembly

-used in conjunction with master production schedule to determine items for which purchase requisitions and production orders must be released

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Item Master Record

A

-typically contains identifying and descriptive data and control values (lead times, lot sizes) and may contain data on inventory status, requirements, planned orders, and costs

-item records are linked by bill-of-material (or product structure) records thus defining bill of material

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Parent Item

A

-item produced from one or more components

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Single-Level Bill of Material

A

-display of components that are directly used in a parent item

-shows only the relationships one level down

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Multilevel bill of material

A

-display of all components directly or indirectly used in a parent, together with quantity required of each component

-if a component is a subassembly

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Indented Bill of Material

A

-form of multilevel bill of material

-exhibits highest-level parents closest to left margin and all components going into these parents are shown indented toward the right

-all subsequent levels of components are indented farther to the right

-if a component is used in more than one parent within a given product structure it will appear more than once under every subassembly in which it is used

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Summarized Bill of Material

A

-form of multilevel bill of material that lists all parts and their quantities required in a given product structure

-unlike indented bill of material, it does not list level of manufacture and lists a component only once for the total quantity used

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Phantom Bill of Material

A

-bill of material coding and structural technique used primarily for transient (non-stocked) subassemblies

-for transient item lead time is set to zero and order quantity to lot-for-lot

-represents an item that is physically built but rarely stocked before being used in the next step or level of manufacturing

-used to simplify complex production orders by reducing number of levels in the BOM

-phantom subassembly is not stocked because it does not exist as an actual component (may be only a drawing of diff. parts that will be used at a igher assembly level)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Parts Requisition

A

authorization that identifies the item and quantity required to be withdrawn from an inventory

example: an order may be release to factory floor but not picked from storage for several days; during that time the item is still part of inventory balance but it has been allocated and is not available; when pick transaction is processed, the inventory system will reduce the item’s on-hand and allocated balances accordingly

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Firm Planned Order

A

-planned order that can be frozen in quantity and time

-computer is not allowed to change it automatically –> responsibility of planner in charge of item being planned

-technique can aid planners working with MRP systems to respond to material and capacity problems by firming up selected planned orders

-normal method of stating the MPS

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Action Message

A

-output of a system that identifies the need for, and type of action to be taken to correct, a current or potential problem

-examples: release order, reschedule in, reschedule out, and cancel

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Rescheduling

A

-process of changing order or operation due dates, usually as a result of their being out of a phase with production or customer commitments

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Bill-of-Material Explosion

A

-process of determining component identities, quantities per assembly and other parent-component relationship data for a parent item

-explosion may be single level, idented or summarized

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Requirements Explosion

A

-process of calculating the demand for the components of a parent item by multiplying the parent item requirements by the component usage quantity specified in the BOM

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Explode

A

-to perform a BOM explosion