Module 2: Cost And Economic Analysis Flashcards
The Defense Acquisition System is the management process that guides DoD acquisition programs and is basically the process by which programmatic risk is managed. What are the three programmatic risks that must be successfully managed?
Cost, Schedule, and Performance Risks
- What are the appropriations that may be caused to fund an acquisition program?
RDT&E, Procurement, O&M, MILCON, and MILPERS
- What is the term used to describe dollars shown in the life cycle cost estimate wherein the effects of inflations are not considered?
Base year dollars or Constant year dollars
- What is the term used to describe dollars used for programming and budgeting purposes wherein the effects of inflation are considered?
Then-year dollars or current year dollars
- What cost structure does MIL-STD-881C represent?
Work Breakdown Structure (WBS)
- Which cost estimating method is based on direct comparison with historical information of one similar system?
Analogy Method
- Which cost estimating method is known as a statistical method or top-down method?
Parametric Approach
- Which cost estimating method requires extensive knowledge of the product or process?
Engineering Approach
- What are the methods/steps in conducting the Delphi Technique?
Query Expert Opinions
Seek supporting rational or information from each expert
Summarize results
Gather second opinion
Continue iteration until consensus or near-consensus is reached
- What is the theory that as the quantity of output doubles, the man-hours required to produce the quantity decreases at a fixed rate?
Learning Curve Theory
- What is the name of the integrated management tool intended to relate contractor actual performance n a contract to the contractor’s planned cost and schedule that measures the work progress in objective terms and that states the value of the work completed in dollars?
Earned Value Management System (EVMS)
- What is the EVM-related term when there is a difference between budgeted cost of work performed (BCWP) and the actual cost of work performed (ACWP) on a cost reimbursable contract?
Cost Variance
- What is a systematic approach to the problem of choosing the best method of allocating scarce resources to achieve a given objective?
Economic Analysis
- Cost Savings, Cost Avoidance, and Productivity Improvements are examples of what type cost benefits?
Quantifiable Benefits
- In regards to measures of central tendency, what is a mean? A mode? A median?
Mean is the arithmetic average
Mode is the most frequent score in a distribution of scores
Median is the middle of arrayed values