Mock-2 Flashcards
Triangular distribution formula?
[Pessimistic estimate + Most likely estimate + Optimistic estimate]/3
Affinity diagram?
Organizes a large number of ideas into their natural relationships
Control charts?
Control chart is a simple yet powerful tool for evaluating the stability of a process or operation over time.
The Rule of seven?
The Rule of Seven as applied in Quality Management says that “A run of seven or more consecutive points in a control chart, either above the mean, or below the mean, or continuously increasing or decreasing, may indicate the process may be out-of-control”.
The purpose of Scope Management Plan?
Is how the scope will be will be defined, developed, monitored, controlled, and verified.
What are quality metrics?
The description of the attributes of the product or project. It also aims to measure the attributes defined by the project manager
What Is a WBS Dictionary?
Is where the details of the tasks, activities, and deliverables of the work breakdown structure are located.
What is a Project Scope Statement?
Is a document that defines all the elements of the project scope as well as assumptions, project requirements and acceptance criteria.
What Is Project Scope?
The project scope is the total amount of work that needs to be done to complete a project.
What Is a Project Charter?
A formal short document that states a project exists and provides project managers with written authority to begin work
What is Work Package?
Is the smallest deliverable in a project. Developed during the “Create WBS” planning / scope process, managed by one person.
What is Activity?
The work packages are decomposed into activities, which are the means to create a deliverable. An activity has an expected duration, consumes budget and/or resources.
What is parametric estimating?
Parametric estimating is a statistical and accuracy-based technique for calculating the time, cost, and resources. A unit rate is used and multiplied by the number of units.
What is an example of analogous estimating?
Uses information from similar projects to establish a cost or duration estimate based on the data available.
What are the 3 point estimating techniques?
Uses Optimistic (O), Most Likely (M), and Pessimistic (P) points.
1. Triangular distribution E = (o + m + p ) / 3
2. Beta (PERT) distribution E = (o + 4m + p ) / 6