MIS 578 Chapter 8: Scheduling Projects Flashcards

1
Q

Activity

A

“A distinct scheduled portion of work performed during the course of a project.”

The building blocks of a project schedule are activities. An activity is “a component of project scope work performed during the course of a project.”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

For activities to be useful as schedule building blocks, they should have the following characteristics:

A
  • Clear starting and ending points
  • Tangible output that can be verified
  • Scope small enough to understand and control without micromanaging
  • Resources, other costs, and schedule that can be estimated and controlled
  • A single person who can be held accountable for each activity (Often more than one person is required to complete the work; however, one person should be responsible.)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Activities should be listed in what format?

A

Verb-noun format, such as “prepare budget,” or “build frame.”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

7 processes of time management

A
  1. Plan schedule management—arranging how to develop, manage, execute, and control the project schedule
  2. Define activities—a project planning process that identifies and determines specific actions to develop and deliver the project outcomes, such as products, services, or results
  3. Sequence activities—determining the predecessor and successor relationships among the project activities
  4. Estimate activity durations—the process of approximating the number of work periods needed to complete individual activities with estimated resources
  5. Develop schedule—the process of analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule
  6. Control schedule—the process of regulating changes to the project schedule
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Method to display activities

A

AOA - Activity on Arrow
ADM - Activity diagramming method
AON - Activity on node - most common
PDM - Precedence diagramming method - most common

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

5 factors that may limit how fast a project can be completed

A

1) Logical order
2) Activity duration
3) Resource availability
4) Imposed dates
5) Cash flow

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Precedence Diagramming Method (PDM)

A

“a technique in which the scheduled activities are represented by nodes and are graphically linked by one or more logical relationships to show the sequence in which the activities are performed.”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Predecessor Activity

A

“an activity that logically comes before a dependent activity in a schedule.”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Successor Activity

A

“a dependent activity that logically comes after another activity in a schedule.”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Finish-to-Start (FS)

A

“a logical relationship in which a successor activity cannot start until a predecessor activity has finished.”

The most common type of logical dependency.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Lead

A

“the amount of time whereby a successor activity can be advanced with respect to a predecessor activity.”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Lag

A

“the amount of time whereby a successor activity is required to be delayed with respect to a predecessor activity.”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Duration

A

“the total number of work periods required to complete a schedule activity, usually expressed as workdays or workweeks.”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Critical Path

A

Critical path is the sequence of activities that have no float.

“the sequence of activities that represents the longest path through the project, which determines the shortest possible duration.”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Two methods to determine the critical path

A

1) Two-pass method

2) Enumeration method

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Forward pass

A

“a critical path method technique for calculating the early start and early finish dates by working forward through the schedule model from the project start.”

17
Q

Early Start date(ES)

A

“the earliest possible point in time on which uncompleted portions of a schedule activity can start, based upon the schedule network logic, the data date, and any schedule constraints.”

18
Q

Early finish date (EF)

A

“the earliest possible point in time on which uncompleted portions of a schedule activity can finish, based upon the schedule network logic, the data date, and any schedule constraints.”

19
Q

Late start date (LS)

A

“the latest possible point in time in which uncompleted portions of a schedule activity can start.”

20
Q

Late finish date (LF)

A

“the latest possible point in time when the uncompleted portions of a schedule activity can finish.”

21
Q

Float

A

Float = Late start (LS) - Early start (ES)

22
Q

Enumeration method

A

List (enumerate) all paths through the network. The path with the longest combined duration is the critical path.

23
Q

Monte Carlo Analysis

A

“a technique that computes, or iterates, the project cost or project schedule many times. . . to calculate a distribution of possible total projects costs or completion dates.”

24
Q

Baselining

A

Baselining is creating a “snapshot” of the project at the very beginning, so you can later status and input actual start, finish and durations. Allows for you to measure the performance of the project against a plan.

25
Q

Dependencies can be either mandatory or discretionary

A

Mandatory dependency - “a logical relationship between activities that that must happen—usually due to a physical or legal demand.”

Discretionary dependency - “a logical relationship between activities that is considered desirable, usually based upon experience or best practice.”

26
Q

Estimating activity duration

A

You can begin estimating activity durations once the activities have been defined and sequenced. Estimating activity durations is the process of approximating the number of work periods needed to complete individual activities with estimated resources.

27
Q

Free float

A

“the amount of time a schedule activity can be delayed without delaying the early start of immediately following schedule activities.”

28
Q

Gant Chart

A

A Gantt chart is a horizontal bar chart that shows each work activity on a separate line with the bar placed from the early start date to the early finish date for each activity on a timescale.